USS CHOSIN (CG 65) Bidder's Questions answered
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QA2
| USS CHOSIN (CG 65) MODPRD Pre-Proposal Information (PPI) Questions | ||||
| Drawing | ||||
| GFM | Solicitation #: | N00024-19-R-4447 | Phone | |
| RLAR | TPPC | TPPC-CG65-SWRMC19-CN01 | Justin Lessel, Contract Specialist, justin.d.lessel@navy.mil | 202-781-4064 |
| Martha Bello, Contracting Officer, martha.bello@navy.mil | 202-781-3864 | |||
| The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation. | ||||
| To request references, drawings, RLARs, and Erratas being provided under this Solicitation Question & Answer Set, |
please contact Justin Lessel, justin.d.lessel@navy.mil, and Martha Bello, martha.bello@navy.mil.
| Work Item No. | Document Number/Title | Question | Government Response |
| 634-21-003 | Paragraph 3.6 states; "Accomplish a visual inspection, concurrently with the SUPERVISOR, Aeronautical Shipboard Installation Representative (ASIR), and a Level 1 Shipboard Corrosion Assessor, of the equipment listed in 1.3.7, 1.3.8, and the equipment removed and disassembled in 3.3 and 3.5 for buckling/deformation, pitting, thinning, cracks, fractures, cracked welds, scale, holes, deflections/distortions, general condition, wear, defects and deterioration using 2.2 through 2.17 for accept or reject criteria".........etc. |
Contractor question #1; there is no paragraphs 1.3.7 & 1.3.8 listed in this spec, also, there is no equipment removed or disassembled in paragraphs 3.3 & 3.5.
Paragraph 3.7 states; "Remove existing and install new a total of 40 each posts for 3/4 inch bolts, 40 each posts for one inch bolts, 23 each 2 inch wide blocks for 3/4 inch bolts, and 22 each 2.6 inch wide blocks for one inch bolts at location listed in 1.2.3 in accordance with the requirements of 2.16. Countersink, plug weld, drill out, ream, and tap 65 each bolt holes in way of broken/deteriorated and 65 each cover plate mounting holes found deteriorated, as directed by the SUPERVISOR. Remove existing and install new up".........etc.
Contractor question #2; There is no paragraph 1.2.3 in this spec & reference 2.16 is listed as the "Deck Covering Schedule" which is not applicable for the accomplishment of this paragraph.
Contractor question #3; The spec continuously refers to the RAST System (which is located at the Flight Deck on the 02 Level) but the locations of work listed is the 01 Level & Main Deck.
The number of discrepancies are more numerous than what has been identified in question #1, #2 and #3. The way the spec is currently written the contractor is unable to determine what the customer wants and therefore is unbiddable.
| Contractor suggest reviewing this item in its entirety and adjusting all discrepancies or deleting this item and RCC the work after award. Please advise. | This WI has been updated via Errata 1. See Amendment 0004 for revisions. | ||
| 074-11-001 | Paragraph 3.3 states; "Submit one legible copy, in hard copy or approved transferrable media, of a bi-weekly report listing results of the requirements of 3.1.1 through 3.2.3.1 to the SUPERVISOR"……. |
QUESTION; There is no paragraph 3.2.3.1 in this work spec.
| Please review & advise. | This Work Item has been updated in Errata 1 to stated paragraph 3.2.3 vice 3.2.3.1. See Amendment 0004 for revisions. | |||
| 261-11-004 | Fuel Oil Suction Cutout Valve and Remote Operator; replace & repair | Paragraph 3.4.1 for 009-90 |
| Please identify the Qualified Technical Representative with contact information | 009-90 is not required. This Work Item has been updated in Errata 1. See Amendment 0004 for revisions. | ||||
| 671-90-001 | SHIPALT CG47-80917K, ABANDON SHIP LOCKER MOD TO STOWAGE ; ACCOMPLISH | Please provide Ref.2.9 (RLAR, 80917/CG65/P312) | Ref.2.9 (RLAR, 80917/CG65/P312) has been provided via Amendment 0002. | ||
| 588-21-004 | Paragraph 3.1 states; "Accomplish the requirements of 009-90 of 2.1 for the services of an on-site Authorized Technical Representative to provide assistance, parts, special tools, guidance for removal, disassembly, inspection, repair, assembly, testing and adjustment of the RAST system and sub-component assembly listed in 1.3.1 and located in 1.2." |
| There is no contact information of the authorized Technical Representative, please provide. | 009-90 is not required. This Work Item has been updated in Errata 1. See Amendment 0004 for revisions. | |||
| 529-11-002 | Secondary Drainage System Repair and Restore; accomplish | ON PARAGRAPH 3.4 Accomplish the requirements of 009-90 of 2.1. |
| Please provide the p.o.c for the qualified on-site Technical Representative. | 009-90 is not required. This Work Item has been updated in Errata 1. See Amendment 0004 for revisions. | |||
| N/A | RFP-N0002419R4447 Page 84 of 163 | Contractor acknowledges contents of Attachment-J-3 Execution Milestones, which contains the major milestones planned for the MODPRD. |
Contractor notes that the J-3 does not currently include the "Planning Events Readiness List" (PERL) that provided to show each work item's Milestone assignment for Work Certification. This information is pertinent to ensuring that work item assignments are appropriately assigned and correlate to Government expectations.
