REQUEST FOR SPECIFICATION CLARIFICATION
#0020
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: 501 & 502
PARAGRAPH / SECTION NO: 5.9
TITLE: Aft AFFF Piping Sprinkling System
QUESTION:
After review of both AFFF Items, the material list on the J-4 GFM is for both work items to accomplish complete renewal of aft systems. Paragraph 5.9 in both items references drawing EUM-001-0-01 which has another material list.
Question: Should the material in dwg. EUM-001-0-01 be subtracted from the GFM list in the J-4?
Also paragraph 3.2 lists materials as (contractor furnish) but paragraph 4.2 lists CUNI piping as GFM and it is on the J-4 GFM list.
ANSWER:
All piping/fittings/flanges are intended to be GFM. During the start of this work, if the winning Shipyard finds any material missing, there will be an RFP generated for any missing piping.
ATTACHMENT J – 8