USS CAPE ST GEORGE (CG-71) Bidder's Questions and answers
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QA3
| USS CAPE ST GEORGE (CG 71) | ||||
| Drawing | ||||
| GFM | Solicitation #: | N00024-19-R-4447 | Phone | |
| RLAR | TPPC | TPPC-CG71-SWRMC20-CN01 | Justin Lessel, Contract Specialist, justin.d.lessel@navy.mil | 202-781-4064 |
| Martha Bello, Contracting Officer, martha.bello@navy.mil | 202-781-3864 | |||
| The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation. | ||||
| To request references, drawings, RLARs, and Erratas being provided under this Solicitation Question & Answer Set, |
please contact Justin Lessel, justin.d.lessel@navy.mil, and Martha Bello, martha.bello@navy.mil.
| Work Item No. | Document Number/Title | Question | Government Response | ||
| 980-90-005 | Title: ShipAlt CG64-SA88635K and SA88645K, CIWS BLK 1B Overhaul, CIWS BLK 1B LCS and RCS Shock Coil Upgrade & LCP Elimination, Alteration | ||||
| Installation Team (AIT) Support Service; provide | 3.12 Services shall: |
3.12.1 Be installed not later than 5 business days prior to
commencement of AIT production start date. (See 4.1.1)
3.12.1.1 AIT to notify contractor 10 days prior to production start date.
3.12.2 Be provided through Aegis Light-Off (ALO) unless otherwise stated. Earlier removal, if required prior to end of availability, will be when directed by the SUPERVISOR
1) Will the Government provide production start, completion and testing dates?
2) Will the Government provide an Errata that includes Para 4.1.1? Production start, completion and test dates will best be discussed, reviewed and approved with AIT and contractor at WIPER. 1) Government will provide production start, completion, and testing dates. As of now this information is too far out to provide accurately.
2) Work Item has been updated in Errata 3 via Amendment 0005.
992-11-006 Messing and Berthing Barge Tow Service, Temporary Service, Equipment and Systems Test, Inspection and Repair in Contractor Plant; accomplish (OPTION ITEM) 3.1 Pick-up and deliver the barge listed in 1.3 from TBD to the Contractor's plant 14 Days prior to Availability Start Date, using 2.2 for guidance. Return the barge to TBD when directed by the SUPERVISOR.
Will the Government provide the size of the barge that will be provided to support ships force?
Can the Government remove the TBD and provide a pick up and return locations of the barge?
| Is this work item for Out of Home Port bidders only? | This work item is for home port bidders only, Location is San Diego Naval station. It was updated via Amendment 0003. Size of barge Length 261 feet. Beam 49 Feet, Draft 11 Feet, Displacement 1,300 Tons. | |||
| 481-90-003 | ShipAlt CG47-78818.03K, Mark 34 Mod 6 Gun Weapons System (GWS) MOD TI12 ABC12 Hardware Upgrade; accomplish | 3.3 Accomplish the requirements of 2.4 through 2.29, including all general, local, special, test and rip-out notes using 2.30 through 2.37 for guidance. |
Reference 2.6 183-8736406, ShipAlt CG47-78818.03K MK 34 Mod 6 GWS Upgrade Misc Foundations invokes Special Note S-3. Special Note 3 states : All flatness contact and angular tolerances and other requirements of reference No 13 shall be maintained.
| Will the Government provide Reference 13; Drawing number 8241881 "Above Deck Sensor Unit, Rcs"? | Work Item has been updated in Errata 3 via Amendment 0005. Updated references have been provided in Amendment 0005. | |||
| 992-11-001 | TEMP FLAMMABLE LIQUID STR & HAZARDOUS MATERIAL STORAGE UNIT; PROVIDE | Para 3.2.4. states" Provide a minimum of 320 sq ft of floor space, with a seven-foot minimum ceiling". Due to the fact that the only size available in San Diego per unit has 160 sqft of floor space contractor request that multiple storage units be allowed to meet the requirements of the total square footage required. |
| Please concur or advise. | Multiple storage units are allowed to meet the requirements of total square footage. | |||
| 521-11-003 | Gage Line Piping; replace | Paragraph 3.2.1 Raychem Cryofit Coupling 920575-250 (F401) is discontinued since 11 Jul 2002 without a replacement . |
| Please advise on how to accomplish the work. | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 521-11-005 | Firemain Piping and Valve; replace | ON para 3.2.1.1 Raychem Cryofit Coupling 920575-250 (F401) is discontinued since 11 Jul 2002 without a replacement . |
| Please advise on how to accomplish the work. | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| N/A | RFP-TPPC-CG71-SWRMC20-CN01 Page 76 of 164 | NOTE F: SPECIAL AGREEMENT FOR GROWTH WITH A VALUE OF $25,000 OR LESS. |
To make administration of small dollar value changes more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $25,000 or less. The Contract will include a firm fixed price for growth valued at $25,000.00 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process.
