J-6_USS_GETTYSBURG_Milestones_Final_Rev1_FBO.xlsx
XLSX spreadsheet 205 KB Posted
- Attached to
- USS COWPENS (CG 63) and USS GETTYSBURG (CG 64) Modernization Period (MODPRD) Availabilities
- Solicitation number
- N00024-18-R-4439
About this file
J-6 GETTYSBURG (CG 64) Milestones Rev1
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exec Milestones
| USS GETTYSBURG (CG 64) KEY EVENTS & MILESTONES | ||||
| Milestone / Key Event | Offeror Proposed Date | Proposed 'A+' value | ||
| (Calculated Values) | Schedule Constraint | |||
| Contract Award | Offeror is not to propose. |
Offeror shall assume contract award on or about 16 March 2018 on initial proposals.
Offeror shall assume contract award on or about 6 April 2018 on Final Proposal Revisions.
| Vessel Available | Offeror shall assume "Vessel Available" milestone will occur no earlier than 16 March 2018. | |
| Avail Start at KTR Facility | 0 | Offeror shall assume vessel will be available to commence transit to the contractor's facility no earlier than to "Vessel Available" milestone. |
Offerors outside the vessels homeport shall propose an Availability start date no less than 60 days from contract award.
Offerors outside the vessels homeport shall propose an Availability start date accounting for vessel preparation and transit duration.
Offerors within the vessels homeport shall propose an Availability start date no less than 15 days from contract award.
Offerors within the vessels homeport shall propose an Availability start date no less than 15 days from "Vessel Available" milestone.
GFM Delivery Offeror is not to propose.
GFM will be delivered incrementally. Offeror should not assume GFM will be delivered prior to 12 May 2017.
10% Availability Complete 31-Dec-99 0 Offeror is not to propose.
Date shall be the mathematically solved 10% point between proposed "Avail Start at KTR Facility" and "KTR Contract Complete" Milestones.
20% Complete - Open and Inspect CFRs Due 31-Dec-99 0 Offeror is not to propose.
Date shall be the mathematically solved 20% point between proposed "Avail Start at KTR Facility" and "KTR Contract Complete" Milestones.
25% CONFERENCE 31-Dec-99 0 Offeror is not to propose.
Date shall be the mathematically solved 25% point between proposed "Avail Start at KTR Facility" and "KTR Contract Complete" Milestones.
| Overhauled Equipment installed | 0 | Offeror proposed date shall be no less than 259 days before "KTR Contract Complete" milestone. | |
| Complete Shipyard Combat Systems Space Release Turnover #1 | 0 | Offeror proposed date shall be no less than 103 days before "Distributed Systems Restored" milestone. | |
| Complete Shipyard Combat Systems Space Release Turnover #2 | 0 | Offeror proposed date shall be no less than 110 days before "ALO" milestone. | |
| Complete Shipyard Combat Systems Space Release Turnover #3 | 0 | Offeror proposed date shall be no less than 90 days before "ALO" milestone. | |
| Complete Shipyard Combat Systems Space Release Turnover #4 | 0 | Offeror proposed date shall be no less than 77 days before "ALO" milestone. | |
| Complete Shipyard Combat Systems Space Release Turnover #5 | 0 | Offeror proposed date shall be no less than 60 days before "ALO" milestone. | |
| DOCK | 0 | Offeror shall propose Dock Date IAW Specification 997-11-001 | |
| 20% Dock Period Complete - Dock Related Open and Inspect CFRs Due | 31-Dec-99 | 0 | Offeror is not to propose. |
Date shall be the mathematically solved 20% point between proposed Dock and Undock Milestones.
UNDOCK 0
Offeror shall propose Undock Date IAW Specification 997-11-001
| Firemain Restored (all repairs, piping mods completed, system filled and pressurized to 100 psi from shore) | 0 | Offeror proposed date shall be no later than "UNDOCK" milestone. | |
| CHT system restored | 0 | "CHT system restored" must be complete prior to "AC plant restored." | |
| CHW system filled and circulated | 0 | "CHT system restored" milestone must be complete prior to the completion of this milestone. | |
| Sea Water cooling sys restored | 0 | Must be complete prior to "Distrubuted Systems Restored"" milestone | |
| LP/HP air systems restored and pressurized | 0 | "Sea Water cooling sys restored" milestone must be complete prior to the completion of this milestone. | |
| AC plant restored (2 of 4 ready to operate) | 0 | "CHW system filled and circulated" milestone must be complete prior to the completion of this milestone. | |
| 400 hz converter available | 0 | "AC plant restored (2 of 4 ready to operate)" milestone must be complete prior to the completion of this milestone. | |
| Potable Water sys restored and sanitized | 0 | Must be complete prior to "Habitability Work Complete" milestone | |
| 50% CONFERENCE | 31-Dec-99 | 0 | Offeror is not to propose. |
Date shall be the mathematically solved 50% point between proposed "Avail Start at KTR Facility" and "KTR Contract Complete" Milestones.
Distributed Systems Restored (CS Testing services avalible (FM, CHW, ECW, 60HZ, 400HZ, HP air, LP air available to CS turn over spaces) 0 Offeror proposed date shall be no less than 185 days before "KTR Contract Complete" milestone.
Combat Systems AEGIS Light Off (ALO) 0 Offeror proposed date shall be no less than 168 days before "KTR Contract Complete" milestone.
"Distributed Systems Restored " milestone must be complete prior to the completion of this milestone.
| Habitability Work Complete | |||
| Commence Crew Move Aboard | 0 | Offeror proposed date shall be no less than 98 days before "KTR Contract Complete" milestone. |
"ALO" milestone must be complete prior to the completion of this milestone.
75% CONFERENCE 31-Dec-99 0 Offeror is not to propose.
Date shall be the mathematically solved 75% point between proposed "Avail Start at KTR Facility" and "KTR Contract Complete" Milestones.
Fuel ship for HPT 0 Offeror proposed date shall be no less than 91 days before "KTR Contract Complete" milestone.
"Habitability Work Complete / Commence Crew Move Aboard" milestone must be complete prior to the completion of this milestone.
Engineering Plant Production Completion Date (PCD) 0 Offeror proposed date shall be no less than 84 days before "KTR Contract Complete" milestone.
"Fuel ship for HPT" milestone must be complete prior to the completion of this milestone.
Commence Hot Plant Testing 0 Offeror proposed date shall be no less than 84 days before "KTR Contract Complete" milestone.
"PCD" milestone must be complete prior to the completion of this milestone.
Complete Hot Plant Testing 0 Offeror proposed date shall be no less than 49 days before "KTR Contract Complete" milestone.
"Commence Hot Plant Testing" milestone must be complete prior to the completion of this milestone.
LOA Preps (Start) 0 Offeror proposed date shall be no less than 49 days before "KTR Contract Complete" milestone.
"Complete Hot Plant Testing" milestone must be complete prior to the completion of this milestone.
LOA 0 Offeror proposed date shall be no less than 21 days before "KTR Contract Complete" milestone.
"IBS testing (Complete)" milestone must be complete prior to the completion of this milestone.
Dock Trials 0 Offeror proposed date shall be no less than 14 days before "KTR Contract Complete" milestone.
"LOA" milestone must be complete prior to the completion of this milestone.
Fast Cruise 0 Offeror proposed date shall be no less than 13 days before "KTR Contract Complete" milestone.
"Dock Trials" milestone must be complete prior to the completion of this milestone.
| Crew Rest Period | 0 | |
| HM&E SEA TRIALS (CSST 1) | 0 | Offeror proposed date shall be no less than 7 days before "KTR Contract Complete" milestone. |
"Fast Cruise " milestone must be complete prior to the completion of this milestone.
Transit to NAVSTA 0 Offeror proposed date shall be no less than 0 days before "KTR Contract Complete" milestone.