| Can the Government provide the PERL for USS Cape St. George MODPRD? | Amendment 0003 updated Attachment J-3 Milestones to include PERL. | |||
| VARIOUS | CGMOD, Critical Path Equipment/Cable Turnover, Power-up and Test Requirement REV A 15SEP17 | Various items require work be accomplished using "CGMOD, Critical Path Equipment/Cable Turnover, Power-up and Test Requirement" document. |
The document provided (CGMOD, Critical Path Equipment/Cable Turnover, Power-up and Test Requirement REV A 15SEP17, located in CD) is for CG-63.
Please provide the document for CG-65
| Amendment 0003 updated Attachment J-3 Milestones to include additional documentation. | |||
| N/A | RFP-N0002419R4447 Page 84 of 163 | Contractor acknowledges contents of Attachment-J-3 Execution Milestones, which contains the major milestones planned for the MODPRD. |
Contractor notes that the J-3 does not currently include the "Planning Events Readiness List" (PERL) that provided to show each work item's Milestone assignment for Work Certification. This information is pertinent to ensuring that work item assignments are appropriately assigned and correlate to Government expectations.
| Can the Government provide the PERL for USSS Chosin MODPRD? | Amendment 0003 updated Attachment J-3 Milestones to include PERL. | ||
| 463-53-001 | Paragraph 1.3.1 Calls out for the following material: |
Flow Sensor, FS200 series Adjustable, ¾ Inch, .5 Gpm to 100 Gpm, Stainless Steel, manufacturer Gems Sensors
However the supplier Gems Sensors states the following:
1) “We do not have a ¾” NPT for the FS-200. In addition, most units are fixed units.
We do have an adjustable version but it’s a 1” NPT and the ranges are 1-6 gpm, 5-15 gpm or 2-8 gpm.
and
2) “The catalog page is misleading when it states .5-100 gpm.”
Please provide correct part information
| This Work Item has been updated in Errata 1 to revised the type of sensor. See Amendment 0004 for revisions. | ||
| All | As of 03/29/19 contractor has 32 unanswered questions. These questions deal with a variety of issues ranging from material concerns, scope clarification, missing information and or missing drawings (36 total). Due to the flow down for this information through subcontractors, vendors and the internal process of reviewing and processing all of this information contractor requests a 3 week extension from the point of receiving answers. |
| Please concur to bid extension. | The date for proposal submission has been extended to 30 MAY 2019 via Amendment 0003. | |||
| 505-11-002 | Flexible hose assembly ; repair | Paragraph 3.1 states "Remove and dispose of system fluids from each flexible hose assembly listed in Attachment B." |
| Please provide attachment B | Paragraphs 1.3.1, 3.1 and 3.2.3 should read Attachment A, which is already attached to spec. Work Item has been updated in Errata 1 via Amendment 0004. | |||
| 514-11-001 | FAN COIL ASSY (FCA), FAN COIL UNIT (FCU) 01 LEVEL AND ABOVE ; REPAIR | Paragraph 3.1 states, "Electrically and mechanically connect each equipment listed in 1.3 and located in 1.2, using Chapter 2 and 3 of 2.2, 2.3 and 2.4 for guidance". |
Question #1 - There are 25 ea. Cooling coils and 52 fan coil units (Where is this equipment coming from? Is this on board or is all the equipment in storage (for installation only)?