| In NOTE F, will the Government clearly identify changes in drawings when they have determined that "no additional work is required"? | Changes in drawings that are identified as admin-only changes are annotated as such. | |||
| N/A | RFP N0002419R4447 | The ability for bidders to meet the current proposal due date of 5/16/2019 remains at risk due to significant pressure of other waterfront bid activities that have been eroding the available planning time for the USS Chosin's and USS Cape St. George's large work item packages in this solicitation. |
The downstream impacts of planning USS Lake Champlain (CG-57) DSRA that was planned yet subsequently cancelled on 4/2/2019, and the USS Decatur (DDG-73) / USS Stethem (DDG-63) EDSRA RFP with three pricing scenarios (now due 5/14/2019 to overcome challenges [was 4/22/2019]), has resulted in erosion of available days to focus on this RFP. This erosion of the planning timeline is hindering our ability to effectively/accurately estimate labor and obtain subcontractor and material vendor quotes. Subcontractors and vendors continue to notify us of delays, and in many cases, No Bidding key elements of work due to constraints.
We expect that the planning tempo will remain high on the MODPRD's where adjudicating forthcoming Amendments, Q&A's, Errata, Addendums, that are necessary but further apply risk to the scheduled due date.
Question:
| To afford all contractors ample time to recover critically needed timeline and prepare/submit accurate proposals, and to allow for adequate time for subcontractor/vendor solicitations/evaluations/selections, request that the proposal due date be extended from 16 May 2019 at 3:00 pm, local time, Washington DC to 6 June 2019 at 3:00 pm, local time, Washington DC. A 21-day proposal due date extension, or roughly ~17 additional planning days. | Proposal due date has been extended to 06 June 2019. | |||
| 123-10-001 and 997-11-001 | RFP-TPPC-CG71-SWRMC20-CN01 Page 84 of 164 | 3.5 MILESTONES FOR CERTAIN REPORTS: |
Quality Assurance Plan (QASP) Attachment J-5 Deliverable 2: The Contractor shall complete the necessary work associated with the reports due on or before the first 20 percent of the docking duration as well as the reports due on or before the first 20 percent of the availability duration and submit to the Government the required reports in the necessary format and containing the required information as specified in the Work Item in accordance with their prescribed due dates or be subject to the deductions provided in Attachments J-5 and J-15, QASP.
NAVSEA Standard Item FY-19 Change-2
3.2.2 For reports required by 2.1 or the Work Item, that could result in a change in work to be accomplished or additional material to be procured, complete the preliminary work and submit one legible copy, in approved transferrable media, of the report in a time frame to allow the SUPERVISOR to initiate early action, but no later than the first 20 percent of the availability.
Paragraph 3.2.4 Dry dock related inspection reports shall be submitted no later than the first 20 percent of the scheduled docking period. Dry dock related reports which contain readings (final, thickness, etc.), clearances, alignments, test results, or other such data for work that has to be completed prior to pre-flood/undocking, shall be submitted to the SUPERVISOR within one day after recording the data but no later than 4 days prior to preflood/undocking, whichever occurs first.
Work Item 997-11-001 Drydocking and Undocking; accomplish Paragraph 3.7 Drydock the ship in accordance with 2.2 and 2.4. The ship shall be drydocked during the first 10 percent of the availability.
Work Item 123-10-001 Tank and Void Open, Pump, Clean and Gas Free; accomplish Contractor notes that the requirements of paragraph 3.1 through 3.5.3.2 of this work item MUST be completed before the contractor can enter the tanks or spaces identified in paragraph 1.2.1 through 1.2.94 which includes voids, cofferdams, and inaccessible or confined areas to conduct the various work items required Condition Found Inspection reports which are to be submitted no later than the first 20 percent of the scheduled docking period. Additionally, the contractor notes that for local bidders the ship must be docked within the first 10 percent of the availability, this delays the contractor from starting the requirements of 123-10-001. 1)
Due to the excessive work associated with the accomplishment of work item 123-10-001 which MUST be complete before the various work item tank Condition Found Inspection reports can be accomplished and in accordance with NAVSEA Standard Item FY19 Change 2, 009-01 “General Criteria; accomplish” paragraph 3.2.5, for local bidders the Contractor requests an exception for submission of all dry dock tank related inspection reports currently tied to the first 20 percent of the scheduled docking period.