"HM&E SEA TRIALS (CSST 1)" milestone must be complete prior to the completion of this milestone.
| KTR Contract Complete | 0 | Offeror Shall propose date no later than 24 July 2019. | ||
| "Arrive NAVSTA" milestone must be complete prior to the completion of this milestone. | 24-Jul-19 |
A+ Dates Rev9
| DDG-57 EDSRA 2013 A + DATES | |||||||||||||
| REV9 | 17-Apr-13 | ||||||||||||
| SUN | MON | TUE | WED | THU | FRI | SAT | SUN | MON | TUE | WED | THU | FRI | SAT |
| 3-Feb-13 | 4-Feb-13 | 5-Feb-13 | 6-Feb-13 | 7-Feb-13 | 8-Feb-13 | 9-Feb-13 | 10-Feb-13 | 11-Feb-13 | 12-Feb-13 | 13-Feb-13 | 14-Feb-13 | 15-Feb-13 | 16-Feb-13 |
| XST to BAE | |||||||||||||
| 17-Feb-13 | 18-Feb-13 | 19-Feb-13 | 20-Feb-13 | 21-Feb-13 | 22-Feb-13 | 23-Feb-13 | 24-Feb-13 | 25-Feb-13 | 26-Feb-13 | 27-Feb-13 | 28-Feb-13 | 1-Mar-13 | 2-Mar-13 |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | ||
| 3-Mar-13 | 4-Mar-13 | 5-Mar-13 | 6-Mar-13 | 7-Mar-13 | 8-Mar-13 | 9-Mar-13 | 10-Mar-13 | 11-Mar-13 | 12-Mar-13 | 13-Mar-13 | 14-Mar-13 | 15-Mar-13 | 16-Mar-13 |
| Dock | |||||||||||||
| 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 |
| 17-Mar-13 | 18-Mar-13 | 19-Mar-13 | 20-Mar-13 | 21-Mar-13 | 22-Mar-13 | 23-Mar-13 | 24-Mar-13 | 25-Mar-13 | 26-Mar-13 | 27-Mar-13 | 28-Mar-13 | 29-Mar-13 | 30-Mar-13 |
| 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
| 31-Mar-13 | 1-Apr-13 | 2-Apr-13 | 3-Apr-13 | 4-Apr-13 | 5-Apr-13 | 6-Apr-13 | 7-Apr-13 | 8-Apr-13 | 9-Apr-13 | 10-Apr-13 | 11-Apr-13 | 12-Apr-13 | 13-Apr-13 |
| 25% Conf | |||||||||||||
| 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 |
| 14-Apr-13 | 15-Apr-13 | 16-Apr-13 | 17-Apr-13 | 18-Apr-13 | 19-Apr-13 | 20-Apr-13 | 21-Apr-13 | 22-Apr-13 | 23-Apr-13 | 24-Apr-13 | 25-Apr-13 | 26-Apr-13 | 27-Apr-13 |
| Turnover 1 | Turnover 2 | ||||||||||||
| 55 | 56 | 57 | 58 | 59 | 60 | 61 | 62 | 63 | 64 | 65 | 66 | 67 | 68 |
| 28-Apr-13 | 29-Apr-13 | 30-Apr-13 | 1-May-13 | 2-May-13 | 3-May-13 | 4-May-13 | 5-May-13 | 6-May-13 | 7-May-13 | 8-May-13 | 9-May-13 | 10-May-13 | 11-May-13 |
| Turnover 3 | #1 SWBD | #3 SWBD | #2 SWBD | ||||||||||
| 69 | 70 | 71 | 72 | 73 | 74 | 75 | 76 | 77 | 78 | 79 | 80 | 81 | 82 |
| 12-May-13 | 13-May-13 | 14-May-13 | 15-May-13 | 16-May-13 | 17-May-13 | 18-May-13 | 19-May-13 | 20-May-13 | 21-May-13 | 22-May-13 | 23-May-13 | 24-May-13 | 25-May-13 |
| Turnover 4 | Turnover 5 | ||||||||||||
| 83 | 84 | 85 | 86 | 87 | 88 | 89 | 90 | 91 | 92 | 93 | 94 | 95 | 96 |
| 26-May-13 | 27-May-13 | 28-May-13 | 29-May-13 | 30-May-13 | 31-May-13 | 1-Jun-13 | 2-Jun-13 | 3-Jun-13 | 4-Jun-13 | 5-Jun-13 | 6-Jun-13 | 7-Jun-13 | 8-Jun-13 |
| 2 FO Banks | Turnover 6 | ||||||||||||
| 97 | 98 | 99 | 100 | 101 | 102 | 103 | 104 | 105 | 106 | 107 | 108 | 109 | 110 |
| 9-Jun-13 | 10-Jun-13 | 11-Jun-13 | 12-Jun-13 | 13-Jun-13 | 14-Jun-13 | 15-Jun-13 | 16-Jun-13 | 17-Jun-13 | 18-Jun-13 | 19-Jun-13 | 20-Jun-13 | 21-Jun-13 | 22-Jun-13 |
| Turnover 7 | 50% Conf | 2 FO Banks | Undock | VCHT | |||||||||
| 111 | 112 | 113 | 114 | 115 | 116 | 117 | 118 | 119 | 120 | 121 | 122 | 123 | 124 |
| 23-Jun-13 | 24-Jun-13 | 25-Jun-13 | 26-Jun-13 | 27-Jun-13 | 28-Jun-13 | 29-Jun-13 | 30-Jun-13 | 1-Jul-13 | 2-Jul-13 | 3-Jul-13 | 4-Jul-13 | 5-Jul-13 | 6-Jul-13 |
| SW/CCS DK | PW | FM/AFFF/Halon/LP/HP/ENG Vent/MRG LO | LOFSP | 2 FO Banks | PH Dk BA/CHW/AC/Steer | ||||||||
| 125 | 126 | 127 | 128 | 129 | 130 | 131 | 132 | 133 | 134 | 135 | 136 | 137 | 138 |
| 7-Jul-13 | 8-Jul-13 | 9-Jul-13 | 10-Jul-13 | 11-Jul-13 | 12-Jul-13 | 13-Jul-13 | 14-Jul-13 | 15-Jul-13 | 16-Jul-13 | 17-Jul-13 | 18-Jul-13 | 19-Jul-13 | 20-Jul-13 |
| CRP | 400HZ | DIU Cal | AHSS/JP5 | FUELING | |||||||||
| 139 | 140 | 141 | 142 | 143 | 144 | 145 | 146 | 147 | 148 | 149 | 150 | 151 | 152 |
| 21-Jul-13 | 22-Jul-13 | 23-Jul-13 | 24-Jul-13 | 25-Jul-13 | 26-Jul-13 | 27-Jul-13 | 28-Jul-13 | 29-Jul-13 | 30-Jul-13 | 31-Jul-13 | 1-Aug-13 | 2-Aug-13 | 3-Aug-13 |
| Hab Vent | FO Test Comp | COMX HPT | NAVSSI/67/73 | AHSS Vent Test | |||||||||
| 153 | 154 | 155 | 156 | 157 | 158 | 159 | 160 | 161 | 162 | 163 | 164 | 165 | 166 |
| 4-Aug-13 | 5-Aug-13 | 6-Aug-13 | 7-Aug-13 | 8-Aug-13 | 9-Aug-13 | 10-Aug-13 | 11-Aug-13 | 12-Aug-13 | 13-Aug-13 | 14-Aug-13 | 15-Aug-13 | 16-Aug-13 | 17-Aug-13 |
| 75% Conf | AHSS Cal | ALO | |||||||||||
| 167 | 168 | 169 | 170 | 171 | 172 | 173 | 174 | 175 | 176 | 177 | 178 | 179 | 180 |
| 18-Aug-13 | 19-Aug-13 | 20-Aug-13 | 21-Aug-13 | 22-Aug-13 | 23-Aug-13 | 24-Aug-13 | 25-Aug-13 | 26-Aug-13 | 27-Aug-13 | 28-Aug-13 | 29-Aug-13 | 30-Aug-13 | 31-Aug-13 |
| AHSS Cert | Hab T/O | ||||||||||||
| 181 | 182 | 183 | 184 | 185 | 186 | 187 | 188 | 189 | 190 | 191 | 192 | 193 | 194 |
| 1-Sep-13 | 2-Sep-13 | 3-Sep-13 | 4-Sep-13 | 5-Sep-13 | 6-Sep-13 | 7-Sep-13 | 8-Sep-13 | 9-Sep-13 | 10-Sep-13 | 11-Sep-13 | 12-Sep-13 | 13-Sep-13 | 14-Sep-13 |
| HPT COMP | PCD | Move NOB | LOA Prep | ||||||||||
| 195 | 196 | 197 | 198 | 199 | 200 | 201 | 202 | 203 | 204 | 205 | 206 | 207 | 208 |
| 15-Sep-13 | 16-Sep-13 | 17-Sep-13 | 18-Sep-13 | 19-Sep-13 | 20-Sep-13 | 21-Sep-13 | 22-Sep-13 | 23-Sep-13 | 24-Sep-13 | 25-Sep-13 | 26-Sep-13 | 27-Sep-13 | 28-Sep-13 |
| Fueling/JP5 | |||||||||||||
| 209 | 210 | 211 | 212 | 213 | 214 | 215 | 216 | 217 | 218 | 219 | 220 | 221 | 222 |
