USNS Richard Byrd
Sol No. 32205-15-R-3000
ATTACHMENT J – 8
Elizabeth.waller@navy.mil
REQUEST FOR SPECIFICATION CLARIFICATION
#0001 12/23/14
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: N/A
PARAGRAPH / SECTION NO: Section F Delivery and Performance; Clause F-1
TITLE:
QUESTION:
Section F-1. It is anticipated that ship will arrive at Contractor’s yard on or about 04 May
2015. All work shall be completed in no more than 45 calendar days from actual start date designated by the Government at time of contract award.
Contractor would like to request an alternate start date of 18 May, 2015 to avoid a dry docking schedule conflict.
ANSWER:
The availability period has been changed to arrive at the contractor’s facility on or about 18 May 15. The POP is changed to 18 May 2015 to 01 July 2015.