| Not authorized, there are no exceptions to NAVSEA Standard items. | |||
| 243-11-003 | Starboard Propulsion Shafting; inspect and repair | Paragraph 3.1 States "Accomplish the requirements of 009-90 of 2.1 for removal, cleaning, repair, welding, installation and testing of shafting components for each equipment listed in 1.3.1 through 1.3.3 and located in 1.2 in accordance |
with 2.2 through 2.5, Section One of 2.6, 2.7 through 2.9, Section 4 of 2.10, 2.11, 2.13, 2.14 and 2.17."
| Please provide contact information for the requirement of 009-90 stated in paragraph 3.1 | Work item has been updated in Errata 3 via Amendment 0005. | |||
| 243-12-001 | Port Propulsion Shafting; inspect and repair | Paragraph 3.1 States "Accomplish the requirements of 009-90 of 2.1 for removal, cleaning, repair, welding, installation and testing of shafting components for each equipment listed in 1.3.1 through 1.3.3 and located in 1.2 in accordance |
with 2.2 through 2.5, Section One of 2.6, 2.7 through 2.9, Section 4 of 2.10, 2.11, 2.13, 2.14 and 2.17."
| Please provide contact information for the requirement of 009-90 stated in paragraph 3.1 | Work item has been updated in Errata 3 via Amendment 0005. | ||
| All | As of 04/23/19, for this contract there are more than 59 questions that have not been answered. 135 new references provided on 4/9/19 including 8 new 4720 documents. This significant amount of missing and new GFI prohibits timely and accurate completion of estimates with the bid due in 3 weeks. |
Please extend the bid due date by 5 weeks to allow time to process new information as well as missing information (that will also need to be processed by contractor, subcontractors and material vendors).
Please advise as soon as possible.
| Thank you. | Proposal due date has been extended to 06 June 2019. | |||
| 243-11-003 | Starboard Propulsion Shafting; inspect and repair | Paragraph 3.1 States "Accomplish the requirements of 009-90 of 2.1 for removal, cleaning, repair, welding, installation and testing of shafting components for each equipment listed in 1.3.1 through 1.3.3 and located in 1.2 in accordance |
with 2.2 through 2.5, Section One of 2.6, 2.7 through 2.9, Section 4 of 2.10, 2.11, 2.13, 2.14 and 2.17."
| Contractor is requesting contact information for the requirement of 009-90 stated in paragraph 3.1 Please advice or provide. | Work item has been updated in Errata 3 via Amendment 0005. | |||
| 243-12-001 | Port Propulsion Shafting; inspect and repair | Paragraph 3.1 States "Accomplish the requirements of 009-90 of 2.1 for removal, cleaning, repair, welding, installation and testing of shafting components for each equipment listed in 1.3.1 through 1.3.3 and located in 1.2 in accordance |
with 2.2 through 2.5, Section One of 2.6, 2.7 through 2.9, Section 4 of 2.10, 2.11, 2.13, 2.14 and 2.17."
| Contractor is requesting contact information for the requirement of 009-90 stated in paragraph 3.1 Please advice or provide. | Work item has been updated in Errata 3 via Amendment 0005. | ||
| N/A | SF 33 Block 9 |
Contractor will need additional time to conduct the ship check, disseminate the information ascertained during the ship check to subcontractors as well as mandated tech reps.
Due to the late access approval to conduct the ship check onboard the USS Cape St. George, please consider the following:
1) Please make the USS Cape St. George available for a ship check. The ship check is necessary to validate the scope and complexity as well identifying potential interferences for each associated work item.
2) Please extend the proposal due date of May 16th to June 28th. Please extend the bidder questions time frame to May 28th.
These extensions will be necessary for contractor to request and receive subcontractor quotes, review entire specification and references, submit questions, allow time to answer questions and contractor time to incorporate answers into our proposal.
Both requests above will need approval for contractor to continue preparing a proposal for this solicitation. 1) Ship check has been granted.
2) Proposal due date has been extended to 06 June 2019.
472-90-001 ShipAlt CG47-80156.03K, Mod to AN/SLQ-32(V)6 Hardware; accomplish 3.2 Accomplish the requirements of 2.4 through 2.23, including all general, local, special, test and rip-out notes using 2.24 through 2.28 for guidance.
Contractor notes paragraph 2.13 Ref-471-8736572, ShipAlt CG-47-80156.03K SLQ-32 (V) 6 Blk Wrg Diag identifies numerous Connectors, Backshells and Cable as Fiber Optic. Contractor notes NAVSEA Standard Item 009-123 for "Fiber Optic Component; Remove, relocate, repair and install" is a Category II and is not called out within the work item to be accomplished.