| 29-Sep-13 | 30-Sep-13 | 1-Oct-13 | 2-Oct-13 | 3-Oct-13 | 4-Oct-13 | 5-Oct-13 | 6-Oct-13 | 7-Oct-13 | 8-Oct-13 | 9-Oct-13 | 10-Oct-13 | 11-Oct-13 | 12-Oct-13 |
| LOA | LOA | LOA | LOA | LOA/DT | FC | Sea Trials | Sea Trials | Sea Trials | EOA |
&D
EquipCable Turnover R9
USS MITSCHER DDG-57
DDGM BF Critical Path Equipment/Cable Turnover, Power-up & Test Requirement Schedule
REV9, 17APR13
| Equipment | A + | Date | Comments |
| Turnover 1 | |||
| SPS-73 ISEA Disconnect SAOP for relocation | 26-Feb-13 | ||
| All Power Sources and Terminal Boxes for Equipment in A+45, A+55 & A+64 to also include new and upgraded sources.* | 44 | 17-Apr-13 | *To include but not limited to: LC11, 12, 13, 21, 23, 24, 25, 31, 32, 33, 34, 35, 41; PP 3-210-2, 2-299-1, 2-299-2, 01-129-2, 1-268-1, 1-288-1, 2-199-2, 3-219-2, 3-173-3, 4-131-1, 2-199-4, 2-219-1, 1-113-1, 3-116-1, 01-130-0, 1-157-2 as per SIDs. |
paul.r.jackson: Tim Gudge:
This is a list of all new or fully upgraded power panels that power 1st-3rd T/O equipment. Some will be removed and put in 4th T/O as they are secondary sources.
| GEDMS Mesh B (BSE B1-B10) | 44 | 17-Apr-13 | |
| GEDMS Mesh A BSEs and power cables affecting 1st Turnover IOUs* | 44 | 17-Apr-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A03: J2: 3-210-2-1L-C) (BSE A10: J2: 3-210-2-1L-G) (BSE A04: J2 : LC25-1L-A8) |
robert.gudge: robert.gudge:
have to check power source.
| IOUs: 31, 32, 34, 42, 72, 82 | 44 | 17-Apr-13 | |
| USEs 31A, 31B, 32A, 32B, 34A, 34B, 42A, 72A, 82A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 44 | 17-Apr-13 | |
| C-DR Boxes 12, 13, 14, 14A, 15, 15A, 16, 24, 37 | 44 | 17-Apr-13 | Install FDS ITB Modification Kit for the following ITB's; 12, 12A, 13, 13A, 14, 15, 16, 16A, 17, 17A, 25 & 25A. |
| Turnover 2 | |||
| UCCs 1 & 2 | 51 | 24-Apr-13 | |
| RSC DCC, C/O SW & Speaker | 51 | 24-Apr-13 | Hold Keyboard, 40" Monitor & Printer for later installation per SMR direction. |
| RSC Repair 5, C/O SW, Speaker & Access Cut | 51 | 24-Apr-13 | Hold Keyboard for later installation per SMR direction. |
| TIWS (CCS) | 51 | 24-Apr-13 | LAN Drop & Power Outlet |
| IOUs: 73, 74, 83, 84, 94 | 51 | 24-Apr-13 | |
| GEDMS Mesh A BSEs and power cables affecting 2nd Turnover IOUs* | 51 | 24-Apr-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A09: J2: LC33-1L-H1) (BSE A06: J2: LC25-1L-A12) |
robert.gudge: robert.gudge:
have to check power source.
| C-DR Boxes 7, 8, 8A, 11, 25, 26, 31 | 51 | 24-Apr-13 | Install FDS ITB Modification Kit for the following ITB's; 7, 7A, 11, 11A, 26, & 26A. |
| USEs 73A, 74A, 74C, 83A, 83B, 84A, 94A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 51 | 24-Apr-13 | |
| Turnover 3 | |||
| Electric Plant DIU 1 (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| Propulsion DIU 4 (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| UCC 3 | 60 | 03-May-13 | |
| ECs 1A, 1B (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| FADC 1 | 60 | 03-May-13 | |
| RSC Repair 2, C/O SW, Speaker | 60 | 03-May-13 | Hold Keyboard for later installation per SMR direction. |
| TIWS (MER 1) | 60 | 03-May-13 | LAN Drop & Power Outlet |
| RSC CSMC, C/O SW, Speaker | 60 | 03-May-13 | Hold Keyboard for later installation per SMR direction. |
| Fire Detection System ITB Upgrade Electrical Mods & Cabling for IOUs in T/Os 1, 2, and 3. | 60 | 03-May-13 | |
| IOUs: 22, 33, 61, 62 | 60 | 03-May-13 | |
| GEDMS Mesh A BSEs and power cables affecting 3rd Turnover IOUs* | 60 | 03-May-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A02: J2: (3-210-2-1L-D) |
robert.gudge: robert.gudge:
Have to check power source.
robert.gudge: robert.gudge:
have to check power source.
paul.r.jackson: Tim Gudge:
| This is a list of all new or fully upgraded power panels that power 1st-3rd T/O equipment. Some will be removed and put in 4th T/O as they are secondary sources. | C-DR Boxes 19, 21, 22, 23, 23A | 60 | 03-May-13 | Install FDS ITB Modification Kit for the following ITB's; 20, 20A, 22, 23, 23A, 24 & 24A. |
| USEs 22A, 33A, 61A, 62A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 60 | 03-May-13 | ||
| F/O, L/O & CRP valves associated with SCD 71604K, Including electrical hook-up, in MER1 | 60 | 03-May-13 | 1A/1B F/O Filt/Sep Outlet, #1MRG Pur Suct/Fill, #1CRP Pur Suct/Fill | |
| #1 SWBD and related Load Centers and 1SF Special Frequency SWBD (2-Days) | 63 | 06-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| #3 SWBD and related Load Centers and 2SF Special Frequency SWBD (2-Days) | 65 | 08-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| #2 SWBD/1SA and any outstanding work/Final Ringout (2-Days, Ships's 60HZ PWR Secured) | 67 | 10-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| Turnover 4 | ||||
| All Power Sources & Terminal Boxes for Equipment in A+73, A+83 and A+92* | 72 | 15-May-13 | *To include but not limited to: PP 02-167-1, 01-178-2, 2-116-1, 3-173-3, 2-48-1, 2-299-1, 3-258-1, 2-405-2, 1-143-2, 2-282-1, 3-256-2, 3-284-3, 04-154-2, 3-442-2, 3-442-1, 1-157-2, 03-142-2, 03-141-1, 03-154-2, 03-133-1, 03-129-1, 03-132-1, 03-130-1, 3-213-2, 3-255-1 as per SIDs. |
paul.r.jackson: Tim Gudge:
This is a list of all new or fully upgraded power panels that feed 4th-6th T/O equipment. Some will be added from the list in 1st T/O.
