REQUEST FOR SPECIFICATION CLARIFICATION
#0022
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: 922
PARAGRAPH / SECTION NO: 7.11.1 and 7.5.1 – 7.5.1.2
TITLE: BILGE ALARM INSTALLATION
QUESTION:
The specification directs the contractor to provide a GE Energy Technical representative to make modifications to MIMIC Screens and make all wire connections in the DAU Cabinets.
The contractor requested a quote from the GE Energy Technical representative and received the following response.
“Unfortunately, I cannot send a proposal to you for WI 922 at this time. The software and test procedure for this modification will take at least a few months to complete (so order for that must come well before yard period, direct from MSC), and then reviewed/approved by both MSC engineering and ABS (that usually takes another 4-6 weeks). MSC has not yet sent us a request for this modification, and so it’s unlikely we will have enough time available to complete development & receive mandatory approvals…….before installation would need to occur on T-AKE 4 (2nd week in June). I believe I previously spoke to the Port Engineer about this, but we have not seen the request from MSC.”
The contractor will be unable to provide a quote from GE Energy. Can MSC supply the name of a different source?
ANSWER:
Work Item Cancelled. See Amendment 0003.
ATTACHMENT J – 8