Question #2 - Please provide individual references showing the locations/spaces of each cooling coil and fan coil unit to be installed.
Question #3 - Paragraph 3.2 states," Remove existing, fit and install new each parts provided in 5.1 , using 2.2 through 2.4". Where will these FCU/cooling coil's be installed? Please provide drawings. 1) All of the equipment is onboard.
2) FCU 01-374-2 LOCATED (01-372-0-L), FCU 02-286-1 LOCATED (02-276-0-Q), FCU 05-157-1 LOCATED (05-149-0-C)
3) Drawing submitted in Amendment 0002.
514-11-002 FAN COIL ASSY (FCA), FAN COIL UNIT (FCU) 01 LEVEL AND ABOVE ; REPAIR Paragraph 3.1 states, "Electrically and mechanically connect each equipment listed in 1.3.4 and located in 1.2, using Chapter 2 and 3 of 2.2, 2.3 and 2.4 for guidance".
Question #1 - There are 73 fan coil units (Where are these equipments coming from? Is this on board or is all the equipment in storage (for installation only)?
Question #2 - Please provide individual references stating the locations/spaces of each fan coil unit to be installed.
Question #3 - Paragraph 3.2 states," Remove existing, fit and install new each parts provided in 5.1.1 and 5.1.2". Please provide drawings and locations for installation of this equipment. 1) All of the equipment is onboard
2) FCU 2-453-2 LOCATED (2-426-2-L), FCU 1-424-2 LOCATED (1-382-01-L), FCU 2-423-1 LOCATED (2-387-0-Q)
3) Drawing submitted in Amendment 0002.
N/A NAVSEA STANDARD ITEMS FY19 Change 2, 009-81, Cat I, Compartment Closeout; accomplish Paragraph 3.1.1 states, "The compartment closeout schedule will be based on the list of affected spaces provided by the SUPERVISOR during the bidding process which lists all affected spaces requiring a compartment closeout along with the assigned Key Event or Milestone. The compartment closeout schedule shall contain the following minimum information"
Will the Government issue an Amendment providing the Compartment Close Out Schedule? The compartment close out schedule will be provided at a later date. Once the execution milestones have been developed a schedule will be forwarded as to what spaces will be required for PCD, ALO, LOA, etc...
KTR shall assume ALL spaces aboard the ship will require a 009-81, since all spaces will have work accomplished in them.
Amendment 0003 updated Attachment J-3 Milestones to include the CRS.
980-90-006 ShipAlt CG47-71386K, 78435K, 79922K, 80264K, 80264K, 80696K, 80897.03K, 80934K, 81322K, 81798K, 82853K, 83712K, 83883K, 84619K, 84694K, 84927K, 8136.03K, 88467.03K, 85030K, 86418K, and 86539.03k, Alteration Installation Team (AIT) Support Service; provide PARA 3.17.2 states accomplish 500 square feet of paint sandblasting, paint removal and heavy metal paint abatement as designated by the supervisor.
To insure that all offerors are bidding the same scope of work (which will insure fair competition) please provide the number of locations requiring containment and how many square ft per location to abate (example: 20 locations @ 25 Sqft per location).
| This is important as the number of containments needing to be built (and how big they need to be) are a driving factor in cost. | For estimating purposes, 25 locations at 20 sqft per location and 20 locations at 15 sqft per location. No change to Work Item necessary. | |||
| 980-90-010 | ShipAlt CG47-74392.03K, 78818.03K, 79256.03K, 85077.03K, 87106.03K, 77614.03K, 785.03K, 82635.03K, 83623, 87438.03K, 89226K, and 87024.03k, Alteration Installation Team (AIT) Support Service; provide | PARA 3.16.2 states accomplish 1000 square feet of paint sandblasting, paint removal and heavy metal paint abatement as designated by the supervisor. |
To insure that all offerors are bidding the same scope of work (which will insure fair competition) please provide the number of locations requiring containment and how many square ft per location to abate (example: 20 locations @ 50 Sqft per location).
| This is important as the number of containments needing to be built (and how big they need to be) are a driving factor in cost. | For estimating purposes, 50 locations at 20 sqft per location. No change to Work Item necessary. | |||
| 992-11-004 | Ship Towing Service, Long Range; provide (OPTION ITEM) | Ship Towing Service, Long Range; provide(OPTION ITEM) |
3.1 Provide licensed pilot, towing bridle, towboat service and waterborne security to tow the ship from NAVSTA San Diego to Contractor facility and back to NAVSTA San Diego, in accordance with 2.2 and 2.3.
when directed by the SUPERVISOR.