| Electric Plant DIUs 2 & 3 (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| Propulsion DIU 5 (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| UCC 4 | 72 | 15-May-13 | |
| RSC Repair 3, C/O SW, Speaker | 72 | 15-May-13 | Hold Keyboard for later installation per SMR direction. |
| ECs 2A, 2B (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| FADCs 2 & 3 | 72 | 15-May-13 | |
| TIWS (MER 2) | 72 | 15-May-13 | LAN Drop & Power Outlet |
| Aft Steering Unit (ASU) | 72 | 15-May-13 | |
| Local Control Steering Units (LCUs 1 - 4) | 72 | 15-May-13 | |
| IOUs: 11, 13, 14, 41, 51, 81 | 72 | 15-May-13 | |
| C-DR Boxes 1, 10, 17, 27, 28, 28A, 30, 33, 34, 35, 36 | 72 | 15-May-13 | Install FDS ITB Modification Kit for the following ITB's; 1, 10, 18, 27, 27A, 28, & 30. |
| USE 11A, 13A, 14A, 41A, 51A, 81A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 72 | 15-May-13 | |
| F/O, L/O & CRP valves associated with SCD 71604K, Including electrical hook-up, in MER2 | 72 | 15-May-13 | 2A/2B F/O Filt/Sep Outlet, #2MRG Pur Suct/Fill, #2CRP Pur Suct/Fill |
| Turnover 5 | |||
| Ship Control Console (SCC) | 81 | 24-May-13 | |
| BCCS | 81 | 24-May-13 | |
| HFS | 81 | 24-May-13 | |
| IBNS Racks 1, 2, including HS Firewall, UPS & C/O Switches | 81 | 24-May-13 | |
| IBNS Radar Rack | 81 | 24-May-13 | |
| Trigger/Video Amp/Nulka Processor | 81 | 24-May-13 | |
| IBNS NAV 1 computer (Pilot House) | 81 | 24-May-13 | |
| IBNS NAV 2 computer (Chart Room) | 81 | 24-May-13 | |
| IBNS NAV 3 computer (CIC) | 81 | 24-May-13 | |
| IBNS NAV 4 computer (CO's Laptop) | 81 | 24-May-13 | |
| SPS-73 SAOP, Ethernet SW, C/O SW & UPS | 81 | 24-May-13 | |
| NAVSSI Inputs to IBNS/SAOP | 81 | 24-May-13 | |
| ELS & LAN Drops/Receptacles | 81 | 24-May-13 | |
| RSC CIC & C/O Switch | 81 | 24-May-13 | Hold Keyboard for later installation per SMR direction. |
| Pilot House IBNS Trainer / RSC | 81 | 24-May-13 | Hold Keyboard, Training Monitors, Joystick & Cables for later installation per SMR direction. |
| IOUs: 21, 23, 53, 71, 91, 93 | 81 | 24-May-13 | |
| GEDMS Mesh A BSEs and power cables affecting 5th Turnover IOUs* | 81 | 24-May-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A01: J2: (3-210-2-1L-A) (BSE A08: J2: LC33-1L-F) (BSE A07: J2; LC25-1L-A10) (BSE A05: J2: LC25-1L-A11) |
robert.gudge: robert.gudge:
Have to check power source.
robert.gudge: robert.gudge:
have to check power source.
paul.r.jackson: Tim Gudge:
| This is a list of all new or fully upgraded power panels that feed 4th-6th T/O equipment. Some will be added from the list in 1st T/O. | C-DR Boxes 4, 6, 5, 5A, 9, 18, 20, 32 | 81 | 24-May-13 | Install FDS ITB Modification Kit for the following ITB's; 2, 4, 5, 6, 8, 8A, 9, 19, 19A, 21, & 21A. |
| Oil Lab PC (SCD 70403K) | 81 | 24-May-13 | Includes all cabling, connections, Oil Lab PC, C-DR 40-43, SCD 70403K, | |
| 2 Fuel banks closed & ready to test (any two from groups 1 through 6) | 89 | 01-Jun-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) | |
| Turnover 6 | ||||
| Continuous Thermal Monitoring System | 92 | 04-Jun-13 | ADACS unit in MER2, including power and all hook-ups | |
| GEDMS Maintenance Group | 92 | 04-Jun-13 | ||
| GEDMS Mesh A BSE A1-A10 Light Off | 92 | 04-Jun-13 | ||
| Turnover 7 | ||||
| SPS-73 ISEA Connectorize SAOP | 98 | 10-Jun-13 | ||
| DVSS - ALL VIROEs, CJBs, Cables (*) | 98 | 10-Jun-13 | ||
| IOU: 92 & Associated UPS, Relay Enclosure, Junction Boxes, and C/O Switches | 98 | 10-Jun-13 | ||
| C-DR Box 2 & 2A | 98 | 10-Jun-13 | ||
| 2 Fuel banks closed & ready to test (any two from groups 1 through 6) | 106 | 18-Jun-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) | |
| CCS Deck COMPLETE | 113 | 25-Jun-13 | ||
| Potable Water System, incl Tanks, TBs, MOVs, TLIs & Modified Pump Controllers | 114 | 26-Jun-13 | ||
| Ventilation - Engineering, CPS Zone 4, Exhaust & Supply | 116 | 28-Jun-13 | E=SS01-150-1, SS01-150-3, ES01-146-1, ES01-146-3, SS2-203-1, ES01-191-1, SS3-251-2, ES01-258-2, SS2-262-2, SS2-270-1, ES01-243-1, ES01-255-2 |
CPS=SS01-301-2, SS01-305-2, ES01-308-2, ES01-309-2, ES01-308-4
| LO Filter Separator Purifier (SCD 76253K) | 119 | 01-Jul-13 | |
| Remaining fuel tank groups closed & ready to test - SCD 70403K COMPLETE | 120 | 02-Jul-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) |
| All TLI's not previously turned over, Including Redundant, Radar/TDR and associated TBs, JP-5, all electrical work COMPLETE, SCDs 77829K/77269K COMPLETE | 120 | 02-Jul-13 | SCD 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) |
| Pilot House Deck COMPLETE | 123 | 05-Jul-13 | |
| AHSS Install Complete, Including Vent Mod | 131 | 13-Jul-13 | |
| Digital Indicators SCD 77427 COMPLETE | 138 | 20-Jul-13 | Placeholder |
| (*) Install all DVSS Cameras as directed by PMR |
| 70403 | Digital Fuel Fill Control System |
| 71604 | Machinery Control Station/Damage Control Station Upgrade |
| 71605 | Advanced Galley Mod |
| 71615 | Digital Video Surveillance System |
| 71726 | Full IBNS Upgrade |
| 71734 | Joint Biological Point Detect System |
| 77269 | Redundant TLI in GEN HD TK |
| 73088 | Gigabit Ethernet Data Multiplex System |
| 73622 | H2S Detector System in VCHT Rooms |
| 76034 | Emer JP5 Fill to #3 GEN HD TK |
| 76253 | Lube Oil Filter Separator Purifier |
| 76974 | Moriah WS HW For DDG Mod Plan |
| 77259 | EM Log Rpl AN/WSN-9(V)1 Digital Hybrid Speed Log (DHYSL) |
| 77427 | Digital Indicators |
| 77829 | Radar and TDR TLI's for DFM/JP5/PotWtr |
&P
Shipbd Test Major Milestone R9
| DDG 57 GEDMS/MCS/IBNS/DVSS/DFC INTEGRATED TEST SCHEDULE | |||||
| INTERNAL MAJOR MILESTONES - REV9, 19APR13 | |||||
