N00033-13-R-7508-0003.doc

DOC document 42 KB Posted

Attached to
USNS SUPPLY (T-AOE 6) Maintenance and Repair Upgrade (MARUP)
Solicitation number
N00033-13-R-7508
Issued by

About this file

Amendment 0003

View the file

Other files

File Type Posted
QandA_-_N00033-13-R-7508_Q38-40_Sep_20.docx DOCX document
N00033-13-R-7508-0006.doc DOC document
AMEND0006_Work_Items.zip ZIP file
QandA_-_N00033-13-R-7508_Q18-37_Sep_19.docx DOCX document
N00033-13-R-7508-0005.doc DOC document
AMEND0005_J-4_GFM_LIST.pdf PDF
AMEND0005_Work_Items.zip ZIP file
AMEND0005_J-2_Contractor_Price_Breakdown.xls XLS spreadsheet
QandA_-_N00033-13-R-7508_Q10-17_Sep_12.docx DOCX document
AMEND0004_Work_Items.zip ZIP file
N00033-13-R-7508-0004.doc DOC document
AMEND0004_J-4_GFM_LIST.pdf PDF
AMEND0004_J-2_Contractor_Price_Breakdown.xls XLS spreadsheet
QandA_-_N00033-13-R-7508_Sep_09.docx DOCX document
QandA_-_N00033-13-R-7508_Aug_30.docx DOCX document
AMEND0003 0109_A_Potable Water Tank Vent Mod.docx DOCX document
AMEND0003 0551_A_RCC Vane Status - RCC-RRG LO Control and Monitoring RCC Fill and Drain Valves Including Piping Mods.doc DOC document
AMEND0003_J-3_NDA_for_Gov_Tech_Data.docx DOCX document
AMEND0003 0603_A_ Flight Deck Safety Nets Repair.doc DOC document
AMEND0003 - USNS SUPPLY 2014 MARUP WORK PACKAGE INDEX.docx DOCX document
AMEND0002_J-4_GFM_LIST.pdf PDF
AMEND0002_Work_Items.zip ZIP file
N00033-13-R-7508-0002.pdf PDF
AMEND0002_J-6_SUPPLY_MARUP_CDRL.docx DOCX document
AMEND0002_J-2_Contractor_Price_Breakdown.xls XLS spreadsheet
N00033-13-R-7508-0001.pdf PDF
N00033-13-R-7508.pdf PDF
N00033-13-R-7508_J-Attachments.zip ZIP file
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003

The purpose of this amendment is as follows:

1. Revise Subsection F-2 to read as follows:

“As set forth in Work Item No. 010, Furnish Offices of On-site Management Team (OMT) and Work Item No. 012, Telephone Services, the OMT office and telephone services shall be functional seven (7) days prior to ship’s arrival and continue for ten (10) days after ship’s departure from the yard.”

2. Revise Attachment J-1, Work Item index to reflect the below Work Item changes.

3. Revise Work Item 551 by deleting the last sentence of Paragraph 1.1.

4. Revise Work Item 109 by deleting Paragraph 7.3.2.d

5. Revise Work Item 603 to read as follows:

“7.8.5 For those areas not accessible to abrasive blasting, contractor may accomplish a SSPC-SP-11 surface preparation.”

“7.8.7 (CHECKPOINT) After surface preparation a joint inspection by shipyard and MSCREP shall be accomplished. The prepared frames will be inspected for cracks, corrosion and other deteriorated conditions. Frames which require replacement or repair will have replacement or repair work completed and be re-blasted prior to coating.

a. Following joint inspection contractor shall submit an “As-Found” Condition report with repair recommendations. The report shall clearly indicate any work outside scope listed below.”

6. Revise Attachment J-3, Paragraphs (5) and (6) to read as follows:

(5) Not copy, release, reproduce, duplicate, transmit, distribute, or otherwise make the Data in any form whatsoever, including in the form of electronic documents posted to a website, available to persons other than those authorized representatives listed herein below.

(6) Assure that disclosure of Data to any third party or subcontractor is subject to a Non-Disclosure Agreement, similar in all material respects to this one.

7. All other terms and conditions remain unchanged.

SECTION F - DELIVERIES OR PERFORMANCE

The following have been modified:

F-1 EFFECTIVE DATE OF CONTRACT

The effective date of this contract is the date of award by the Government. The anticipated award date is 09 December 2013.

F-2 SHIP AVAILABILITY PERIOD

It is anticipated that the ship will arrive at the Contractor’s yard on or about 15 January 2014. All work shall be completed in no more than 270 calendar days from actual start date designated by the Government at time of contract award. As set forth in Work Item No. 010, Furnish Offices of On-site Management Team (OMT) and Work Item No. 012, Telephone Services, the OMT office and telephone services shall be functional seven (7)AMEND0003 days prior to ship’s arrival and continue for ten (10) days after ship’s departure from the yard.

F-3 PLACE OF PERFORMANCE

The place of performance for this contract shall be the contractor’s facility.

F-4 DELIVERY OF DATA

Place and time of delivery of data shall be specified on the DD 1423 (Contract Data Requirements List) which is an attachment to this contract, unless delivery is deferred at the Government's Option by written order of the Contracting Officer.

F-5 PLACE OF DELIVERY

Originals of all correspondence requiring signature, such as copies of invoices, monthly status report, etc. shall be delivered to the Contracting Officer’s Representative (COR) at the following address: To be provided at the time of award.

Deliverables may be electronically submitted to: to be provided at time of award

F-6 WRITTEN DELIVERABLES

The contractor shall review, approve, and sign all draft and final documents before being delivered to the Government.

F-7 FORMAT FOR DELIVERABLES

All documentation deliverables shall be prepared using Microsoft Word, Excel, Project, CAD or Adobe Acrobat.

(End of Summary of Changes)