Contractor has reviewed the RFP, specification, and all identified references noting that, the intent of this work item appears to be for out of home port (San Diego) bidders.
Is this work item to be priced only by OUT of homeport (San Diego) Bidders and to be accomplished only if the contract is awarded outside of San Diego?
| Only shipyards out side of San Diego shall bid this work item. Attachment J-4, Pricing Worksheet has been revised to state, "to be priced by out of homeport bidders only" via Amendment 0004. | ||||
| RFP | Attachment J-4 | Several work Items listed in Attachment J-4 don’t appear to be applicable to Offerors located in the vessel's homeport. Please identify which work items should not be bid for Offerors located in the vessel homeport. | Only shipyards out side of San Diego shall bid 992-11-004 and 992-11-006. Attachment J-4, Pricing Worksheet has been revised to state, "to be priced by out of homeport Offeror's only" via Amendment 0004. | |
| 772-21-001 | Ammunition Strikedown Elevator (Fwd);repair | Paragraph 3.1 States "Accomplish the requirements of 009-90 of 2.1 for inspection, disassembly, repair, assembly and testing each equipment listed in 1.3 and located in 1.2." |
Equipment listed in 1.3 does not define water tight hatch that’s going to be overhauled.
| Please revise spec. | Work Item has been updated in Errata 1 via Amendment 0004. | ||
| 474-11-001 | Paragraph 3.2 states; "Install new each ablative pad listed in 1.3.1.1 through 1.3.4.1 and located in 1.2, using 2.2 through 2.4 for guidance." |
QUESTION; It is the intention of this paragraph to remove/reinstall the existing cover plates of each one of the ablative pad structures and replace the ablative pads inside? or is the intention to replace the entire ablative pad structures and the ablative pads?
| please advise. | This work item has been removed from work package in Attachment J-4 and in Errata 1 via Amendment 0004. | |||
| N/A | RFP | The current proposal due date of 16 May 2019 is being negatively impacted by preceding solicitations, resulting in a compressed proposal development timeline when coupled with other waterfront solicitation's competing interests. In addition to this solicitation, bidders have received and are planning the USS Lake Champlain (CG-57) DSRA and the USS Decatur (DDG-73) and USS Stethem (DDG-63) EDSRA's. This has saturated the waterfront with nearly 2,000 work items, and having three proposals for five ships due in quick succession is negatively affecting the downstream responsiveness of the subcontractor and material vendor community who are already notifying us of delays in pricing, and several cases, No Bidding key elements of work packages. |
The Contractor expects that we will continue to receive Amendments, Errata, and possible Addendums on all RFPs, further stressing the schedule for this proposal.
Question:
In order to depressurize the planning schedule and afford all contractors ample time to prepare/submit accurate proposals, and to allow for adequate time for subcontractor/vendor solicitations/evaluations/selections, request that the proposal due date be extended from 16 May 2019 at 3:00 pm, local time, Washington DC to 30 May 2019 at 3:00 pm, local time, Washington DC. A 14-day proposal due date extension, or roughly ~11 additional planning days.
| The date for proposal submission has been extended to 30 MAY 2019 via Amendment 0003. | ||
| All | As of today, for this contract there are more than 66 questions that have not been answered and there are 138 missing drawings. This significant amount of missing GFI prohibits timely and accurate completion of estimates. |
Please extend the bid due date by 3 weeks after all GFI is received.