| System | Scheduled | Revised (4/17/13) | Actual End | A+ Dates | |
| Ship Move to BAE | Thursday, February 07, 2013 | 2/7/13 | |||
| DOCK SHIP (Tentative) | Tuesday, March 05, 2013 | 3/5/13 | 1 | ||
| 1 | TURNOVER 1 | Wednesday, April 17, 2013 | 3/15/13 | 44 | |
| 2 | TURNOVER 2 | Wednesday, April 24, 2013 | 51 | ||
| 3 | GEDMS MESH B POWER UP/INITIAL SW LOAD (ISEA) | Monday, April 29, 2013 | 56 | ||
| 4 | DFC (LM2500) TRAINING (ISEA) | Wednesday, May 01, 2013 | 58 | ||
| 7 | TURNOVER 3 | Friday, May 03, 2013 | 60 | ||
| 6 | #1/3/2 SWBD/LC/1SF/2SF TIE-IN/CTM INSTALL - 6-11 MAY | Monday, May 06, 2013 | 63 | ||
| GEDMS TEMPORARY 3GMG (COMMS AVAILABLE)(ISEA) | Wednesday, May 08, 2013 | 65 | |||
| 8 | START FDS HARNESS CHECKS (T/O 1,2,3) (ISEA) | Wednesday, May 08, 2013 | 65 | ||
| 9 | TURNOVER 4 | Wednesday, May 15, 2013 | 72 | ||
| 10 | START FDS INITIAL POWER UP (ISEA) | Thursday, May 16, 2013 | 73 | ||
| 11 | MCS PWR UP/EC/MCS SW LOAD (INCL TIWS) (ISEA) | Thursday, May 16, 2013 | 73 | ||
| 13 | MCS/EC GRND ISO/SIG VERIFICATION/COLD TESTING(MER1) | Saturday, May 18, 2013 | 75 | ||
| 14 | TURNOVER 5 | Friday, May 24, 2013 | 81 | ||
| 16 | MCS/EC GRND ISO/SIG VERIFICATION/COLD TESTING(MER2) | Saturday, May 25, 2013 | 82 | ||
| 18 | START DC SENSOR TESTING (ISEA) | Monday, May 27, 2013 | 84 | ||
| 19 | IBNS POWER UP (ISEA) | Monday, May 27, 2013 | 84 | ||
| 21 | 2 FO TANK GROUPS TURNED OVER START TLI/FCS TESTING | Saturday, June 01, 2013 | 89 | ||
| 22 | TURNOVER 6 | Monday, June 03, 2013 | 91 | ||
| 24 | IBNS SIGNAL VERIFICATION/SW LOAD (ISEA) | Wednesday, June 05, 2013 | 93 | ||
| GEDMS MESH A POWER UP (ISEA) | Wednesday, June 05, 2013 | 93 | |||
| 23 | TURNOVER 7 | Monday, June 10, 2013 | 98 | ||
| 24 | 2 FO TANK GROUPS TURNED OVER CONT' TLI/FCS TESTING | Tuesday, June 18, 2013 | 106 | ||
| UNDOCK | Monday, June 03, 2013 | Thursday, June 20, 2013 | 108 | ||
| 20 | VCHT (TANKS/PIPING/PUMPS) | Friday, June 14, 2013 | Friday, June 21, 2013 | 109 | |
| 26 | SWS SYSTEM (PIPING/PUMPS/MOVs) | Tuesday, June 18, 2013 | Tuesday, June 25, 2013 | 113 | |
| DECK IN CCS COMPLETE | Tuesday, June 25, 2013 | 113 | |||
| POTWTR SYSTEM (PIPING/TANKS/PUMPS/MOVs) | Wednesday, June 19, 2013 | Wednesday, June 26, 2013 | 114 | ||
| 27 | FM/AFFF/HALON (PIPING/PUMPS/MOVs) | Friday, June 14, 2013 | Friday, June 28, 2013 | 116 | |
| 28 | VENT SYSTEM (FUELING/HPT, ENG/CPS-Z4) | Wednesday, June 19, 2013 | Friday, June 28, 2013 | 116 | |
| 29 | LP/HP AIR (PIPING/VALVES/COMPRESSORS) | Friday, June 21, 2013 | Friday, June 28, 2013 | 116 | |
| 30 | MRG LO SYSTEM (PIPING/MRGs/PUMPS/FILTERS/COOLERS) | Saturday, June 22, 2013 | Saturday, June 29, 2013 | 117 | |
| 31 | LO FILTER SEPARATOR PURIFIER | Saturday, June 22, 2013 | Monday, July 01, 2013 | 119 | |
| REMAINING FO TANKS TURNED OVER TO TEST | Tuesday, June 25, 2013 | Tuesday, July 02, 2013 | 120 | ||
| 32 | DECK IN PILOT HOUSE COMPLETE | Friday, July 05, 2013 | 123 | ||
| BLEED AIR (PIPING/VALVES) | Thursday, June 27, 2013 | Saturday, July 06, 2013 | 124 | ||
| 33 | STEERING (RUDDERS/RAMS/HPUs) | Thursday, June 27, 2013 | Saturday, July 06, 2013 | 124 | |
| 34 | AC PLANTS / CHILL WATER SYSTEM | Friday, June 28, 2013 | Saturday, July 06, 2013 | 124 | |
| EOSS VALIDATION (ISEA) | Wednesday, July 03, 2013 | Sunday, July 07, 2013 | 125 | ||
| 35 | CPP/CRP (PIPING/SHAFTS/PUMPS/HOPM/OD BOX) | Monday, June 24, 2013 | Sunday, July 07, 2013 | 125 | |
| FCS TRAINING FOR SHIPS FORCE (ISEA/NAG) | Wednesday, June 26, 2013 | Monday, July 08, 2013 | 126 | ||
| DVSS OPERATOR TRAINING (ISEA) | Friday, July 05, 2013 | Monday, July 08, 2013 | 126 | ||
| 36 | LUBE OIL FILTER SEPARATOR TRAINING (ISEA) | Wednesday, June 26, 2013 | Monday, July 08, 2013 | 126 | |
| 400HZ AVAILABLE | Tuesday, July 02, 2013 | Tuesday, July 09, 2013 | 127 | ||
| DIU CALIBRATIONS COMPLETE | Friday, July 05, 2013 | Friday, July 12, 2013 | 130 | ||
| AHSS SYSTEM COMPLETE (INCL VENT MOD) | Saturday, July 06, 2013 | Saturday, July 13, 2013 | 131 | ||
| JP5 (TANKS/TLIs/PIPING/PUMPS/FILTERS) | Saturday, July 06, 2013 | Saturday, July 13, 2013 | 131 | ||
| 37 | RSC TRAINING (ISEA) | Monday, July 01, 2013 | Monday, July 15, 2013 | 133 | |
| 38 | FUEL SHIP | Wednesday, July 03, 2013 | Wednesday, July 17, 2013 | 135 | |
| TIWS TRAINING (ISEA) | Tuesday, July 09, 2013 | Monday, July 22, 2013 | 140 | ||
| VENT SYSTEM (HAB, CPS-Z1-3) | Thursday, July 18, 2013 | Thursday, July 25, 2013 | 143 | ||
| 39 | F/O TESTING COMPLETE | Saturday, July 13, 2013 | Saturday, July 27, 2013 | 145 | |
| 40 | HOT PLANT TESTING COMMENCE | Monday, July 15, 2013 | Monday, July 29, 2013 | 147 | |
| 41 | NAVSSI/IFF/67/73 RADAR AVAILABLE FOR IBNS TESTING | Tuesday, July 23, 2013 | Tuesday, July 30, 2013 | 148 | |
| AHSS VENT VELOCITY TESTING (MSR/BIW) | Monday, July 15, 2013 | Wednesday, July 31, 2013 | 149 | ||
| 42 | AHSS CAL/TESTING/TRAINING (ISEA/OEM) | Thursday, August 01, 2013 | Thursday, August 15, 2013 | 164 | |
| AEGIS LIGHT OFF | Saturday, August 03, 2013 | Saturday, August 17, 2013 | 166 | ||
| 43 | AHSS CERTIFICATION (NHRC) | Monday, August 05, 2013 | Monday, August 19, 2013 | 168 | |
| 44 | HAB TURNOVER / MOVE ABOARD COMMENCE | Thursday, August 08, 2013 | Thursday, August 22, 2013 | 171 | |
| HOT PLANT TESTING COMPLETE | Wednesday, August 21, 2013 | Wednesday, September 04, 2013 | 184 | ||
| 46 | PCD | Thursday, August 22, 2013 | Thursday, September 05, 2013 | 185 | |
| 47 | SHIP MOVES TO NAVSTA | Friday, August 23, 2013 | Friday, September 06, 2013 | 186 | |
| 48 | SHIP LOA PREP | Monday, August 26, 2013 | Monday, September 09, 2013 | 189 | |