RFP-N000241R4447 Page 79 of 163 states. Category II NAVSEA FY19 Standard Items through CHG 2 are applicable when invoked and/or referenced in individual work items specified in Attachments J-1 and J-11.
| Will the Government issue an Errata and invoke the requirement of NAVSEA Standard Item 009-123? | Work Item has been updated in Errata 3 via Amendment 0005. | ||
| 634-90-001 | Paragraph 3.3 states; "Accomplish the requirements of 009-26 of 2.1, including Attachment A, for installation of Ceramic Tile" |
Question; there is no Ceramic Tile on any of the references from this work item. Also paragraph 3.3.1 is affected by paragraph 3.3
| Please review & advise. | Work Item has been updated in Errata 3 via Amendment 0005. | ||
| 634-90-001 | Paragraph 3.5 states; "Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 6, Columns A, B, and E." |
Question; there is no statement of location to where this paragraph has to be accomplished.
| Please review and advise. | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 551-51-002 | High Pressure Air Compressor, install | Paragraph 5.1 air compressor APL 061050055 is a RIX INDUSTRIES compressor however, paragraph 4.2 calls out Curtiss-wright as a know source for technical representative. |
Contractor contacted Curtiss-wright who said they are not the technical representative.
| Please confirm & advise | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 551-51-002 | High Pressure Air Compressor, install | Rix Industries and has informed the contractor that references 2.2 & 2.4 are listing incorrect tech manuals. |
Rix Industries stated that paragraph 2.2 should be S9550-BZ-MMA-A10 REV2 and paragraphs 2.4 should be 4C551C101 REV D.
| Please confirm and advise | Ref 2.2 is correct. Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 542-11-001 | JP-5 Storage and Service System; repair | 3.3 Accomplish the overhaul for equipment listed in 1.3.2 and located in 1.2.1, using 2.2 for guidance through paragraph 3.4.1. |
Contractor notes the requirement to accomplish an 009-90 Technical Representative; provide is not included within the work item.
Will the Government issue an Errata and invoke the requirement of NAVSEA Standard Items 009-90?
| Will the Government provide the name and contact information for the Contractor to use in order to accomplish the 009-90? | 009-90 is not required in this work item. | |||
| 251-33-001 | Gas Turbine Module (GTM) Intake; partial repair | Paragraph 3.2 states, "Straighten and weld repair the equipment listed in 1.3 and located in 1.2 to prevent a gap between the lower support beam, using 2.2 through 2.5 for guidance". |
*Contractor notes that there is no preceding paragraph that invokes an inspection and report of the existing conditions of the Foreign Object Debris (FOD) Screen to identify exactly what repairs need to be accomplished or if it should be replaced.
| Please provide clarification regarding the disparity identified above and requirements of the specification as written for paragraph 3.2? | Ship checks are authorized to determine existing conditions, and Work Item has been updated in Errata 3 via Amendment 0005. | ||||
| RFP Section J | RFP Section J | Attachment A to this Question No. 0034 provides a listing of 5 technical drawings where as of 5/1/19 have not been provided. This includes 4720 reports that have not been provided. These discrepancies are preventing accurate estimates from being developed. Please provide as soon as possible. | See attachment A tab. | ||
| n/a | RFP N0002419R4447; Section F Deliveries or Performance | RFP Section F depicts the following “Delivery Dates”; |
USS CHOSIN CLINs 0001 through 0054: 17-JUN-2021 USS CAPE ST GEORGE CLINs 0101 through 0140: 20-May-2022
RFP Section J, Attachments J-3 and J-13 (Execution Milestones and Key Event Days) depict the following dates;
USS CAPE ST GEORGE:
KTR Contract Complete: Monday, January 17, 2022 Availability Complete: Friday, May 20, 2022
Bidder acknowledges that Section F “Delivery Dates” match the Attachment J-13 “Availability Complete” date.