| Thank you. | The date for proposal submission has been extended to 30 MAY 2019 via Amendment 0003. | |||
| 456-90-003 | Shipalt CG47-77614.03K, ACB12/TI12 OA Computer Plant Upgrade; accomplish | Para 3.2 states accomplish ref 2.4 through 2.22. ref 2.28 drawing 8710393 is an arrangement drawing that has rip out and installation of equipment, and equipment is being ordered on ref 14, 17, 18, 20, 26, 31, 36, 42 and 51 which are not called out on the spec. |
| please advice who is accomplishing those references of drawing 8710393 | The Contractor is to accomplish reference 14 of DWG 8710393. All material not listed on the 4720 is Installing Activity Furnished. AIT is responsible to accomplish ref 17, 18, 20, 26, 31, 42, and 51. | |||
| 456-90-003 | Shipalt CG47-77614.03K, ACB12/TI12 OA Computer Plant Upgrade; accomplish | Para 3.2 states accomplish ref 2.4 through 2.22. ref 2.29 drawing 8710394 is an arrangement drawing that has rip out and installation of equipment, and equipment is being ordered on ref 12 and 16 which are not called out on the spec. |
| Please advice who is accomplishing those references of drawing 8710394 | AIT is to accomplish ref 12 & 16 of DWG 8710394. | |||
| 583-11-002 | Starboard Boat Davit | Paragraph 3.5 call for the removal/installation of new hoses. This unit is hard pipped and does not have flexible hoses. |
| Please review and advise. | The Work Item has been updated in Errata 1 via Amendment 0004 to state there are flex hoses from the HPU to the control station. | |||
| 583-11-002 | Starboard Boat Davit | Contractor believes the listed technical manuals in this item are for a port side Vest Davit (not STBD) and therefore it seems as though the references are incorrect which has the following additional issues. |
1.) Due to the references being incorrect the GFM listed in the spec does not match the material listed in the Tech manuals.
2.) Lakeshore/Vest Davit are listed as the OEM on the Tech manual, however neither of these are the OEM. The OEM is Nick's Hydraulics and they have been out of business since July of 1998.
| Please concur and or advise on all issues. | The Work Item has been updated in Errata 1 via Amendment 0004. | ||
| 120-11-006 | Regarding para 3.5 of WI 120-11-006, Table and Lines specified is incorrect as this is for exterior hull preservation and does not match the locations identified in paras 1.2.1 – 1.2.6. |
| Please advise | The Work Item has been updated in Errata 1 via Amendment 0004 to read table 3. | |||
| 992-11-004 | Ship Towing Service, Long Range; provide(OPTION ITEM) | WI 992-11-004, Ship Towing Service, Long Range; provide (OPTION ITEM) - Requires the contractor outside of San Diego to tow the vessel from its homeport to the location of the contractor and back to the vessels homeport once the MODPRD has been accomplished. |
Contractor has competed numerous availabilities of vessels homeported in San Diego and this is the first time a NAVSEA tow has been incorporated on a vessel that is self propelled into the specification.
Page 150 of the solicitation section b) The IPD applicable to the USS CHOSIN CG 65 must be included in all offers and is calculated using foreseeable costs for fuel, towing and pilot charges, and travel to the contractor’s facility by applicable Government personnel. The following chart provides the values to be included in all offerors’ price proposals to determine the offeror’s total evaluated price.
Question #1 - As this item is designated as an option item, is it the intent for the Government to use one of MSC's towing/salvage tugs to accomplish the tow and if they cannot accommodate the schedule have the contractor provide commercial towing services?
Contractor believes that by having the IPD stated within the solicitation as well as pricing the option item for the tow evaluated together essentially doubles the IPD for this vessel and gives San Diego contractors an unfair advantage prior to bidding any other work within the specification.
Question #2 - If the vessel has a propulsion system, why is it necessary to accomplish towing the vessel rather then have the vessel come under its own power?
Question #3 - Why does the vessel need to be towed both ways?
Towing Service Long Range is for contractors outside of San Diego area. Attachment J-4 has been updated in Amendment 0004 to note certain WIs that are to be priced by out of homeport bidders only.
Answer #1 - The MSC is required to provide long range towing services for towing outside of the San Diego area.
Answer #2 - The vessel does not currently have engines installed, thus the requirement of long range towing service to areas outside san Diego area.
Answer #3 - This requirement may be necessary.
NA USS CHOSIN specification index The specification index for the USS CHOSIN states FY-18 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE for both Category I & II.
| Is this correct or should they be FY19? | CAT I STD ITEMS FY19 through CH2 and CAT II STD ITEMS FY19 through CH2 apply. WI Index has been updated in Errata 1 via Amendment 0004. | |||
| 665-90-002 | ShipAlt CG47-83343K, Replace Bandsaw with Hacksaw; accomplish | Ref 2.6 identifies items 100-102 of reference 2.3 as PreFab. |
| Are these items just pre-cut or are they already assembled as a complete ready to go foundation? | Item 100 -102 will be furnished as a complete assembly. | ||
| All | As of 04/09/19, for this contract there are more than 51 questions that have not been answered. 135 new references provided on 4/9/19 including 8 new 4720 documents. This significant amount of missing and new GFI prohibits timely and accurate completion of estimates. |
Please extend the bid due date by 3 weeks to allow time to process new information as well as missing information (that will also need to be processed by contractor, subcontractors and material vendors).