| MCS OVER THE SHOULDER TRAINING (ISEA ~5 days) | Monday, August 26, 2013 | Monday, September 09, 2013 | 189 | ||
| IBNS OPERATOR TRAINING | Tuesday, September 03, 2013 | Monday, September 16, 2013 | 196 | ||
| 49 | FUELING / RECEIVE JP5 | Thursday, September 05, 2013 | Thursday, September 19, 2013 | 199 | |
| IBNS IOS/IBNS OPERATOR TRAINING BUFFER | Monday, September 09, 2013 | Monday, September 23, 2013 | 203 | ||
| LOA | Monday, September 16, 2013 | Monday, September 30, 2013 | 210 | ||
| 51 | DOCK TRIALS | Friday, September 20, 2013 | Friday, October 04, 2013 | 214 | |
| 52 | FAST CRUISE | Saturday, September 21, 2013 | Saturday, October 05, 2013 | 215 | |
| 53 | SEA TRIALS | Tuesday, September 24, 2013 | Tuesday, October 08, 2013 | 218 | |
| IBNS TRAINING UNDERWAY | Tuesday, September 24, 2013 | Tuesday, October 08, 2013 | 218 | ||
| 54 | END OF AVAIL | Friday, September 27, 2013 | Friday, October 11, 2013 | 221 | |
| 55 | FINAL SOFTWARE LOAD | Post Sea Trials | |||
| 56 | TLI TESTING (FUELING AT SEA) | Post Sea Trials | |||
| FOLLOW-ON IBNS MAINTENANCE TRAINING (TBD) | Post Sea Trials |
GEDMS Checklist
| DDG61 GEDMS CHECKLIST | |||||||||
| BSE | BSE | IOU | C-DR | NEW | USE-A | USE-B | |||
| A1 | Weight Rm | B1 | Supply Strm 4 | 11 | 30 | ET Shop | 11A | ||
| A2 | DC Locker | B2 | Crew 5 | 13 | 28 | 28A | Load Center 1 | 13A | |
| A3 | PW 1-254-6-L | B3 | Supply Support | 14 | 27 | CO PW 02-154-1-L | 14A | ||
| A4 | PW 1-174-01-L | B4 | Pwr Convers Rm | 21 | 18 | Supply Strm 3 | |||
| A5 | CSMC | B5 | Crew 2 | 22 | 21 | EM Shop | 22A | ||
| A6 | PW 1-78-01-L | B6 | Fwd IC | 23 | 20 | PW 2-338-1-L | |||
| A7 | Sonar | B7 | AUX 1 | 31 | 12 & 13 | MER 2 | 31A | 31B | |
| A8 | Crew 1 | B8 | Supply Strm 1 | 32 | 16 | CCS | 32A | 32B | |
| A9 | MER 1 | B9 | Crew 4 | 33 | 23 | 23A | DC Locker | 33A | |
| A10 | Crew 3 | B10 | Crew 6 | 34 | 37 | MER 2 | 34A | 34B | |
| 41 | 17 | Aft IC | 41A | ||||||
| 42 | 24 | CSER 3 | 42A | ||||||
| 51 | 1 | Fwd IC | 51A | ||||||
| 53 | 5 | 5A | TR 2-116-1-T | ||||||
| 54 | 31 | MER 1 | 54A | ||||||
| 61 | 22 | Rep 3 | 61A | ||||||
| 62 | 19 | Aft Steering | 62A | ||||||
| 71 | 9 | Radio | |||||||
| 72 | 15 | Rep 5 | 72A | ||||||
| 73 | 26 | CSMC | 73A | ||||||
| 74 | 11 | MER 1 | 74A | 74C | |||||
| 81 | 10 | CSER 2 | 81A | ||||||
| 82 | 14 | 14A | OPS Office | 82A | |||||
| 83 | 8 | 8A | Aux 1 | 83A | |||||
| 84 | 25 | Admin | 84A | ||||||
| 91 | 6 | GSE Shop/Gage Cal | |||||||
| 92 | 2 | 2A | Sonar 3 | ||||||
| 93 | 4 | CSER 1 | |||||||
| 94 | 7 | Sec Force Locker | 94A | ||||||
| DELETED: | IOU 12 / C-DR29 IOU 52 / C-DR3 |
Tota # of USE = 26
ALO CRS
| USS OSCAR AUSTIN DDG79 FY18 DMP AEGIS Light Off Compartment Release Schedule | |||||||||||||||
| COMPARTMENT NUMBER | COMPARTMENT NAME | MSR turnover to AIT | Date | A = SOA | 8-Jan-18 | SUPPORT SERVICES: Gray Fill Indicates Services Required | |||||||||
| 60 Hz | 400 Hz | A/C | ECW | Chill Water | Fire Main | Dry Air | HP Air | LP Air | |||||||
| 4-94-0-C | IC & Gyro Room #1 (FWD) | 158 | 15-Jun-18 | 93 | 207 | 3-Aug-18 | |||||||||
| 3-300-0-C | IC & Gyro Room #2 (AFT) | 158 | 15-Jun-18 | 93 | 207 | 3-Aug-18 | |||||||||
| 03-128-0-C | Radar Room #1 | 200 | 27-Jul-18 | 66 | 221 | 17-Aug-18 | |||||||||
| 06-157-0-T | Mast and Access Trunk | 221 | 17-Aug-18 | 70 | 235 | 31-Aug-18 | |||||||||
| 03-142-0-C | Radar Room #2 | 207 | 3-Aug-18 | 63 | 235 | 31-Aug-18 | |||||||||
| 2-53-1-C | CSER #1 | 207 | 3-Aug-18 | 63 | 235 | 31-Aug-18 | |||||||||
| 2-126-2-C | CSER #2 | 193 | 20-Jul-18 | 62 | 241 | 6-Sep-18 | |||||||||
| 1-300-0-C | CSER #3 | 193 | 20-Jul-18 | 62 | 241 | 6-Sep-18 | |||||||||
| 1-126-0-C | Combat Information Center | 193 | 20-Jul-18 | 62 | 241 | 6-Sep-18 | |||||||||
| 05-131-0-Q | Director Equipment Room #1 | 228 | 24-Aug-18 | 58 | 241 | 6-Sep-18 | |||||||||
| 2-50-2-C | Sonar Control Room | 221 | 17-Aug-18 | 58 | 241 | 6-Sep-18 | |||||||||
| 1-18-0-Q | Sonar Equipment Room #1 | 221 | 17-Aug-18 | 42 | 228 | 24-Aug-18 | |||||||||
| 2-18-0-Q | Sonar Equipment Room #2 | 221 | 17-Aug-18 | 42 | 228 | 24-Aug-18 | |||||||||
| 3-18-0-Q | Sonar Equipment Room #3 | 221 | 17-Aug-18 | 42 | 228 | 24-Aug-18 | |||||||||
| 01-130-2-C | SSES | 242 | 7-Sep-18 | 46 | 241 | 6-Sep-18 | |||||||||
| 2-220-1-Q | SNAP II Computer Room (LAN Room) | 186 | 13-Jul-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-128-1-Q | SPY Array Room #1 (FWD/STBD) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-128-2-Q | SPY Array Room #2 (FWD/PORT) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-158-3-Q | SPY Array Room #3 (AFT/STBD) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-158-2-Q | SPY Array Room #4 (AFT/PORT) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 01-130-0-Q | Combat Systems Maintenance Central | 235 | 31-Aug-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 2-126-1-C | Communications Center | 200 | 27-Jul-18 | 39 | 235 | 31-Aug-18 | |||||||||
| 3-126-2-Q | Power Supply/Conversion Room | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 3-319-0-Q | Power Conversion Room | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 4-42-0-Q | Sonar Cooling Equipment Room | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 4-126-0-E | Auxiliary Machinery Room #1 | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 1-78-1-Q | VLS Fan Room fwd | 249 | 14-Sep-18 | 28 | 228 | 24-Aug-18 | |||||||||
| 1-78-2-Q | VLS Fan Room fwd | 249 | 14-Sep-18 | 28 | 228 | 24-Aug-18 | |||||||||
| 3-362-0-Q | VLS Fan Room aft | 249 | 14-Sep-18 | 28 | 228 | 24-Aug-18 | |||||||||
