REQUEST FOR SPECIFICATION CLARIFICATION #0008
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: 907
PARAGRAPH / SECTION NO: 4.0
TITLE: Propeller Shaft Horizontal Proximity Probe Installation
QUESTION:
Materials listed in specification as GFM do not match the materials listed in J-4.
Please clarify
ANSWER:
Attachment J-4 GFM revised.