MILITARY SEALIFT COMMAND
N32205-16-R-4311
QUESTIONS AND ANSWERS #2
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
QUESTION #1:
SPECIFICATION ITEM NO.: 136
PARAGRAPH / SECTION NO: 2.1
TITLE: Peck and Hale Tie Down Points Installation at Unrep Station
We have been unable to identify the item listed as “Peck and Hale Dwg. No. 2122” on the Peck and Hale Website. Please identify what the part or piece is for purposes of cross referencing to a part number versus a drawing number?
ANSWER:
Peck and Hale Drawing Number 3484B will available via AMRDEC.
Tie Downs Data:
· Cover - PH2931-2B-PG
· Flush I.S.O. Socket - F273-1-OF
· Twistlock Stacker - F476-R-C
· D-ring - F483-3 - I.S.O
QUESTION #2:
SPECIFICATION ITEM NO.: 335
PARAGRAPH / SECTION NO: 2.0
TITLE: M-711 Light Fixture Conversion to LED (T-ALT 353)
References listed in paragraphs 2.8, 2.9 and 2.10 are not found in the file of references provided. Please identify from the references provided those that are listed in this work item?
If the references listed in this work item have not been provided, please provide them and extend the bid date by the number of days that the references have not been provided?
ANSWER:
Reference Documents will be available via ARMDEC.
QUESTION #3:
SPECIFICATION ITEM NO.: 502
PARAGRAPH / SECTION NO: 2.0
TITLE: Distiller Flow Meter Replacement (T-ALT 340)
References listed in paragraphs 2.1.1 and 2.1.2 are not found in the file of references provided. Please identify from the references provided those that are listed in this work item?
If the references listed in this work item have not been provided, please provide them and extend the bid date by the number of days that the references have not been provided?
ANSWER:
Reference Documents will be available via ARMDEC.
QUESTION #4:
SPECIFICATION ITEM NO.: 532
PARAGRAPH / SECTION NO: 2.0
TITLE: Firemain Cascade Orificial Restrictive Device (CORD) Repair
References listed in paragraphs 2.1 and 2.2 are not found in the file of references provided. Please identify from the references provided those that are listed in this work item?
If the references listed in this work item have not been provided, please provide them and extend the bid date by the number of days that the references have not been provided?
ANSWER:
Reference Documents will be available via ARMDEC.
QUESTION #5
SPECIFICATION ITEM NO.: 547
PARAGRAPH / SECTION NO: Various TITLE: Miscellaneous Piping and Steel Repairs
Paragraphs 3.2.1 and 7.1.1 state to assume 250 feet of pipe repairs that include firemain, main drainage etc. in sizes ranging from 1-1/2” to 10”. The range is quite dramatic. Please provide a more specific size to quantity ratio so that the bid price can be mores can be more realistic and based on closer assumptions? By example, 8” pipe is about 20 x the price of 1-1/2”.
Paragraph 7.1.4 b. states to “Make firemain piping repairs…No. 1 (12-inch). Where does 12” fall between 1-1/2” and 10”?
Please provide some guidance as to what type of material is to be assumed PVC, schedule 40 black iron, schedule 80 galvanized, schedule 40 stainless steel, copper nickel? By example, 1-1/2” copper nickel pipe is about 4 x the price as pipe in black iron.
ANSWER:
See amendment 0003 posted on FBO.
QUESTION #6
SPECIFICATION ITEM NO.: 553
PARAGRAPH / SECTION NO: 2.1
TITLE: Cargo Brine System Valve and Piping Modification (T-ALT 349)
Reference listed in paragraph 2.1 is not found in the file of references provided. Please identify from the references provided those that are listed in this work item?
If the references listed in this work item have not been provided, please provide them and extend the bid date by the number of days that the references have not been provided?
ANSWER:
Reference Documents will be available via ARMDEC.
QUESTION #7
SPECIFICATION ITEM NO.: 925
PARAGRAPH / SECTION NO: 2.1
TITLE: Bow Thruster Tunnel Protective Grating Bar Modification
Reference listed in paragraph 2.1 is not found in the file of references provided. Please identify from the references provided those that are listed in this work item?
If the references listed in this work item have not been provided, please provide them and extend the bid date by the number of days that the references have not been provided?
ANSWER:
Reference Documents will be available via ARMDEC.