| 04-130-0-C | Pilot House | 228 | 24-Aug-18 | 23 | 228 | 24-Aug-18 | |||||||||
| 2-338-0-M | VLS Magazine #2 (AFT) | 242 | 7-Sep-18 | 22 | 228 | 24-Aug-18 | |||||||||
| 2.5-78-0-M | VLS Magazine #1 (FWD) | 242 | 7-Sep-18 | 22 | 228 | 24-Aug-18 | |||||||||
| 02-112-0-Q | CIWS Workshop #1 | 242 | 7-Sep-18 | 14 | 221 | 17-Aug-18 | |||||||||
| 2-153-2-C | Tomahawk Equipment Room | 221 | 17-Aug-18 | 14 | 221 | 17-Aug-18 | |||||||||
| 03-142-1-C | CSER #4 | 242 | 7-Sep-18 | 7 | 221 | 17-Aug-18 | |||||||||
| 04-150-0-C | Chart Room (w/4) | 249 | 14-Sep-18 | 7 | 221 | 17-Aug-18 | |||||||||
| 03-142-2-Q | Electric Load Center #1 | 256 | 21-Sep-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 01-274-1-C | Radar Room #3 | 235 | 31-Aug-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 03-112-0-C | CIWS Control Room #1 | 242 | 7-Sep-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 1-46-0-M | 5"/54 Loader Drum & Fan Room | 242 | 7-Sep-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 2-458-0-Q | MFTA Winch Room | 256 | 21-Sep-18 | 13 | 228 | 24-Aug-18 | |||||||||
| 2-157-1-C | Radio Transmitter Room | 256 | 21-Sep-18 | 11 | 228 | 24-Aug-18 | |||||||||
| 01-300-0-Q | CIWS Wpn & Avn Ord Eqpt Wks | 256 | 21-Sep-18 | 11 | 228 | 24-Aug-18 | |||||||||
| 02-299-0-C | CIWS Control Room#2 | 256 | 21-Sep-18 | 11 | 228 | 24-Aug-18 | |||||||||
| 1-314-0-C | CSER 3 Annex | 242 | 7-Sep-18 | 21 | 241 | 6-Sep-18 | |||||||||
| 1-268-0-C | CCS (VLS Alarms) | 249 | 14-Sep-18 | 7 | 235 | 31-Aug-18 | |||||||||
| Fwd 03 lvl, Aft 05 lvl | AN/SPY-1 Antenna Arrays | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 04-272-0-Q | Director Equipment Room #2 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 03-282-0-Q | Director Equipment Room #3 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 1-97-2-Q | VLS Service Interface Room (FWD) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 02 LVL FR 338-370 | Missile Deck (AFT) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 01 LVL FR 78-110 | Missile Deck (FWD) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 01-(46-78)-0-M | 5"/54 CAL Gun Mount (MT 51) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 06-150-0/Deck | FCS Director #1 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 05-280-0/Deck | FCS Director #2 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 04-292-0/Deck | FCS Director #3 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 01-(247-257) | SVTT (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 01-(240-250) | SVTT (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 2-450-1-Q | NIXIE Room | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(200-220)-1 | Decoy Launchers (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(200-220)-2 | Decoy Launchers (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(220-237) | NULKA Launchers (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(220-237) | NULKA Launchers (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 03-(142-158)-3 | EW Array SLQ-32 (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 03-(142-158)-4 | EW Array SLQ-32 (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 03-(112-128)-0 | CIWS (MT 21) FWD | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(300-316)-0 | CIWS (MT 22) AFT | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 2-442-6-Q | Bathythermograph Room | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 0 1/2-28-0-Q | Dome Equipment Room | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 1-304-2-M | Torpedo, Missile & Rocket Mag | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 01-110-3-Q | Fan Room PZ #1 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||||||||||
| 01-126-3-Q | Fan Room PZ #2 |
Mike Kraft: Mike Kraft:
| supply AUX 1 fan SS 01-150-1 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | |||
| 01-158-0-Q | Fan Room PZ #2 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 01-190-1-Q | Fan Room PZ #2 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 01-200-2-Q | Fan Room PZ #2 |
Mike Kraft: Mike Kraft:
| supplies MER 1 fan SS 2-203-1 | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
| 01-240-01-Q | Fan Room PZ #3 |
Mike Kraft: Mike Kraft:
| supply for MER2 (fans SS 262-2 and SS 2-270-1) and AUX 2 (SS 3-251-2) | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
| 01-300-2-Q | Fan Room |
Mike Kraft: Mike Kraft:
| Aft VCHT supply fan 4-330-1 ? | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
| 01-338-3-Q | Fan Room |
Mike Kraft: Mike Kraft:
supplies #3GTG and aft steering Mike Kraft: Mike Kraft:
supply AUX 1 fan SS 01-150-1 Mike Kraft: Mike Kraft:
supplies MER 1 fan SS 2-203-1 Mike Kraft: Mike Kraft:
| supply for MER2 (fans SS 262-2 and SS 2-270-1) and AUX 2 (SS 3-251-2) | 224 | 20-Aug-18 | 200 | 27-Jul-18 | |||
| 01-338-4-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 03-142-3-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 03-142-4-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 03-152-2-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 2-42-2-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 2-430-1-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 3-164-2-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
Conf day calc
| 347 | 87 | 174 | 260 | |
| KTR days | 20 | 25% | 50% | 75% |
CS Turnovers USS GETTYSBURG CG 64 FY18 EDSRA Combat Systems (CS) Turnovers
| Offeror proposed date shall be no less than X days before Completion milestone. | MSR/AIT Completion milestone | ||
| COMPARTMENT NUMBER | COMPARTMENT NAME |