Please advise as soon as possible.
| Thank you. | The date for proposal submission has been extended to 30 MAY 2019 via Amendment 0003. | |||
| 992-11-016 | Fuel Assistance and Towboat Service for Fuel Barge; accomplish | Paragraph 3.2 states, "Furnish pilot, towing bridle and towboat service and tow 2 (EA) fuel barges totaling 500,000 gallons of fuel from Authorized Fuel Depot, to the contractor's plant, adjacent to the ship. Upon completion of fueling and when directed by the SUPERVISOR, return the fuel barges to their |
original location".
Contractor notes Fuel Depot Point Loma does not allow contractor tugs to enter and tow their barge.
| Will the Government confirm this work item is for out of port bidders only? | Only shipyards outside of San Diego shall bid 992-11-004 and 992-11-006. Attachment J-4, Pricing Worksheet has been revised to state, "to be priced by out of homeport Offeror's only" via Amendment 0004. | |||
| 992-11-004 | Ship Towing Service, Long Range; provide (OPTION ITEM) | Paragraph 3.1 states, "Provide licensed pilot, towing bridle, towboat service and waterborne security to tow the ship from NAVSTA San Diego to Contractor facility and back to NAVSTA San Diego, in accordance with 2.2 and 2.3. when directed by the SUPERVISOR". |
Contractor notes this is an Option specification that appears to be for bidders outside the vessels home Port of San Diego, Ca.
| Will the Government confirm that this Option specification is applicable only for those bidders outside vessels home Port of San Diego, Ca? | Only shipyards out side of San Diego shall bid 992-11-004 and 992-11-006. Attachment J-4, Pricing Worksheet has been revised to state, "to be priced by out of homeport Offeror's only" via Amendment 0004. | |||
| 633-21-001 | Impressed Current Cathodic Protection (ICCP) System; Repair | Paragraph 3.10 states, "Accomplish the requirements of 009-32 of 2.1 for each newly installed capastic shield, using 2.6 for guidance, including Table One, Line 7". |
Contractor notes that the correct NAVSEA Standard Items FY19 Change 2, 009-32 requirements are Table One, Line 8 or 9.
| Can the Customer provide clarification as to the disparity between Paragraph 3.10 of the specification as written and the NSI 009-32 requirement identified by the Contractor? | This Work Item has been updated in Errata 1 via Amendment 0004 to read line 8 or 9. | |||
| 551-11-004 | High Pressure Air Compressor; installation | Paragraph 3.6 states, "Fill each compressor oil reservoir to the full mark with new oil conforming to MIL-PRF-17331, Symbol 2190 TEP, in accordance with Table 1-1 of 2.2". |
Contractor notes reference 2.2 "S9073-A2-HBK-010 Rev 1, Resilient Mount Handbook" is not applicable to accomplishment to fill each compressor oil reservoir and that reference 2.5 "S6220-DR-OMI-010 Rev 3, Technical Manual Installation, Operation, Maintenance, Repair Instructions" is the actual applicable document for these requirements.
| Can the Customer provide clarification as to the disparity between Paragraph 3.6 of the specification as written and the actual requirement identified by the Contractor? | The Work Item has been updated in Errata 1 via Amendment 0004 to read ref 2.5. | |||
| 992-11-004 | Ship Towing Service, Long Range; provide(OPTION ITEM) | WI 992-11-004, Ship Towing Service, Long Range; provide (OPTION ITEM) - Requires the contractor outside of San Diego to tow the vessel from its homeport to the location of the contractor and back to the vessels homeport once the MODPRD has been accomplished. |
Contractor has competed numerous availabilities of vessels homeported in San Diego and this is the first time a NAVSEA tow has been incorporated on a vessel that is self propelled into the specification.
Page 150 of the solicitation section b) The IPD applicable to the USS CHOSIN CG 65 must be included in all offers and is calculated using foreseeable costs for fuel, towing and pilot charges, and travel to the contractor’s facility by applicable Government personnel. The following chart provides the values to be included in all offerors’ price proposals to determine the offeror’s total evaluated price.