QUESTION:
| Please explain Contractor’s performance/contractual obligations after the Attachment J-13 “KTR Contract Complete” dates? In other words, what are the contractor’s performance/contractual obligations during the period between the above Attachment J-13 “KTR Contract Complete” date and “Availability Complete” date; understanding that RFP Section F establishes the “Delivery Date” as the same as the Attachment J-13 “Availability Complete” date? | Attachment J-3 and J-13, as well as, Section F Delivery Dates have been revised via Amendment 0005 to correspond with each other. | |||
| n/a | RFP-N00024-19-R-4447 Section- C Page-85 | Contractor acknowledges that Section C Paragraph 2.1 (Page-85) of the conformed Amendment 0004 states in paragraph 2.1 "The required place of performance for the MODPRDs shall be the contractors facility." |
The contractor has reviewed previously awarded contracts, both Coastwide and SDMAC, and notes that availabilities accomplished in the Port of San Diego start pierside at NAVSTA 32nd Street for the first 14 Calendar days. This allows the customer and ship's force time to prepare the ship to enter contractors facility. Activities listed are not all inclusive: Ship's Force movement to Berthing Barge and Ship's Force off-load of stores, material, and portable equipment. This also allows the contractor an opportunity to set-up temporary services; installation of staging, drain, disposal, and dewatering of specific water systems; installation of the AN/SPY-1D Antenna Protective Covers and installation of deck protection prior to arrival in the contractors facility.
| Question: Can bidder's assume that if the contract is awarded to a bidder for accomplishment in the Port of San Diego, than the first 14 Calendar days will be accomplished pierside at NAVSTA 32nd Street prior to movement of the ship and berthing barge to the contractors facility? | Bidder's cannot assume that if the contract is awarded for accomplishment in the Port of San Diego, that the first 14 Calendar days will be accomplished pierside at NAVSTA 32nd Street prior to movement of the ship and berthing barge to the contractors facility. | ||||
| 634-90-001 | Paragraph 3.3 states; "Accomplish the requirements of 009-26 of 2.1, including Attachment A, for installation of Ceramic Tile" Question; there is no Ceramic Tile on any of the references from this work item, please review & advise. | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 634-90-001 | Paragraph 3.3.1 is affected by paragraph 3.3 | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 634-90-001 | Paragraph 3.5 states; "Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 6, Columns A, B, and E." Question; there is no statement of location to where this paragraph has to be accomplished, please review & advise. | Work Item has been updated in Errata 3 via Amendment 0005. | |||
| 123-21-002 E2 | Please provide reference 2.9 (191-6253823 REV B, CG 71 Permanent Lead Ballast Installation). | Provided in Errata 2 references and again in Errata 3 References via Amendment 0005. | |||
| 311-30-002 (E1) | Gas Turbine Generator (GTG) Enclosure; repair | 3.7 Repair broken weld at base of material identified in 1.3.4 and |
located in 1.2.1.
*Contractor notes that there is no preceding paragraph that invokes an inspection and report of the existing conditions of the Foreign Object Debris (FOD) Screen to identify exactly what repairs need to be accomplished or if it should be replaced.
| Please provide clarification regarding the disparity identified above and requirements of the specification as written for paragraph 3.2? | Ship checks are authorized to determine existing conditions. | |||
| 551-51-002 | High Pressure Air Compressor, install | 3.1 Accomplish the requirements of 009-90 of 2.1 for the services of a qualified on-site technical representative to install, test and provide drawings, material, equipment or special tools for each equipment provided in 5.1.2, and located in 1.2. |
4.2 Known source for qualified on-site technical representative:
Curtiss-Wright Service Center 1675 Brandywine Avenue, Suite F Chula Vista, CA 91911
Contractor was informed by the Technical Representative, Curtiss Wright, that these are not Curtiss Wright High Pressure Air Compressors.
Will the Government issue an Errata changing Para 4.2 for the 009-90 for the services of a qualified on site technical representative to Rix Industries?
Will the Government include point of contact information? Work Item has been updated in Errata 3 via Amendment 0005.
&P of &N
Attachment A
| DISCREPANCIES | PM Status | |||
| DOCUMENT TYPE | WORK ITEM | DOCUMENT NUMBER | DISCREPANCY DESCRIPTION | |
| NAVSEA Drawing | 123-11-001 | 110-5919495-U | Technical Document Not Included On CD | Provided in Errata 3, Amendment 0005 |
| NAVSEA Drawing | 640-8737760-A | Technical Document Not Included On CD | What work Item? | |
| 4720 GFM | 641-11-001 | 4720-CG47-FY21 Rev05 | Technical Document Not Included On CD Does Not exist | Provided in Errata 3, Amendment 0005 |
| 4720 GFM | 643-11-001 | 4720-CG47-FY21 Rev05 | N/A | Provided in Errata 3, Amendment 0005 |
| 4720 GFM | 980-90-004 | 4720-CG47-FY21 Rev05 | Technical Document Not Included On CD Does Not exist | Provided in Errata 3, Amendment 0005 |
| NAVSEA Drawing | 997-11-001 | 801-6253821-B | Technical Document Not Included On CD | Confidential |
| NAVSEA Drawing | 801-6253822-B | Technical Document Not Included On CD | Confidential |