Question #1 - As this item is designated as an option item, is it the intent for the Government to use one of MSC's towing/salvage tugs to accomplish the tow and if they cannot accommodate the schedule have the contractor provide commercial towing services?
Contractor believes that by having the IPD stated within the solicitation as well as pricing the option item for the tow evaluated together essentially doubles the IPD for this vessel and gives San Diego contractors an unfair advantage prior to bidding any other work within the specification.
Question #2 - If the vessel has a propulsion system, why is it necessary to accomplish towing the vessel rather then have the vessel come under its own power?
Question #3 - Why does the vessel need to be towed both ways?
Towing Service Long Range is for contractors outside of San Diego area. Attachment J-4 has been updated in Amendment 0004 to note certain WIs that are to be priced by out of homeport bidders only.
Answer #1 - The MSC is required to provide long range towing services for towing outside of the San Diego area.
Answer #2 - The vessel does not currently have engines installed, thus the requirement of long range towing service to areas outside San Diego area.
Answer #3 - This requirement may be necessary.
NA USS CHOSIN specification index The specification index for the USS CHOSIN states FY-18 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE for both Category I & II.
| Is this correct or should they be FY19? | CAT I STD ITEMS FY19 through CH2 and CAT II STD ITEMS FY19 through CH2 apply. WI Index has been updated in Errata 1 via Amendment 0004. | |||
| 665-90-002 | ShipAlt CG47-83343K, Replace Bandsaw with Hacksaw; accomplish | Ref 2.6 identifies items 100-102 of reference 2.3 as PreFab. |
| Are these items just pre-cut or are they already assembled as a complete ready to go foundation? | Item 100 -102 will be furnished as a complete assembly. | |||
| N/A | SF 33 Block 9 | The USS Cape St George and USS Chosin MODPRD's have combined a total over 800 work items inclusive of over 200 ShipAlts to be priced by May 16th. Contractor has received numerous notifications by not only subcontractors but also mandated tech reps that they will not be able to meet and support the current proposal date of May 16th. |
Contractor requested a ship check on 4/9/19 and to date has not had a response from the Government.
Please consider the following:
1) Please make either the USS Cape St. George or the USS Chosin available for a ship check. The ship check is necessary to validate the scope and complexity as well identifying potential interferences for each associated work item.
2) Please extend the proposal due date of May 16th to June 16th. Please extend the bidder questions time frame to May 16th.
These extensions will be necessary for contractor to request and receive subcontractor quotes, review entire specification and references, submit questions, allow time to answer questions and contractor time to incorporate answers into our proposal.
| Both requests above will need approval for contractor to continue preparing a proposal for this solicitation. | The date for proposal submission has been extended to 30 MAY 2019 via Amendment 0003. | |||
| 634-90-001 | ShipAlt CG47-83539K, Compartment Deck Covering Replacement; accomplish | Please provide the following missing references: |
2.5 RLAR 83539/CG65/P272, Replace Compt Deck Coverings
| 2.6 RLAR 83539/CG65/P331, Replace Compt Deck Coverings | Ref 2.5 and 2.6 provided via Amendment 0004. | |||
| 980-80-001 | AER 84293 and AER 84893, NSWC Alteration Installation Team (AIT) Alteration Installation Team (AIT) Support Service; provide | Paragraph 3.11 states, "Services shall" |
*Contractor believes that the intent of this paragraph applicable to the services identified in 3.7 through 3.10.2.
Paragraph 3.11.1 states, "Be installed not later than 5 business days prior to commencement of production start date"
*Contractor notes the AIT's production start date was not provided in the specification as written.
Paragraph 3.11.2 states, "Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR"
*Contractor notes the AIT's completion and testing dates was not provided in the specification as written.
Question: Will the Government provide production start, completion and testing dates?
| AIT has not provided a schedule start of work for this item. It is assumed that all work will start on avail start date. See Attachment J-3 and PERL for testing dates via Amendment 0003. | |||
| 980-90-001 | ShipAlt CG47-83143K, CG ISC OSU SS20 Upgrade, Alteration Installation Team (AIT) Support Service; provide | Paragraph 3.12 states, "Services shall" |
*Contractor believes that the intent of this paragraph applicable to the services identified in 3.9 through 3.11.
Paragraph 3.12.1 states, "Be installed not later than 5 business days prior to commencement of production start date"
*Contractor notes the AIT's production start date was not provided in the specification as written.
Paragraph 3.12.2 states, "Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR"
*Contractor notes the AIT's completion and testing dates was not provided in the specification as written.
Question: Will the Government provide production start, completion and testing dates?
Note the response to this Pre-Proposal Information (PPI) Question is also applicable to the following listed (5) specifications and paragraphs,
| AIT has not provided a schedule start of work for this item. It is assumed that all work will start on avail start date. Testing dates are on J-3 and PERL, submitted via Amendment 0003. | |||
| 980-90-005 | ShipAlt CG47-77543K, Improved Point Detection System Lifecycle Replacement (IPDS-LR) Installation, Alteration Installation Team (AIT) Support Service; provide | Paragraph 3.7 states, "Services shall" |
*Contractor believes that the intent of this paragraph applicable to the services identified in 3.4 through 3.6.2.
Paragraph 3.7.1 states, "Be installed not later than 5 business days prior to commencement of production start date"
*Contractor notes the AIT's production start date was not provided in the specification as written.
Paragraph 3.7.2 states, "Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR"
*Contractor notes the AIT's completion and testing dates was not provided in the specification as written.
Question: Will the Government provide production start, completion and testing dates?
| AIT has not provided a schedule start of work for this item. It is assumed that all work will start on avail start date. See Attachment J-3 and PERL for testing dates via Amendment 0003. | |||
| 980-90-009 | ShipAlt CG-47-89096K,CLS P25 Hydra Technology Installation, Alteration Installation Team (AIT) Support Service; provide | Paragraph 3.8 states, "Services shall" |
*Contractor believes that the intent of this paragraph applicable to the services identified in 3.6 through 3.7.
Paragraph 3.8.1 states, "Be installed not later than 5 business days prior to commencement of production start date (See 4.1.1)"
*Contractor notes the AIT's production start date was not provided in the specification as written.
Paragraph 3.8.2 states, "Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR"
*Contractor notes the AIT's completion and testing dates was not provided in the specification as written.
| Question: Will the Government provide production start, completion and testing dates? | AIT has not provided a schedule start of work for this item. It is assumed that all work will start on avail start date. See Attachment J-3 and PERL for testing dates via Amendment 0003. | |||
| 980-90-010 | ShipAlt CG47-74392.03K, 78972.03K, 78818.03K, 79256.03K, 85077.03K, 87106.03K, 77614.03K, 78510.03K, 82635.03K, 83623K, 87438.03K, 89226K, and 87024.03K, Alteration Installation Team (AIT) Support Service; provide | Paragraph 3.12 states, "Services shall" |
*Contractor believes that the intent of this paragraph applicable to the services identified in 3.6 through 3.11.1.
Paragraph 3.12.1 states, "Be installed not later than 14 business days after commencement of production start date (See 4.1.1)"
*Contractor notes the AIT's production start date was not provided in the specification as written.
Paragraph 3.12.2 states, "Be provided until completion of inport testing (See 4.1.4). Earlier removal, if required, will be when directed by the
SUPERVISOR"
*Contractor notes the AIT's completion and testing dates was not provided in the specification as written.
| Question: Will the Government provide production start, completion and testing dates? | AIT has not provided a schedule start of work for this item. It is assumed that all work will start on avail start date. See Attachment J-3 and PERL for testing dates via Amendment 0003. | |||
| 980-90-016 | OrdAlt CG47-20204 CLS 1.0, OA-20379 Antenna Power Assembly, OA-70699 Aws Fcs/Cwi Noise and Capability Installation, Alteration Installation Team (AIT) Support Service; provide | Paragraph 3.6 states, "Services shall" |
*Contractor believes that the intent of this paragraph applicable to the services identified in 3.3 through 3.5.1.
Paragraph 3.6.1 states, "Be installed not later than 5 business days prior to commencement of production start date"
*Contractor notes the AIT's production start date was not provided in the specification as written.
Paragraph 3.6.2 states, "Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR"
*Contractor notes the AIT's completion and testing dates was not provided in the specification as written.
Question: Will the Government provide production start, completion and testing dates?
AIT has not provided a schedule start of work for this item. It is assumed that all work will start on avail start date. See Attachment J-3 and PERL for testing dates via Amendment 0003.