| COMBAT SYSTEMS TURNOVER #1 (MSR to AIT) | |||
| 2-127-0-C | IC & GYRO RM #1 (FWD) | 103 | Distrubited Systems Restored |
| 3-382-0-C | IC & GYRO RM #2 (AFT) | 103 | Distrubited Systems Restored |
| 01-138-0-C | COMPUTER CENTRAL | 103 | Distrubited Systems Restored |
| 02-138-0-C | COMBAT INFO CENTER | 103 | Distrubited Systems Restored |
| 02-174-0-C | SONAR CONTROL RM | 103 | Distrubited Systems Restored |
| 1-159-0-Q | C/S MAINT CENTRAL | 103 | Distrubited Systems Restored |
| 2-236-0-Q | AEGIS COOLING RM #1 (C&D SKID) | 103 | Distrubited Systems Restored |
| 3-382-2-Q | AEGIS COOLING RM #2 (SPY SKID) | 103 | Distrubited Systems Restored |
| 5-220-0-E | AMR 1 (UPPER DK) (SPY SKID) | 103 | Distrubited Systems Restored |
| 5-220-0-E | AMR 1 (UPPER DK) 400HZ | 103 | Distrubited Systems Restored |
| 3-393-4-Q | 400 HZ CONV RM | 103 | Distrubited Systems Restored |
| 03-220-0-Q | EW EQUIP COOLING RM (EW SKID) | 103 | Distrubited Systems Restored |
| 4-58-0-Q | DOME EQUIP RM (SONAR SKID) | 103 | Distrubited Systems Restored |
| 1-28-0-Q | SONAR RM #1 | 103 | Distrubited Systems Restored |
| 2-28-0-Q | SONAR RM #2 | 103 | Distrubited Systems Restored |
| 3-28-0-Q | SONAR RM #3 | 103 | Distrubited Systems Restored |
| 4-34-0-Q | SONAR RM #4 | 103 | Distrubited Systems Restored |
| 2-220-0-Q | SONAR RM #5 | 103 | Distrubited Systems Restored |
| 5-260-0-E | AUX 2 (SPY SWS PUMP) | 103 | Distrubited Systems Restored |
| 02-220-0-C | RADIO CENTRAL | 103 | Distrubited Systems Restored |
| 5-138-0-E | PUMP RM # 1 (SPY SWS PUMP) | 103 | Distrubited Systems Restored |
| COMBAT SYSTEMS TURNOVER #2 (MSR to AIT) | |||
| 03-224-0-C | ELEC WARFARE RM | 110 | ALO |
| 04-140-1-C | AEGIS RADAR RM #1 | 110 | ALO |
| 03-138-1-C | AEGIS RADAR RM #2 | 110 | ALO |
| 01-220-0-C | AEGIS RADAR RM #3 | 110 | ALO |
| 05-316-0-C | AEGIS RADAR RM #4 | 110 | ALO |
| 04-316-0-C | AEGIS RADAR RM #5 | 110 | ALO |
| 06-170-1-Q | FCS DIR #1 | 110 | ALO |
| 06-170-2-Q | FCS DIR #2 | 110 | ALO |
| 07-312-2-Q | FCS DIR #3 | 110 | ALO |
| 06-324-2-Q | FCS DIR #4 | 110 | ALO |
| COMBAT SYSTEMS TURNOVER #3 (MSR to AIT) | |||
| 04-188-0-Q | FOREMAST | 90 | ALO |
| 03-260-0-Q | MAINMAST | 90 | ALO |
| 03-138-2-Q | FAN ROOM (CEC AECU) | 90 | ALO |
| 03-174-1-Q | FAN ROOM | 90 | ALO |
| 03-188-0-Q | FAN ROOM | 90 | ALO |
| 2-94-1-Q | FAN ROOM | 90 | ALO |
| 2-94-2-Q | FAN ROOM | 90 | ALO |
| 2-464-1-Q | FAN ROOM | 90 | ALO |
| 3-426-0-Q | FAN ROOM | 90 | ALO |
| 01-392-2-Q | FAN ROOM | 90 | ALO |
| 01-148-1-Q | FAN ROOM | 90 | ALO |
| 01-178-0-Q | FAN ROOM | 90 | ALO |
| 01-226-1-Q | FAN ROOM | 90 | ALO |
| 02-228-4-Q | FAN ROOM | 90 | ALO |
| 02-234-2-Q | FAN ROOM | 90 | ALO |
| 04-300-2-Q | FAN ROOM | 90 | ALO |
| 1-82-2-Q | FAN ROOM | 90 | ALO |
| 1-382-3-Q | FAN ROOM | 90 | ALO |
| 03-162-2-C | MK 99 XMTR ROOM | 90 | ALO |
| 05-149-0-C | PILOT HOUSE | 90 | ALO |
| 03 LVL FR 228-248 | AN/SLQ-32 (STBD) | 90 | ALO |
| 03 LVL FR 228-248 | AN/SLQ-32 (PORT) | 90 | ALO |
| COMBAT SYSTEMS TURNOVER #4 (MSR to AIT) | |||
| 04 LVL FR 221-260 | PHALANX (MT 21) STBD | 77 | ALO |
| 01-236-0-C | LOAD CENTER 41 | 77 | ALO |
| 02-200-0-C | RADIO TRANSMITTER RM | 77 | ALO |
| 03-199-0-Q | IFF EQUIPMENT ROOM | 77 | ALO |
| 03-227-2-C | PHALANX LOC CONT RM | 77 | ALO |
| 05-166-1-C | DIR SLIP RING ASSY RM #1 | 77 | ALO |
| 05-166-2-C | DIR SLIP RING ASSY RM #2 | 77 | ALO |
| 06-308-2-Q | DIR SLIP RING ASSY RM #3 | 77 | ALO |
| 05-308-2-Q | DIR SUPT EQUIP RM | 77 | ALO |
| 3-260-2-Q | SNAP EQUIPMENT ROOM | 77 | ALO |
| 01-180-0-C | SHIP SIG EXP SPACE | 77 | ALO |
| 3-127-0-Q | T-HAWK EQUIPMENT RM | 77 | ALO |
| 1-390-1-M | TORPEDO RM #1 | 77 | ALO |
| 1-390-4-M | TORPEDO RM #2 | 77 | ALO |
| 01 LVL FR 97-127 | VLS MODULE TOP (FWD) | 77 | ALO |
| 3-94-0-M | VLS LAUNCHER #1 (FWD) | 77 | ALO |
| 1-92-1-Q | SECURITY STA #1 (FWD) | 77 | ALO |
| 01 LVL FR 435-464 | VLS MODULE TOP (AFT) | 77 | ALO |
| 3-435-0-M | VLS LAUNCHER #2 (AFT) | 77 | ALO |
| 1-464-2-Q | SECURITY STA #2 (AFT) | 77 | ALO |
| MD FR 506-529 | HARPOON LNCHR #1 (PORT) | 77 | ALO |
| MD FR 506-529 | HARPOON LNCHR #2 (PORT) | 77 | ALO |
| 05 LVL FR 142 | EOSS (FWD PORT) | 77 | ALO |
| 04 LVL FR 345 | EOSS (AFT STBD) | 77 | ALO |
| COMBAT SYSTEMS TURNOVER #5 (MSR to AIT) | |||
| FWD,STBD,PORT,AFT | AN/SPY-1A ARRAYS | 60 | ALO |
| 03-(250-260) STBD | SRBOC Lnchr No. 6 | 60 | ALO |
| 03-(250-260) PORT | SRBOC Lnchr No. 5 | 60 | ALO |
| 04-(190-220) STBD | SRBOC Lnchr No. 1 and 3; DECOY Lnchr No. 1 and 5 | 60 | ALO |
| 04-(220-230) PORT | DECOY Lnchr No. 6 | 60 | ALO |
| 05-(292-308) PORT | DECOY Lnchr No. 2; SRBOC Lnchr No. 2 and 4 | 60 | ALO |
| 2-506-0-Q | TOWED ARRAY RM | 60 | ALO |
| 2-506-1-Q | NIXIE RM | 60 | ALO |
| 01 LVL FR 46-94 | 5”/62 GUN MT (MT 51) | 60 | ALO |
| 1-58-0-M | 5”/62 LOAD DRUM RM #1 | 60 | ALO |
| MD FR 464-506 | 5”/62 GUN MT (MT 52) | 60 | ALO |
| 2-482-0-M | 5”/62 LOAD DRUM RM #2 | 60 | ALO |
| 04 LVL FR 221-260 | PHALANX (MT 22) PORT | 60 | ALO |
GET PERL
WORK ITEM NO. USS GETTYSBURG (CG-64)
| FY18 EDSRA Planning Event Readiness List (PERL) (Work Item Title) FOUO: Distribution authorized to Department of Defense and U.S. Department of Defense contractors only (administrative use) (26 Sep 16) Other requests referred to CNRMC. | GOV EST | DRY DOCK SHIP TBD | AVAIL 20% (O&I) 27 AUG 18 | FIREMAIN SYS RESTORED 100 PSI PIER SERVICE 15 OCT 18 | UNDOCK SHIP | 3 OF 6 FIREPUMPS READY TO OPERATE 19 | DISTRIBUTED SYSTEMS RESTORED 21 DEC 18 | ALO CSST 07 JAN 19 | HABITABILITY TURN OVER 18 MAR 19 | REFUEL SHIP for HPT 25 MAR 19 | PCD 01 APR 19 | FUEL SHIP FOR SEA TRIALS 20 MAY 19 | DOCK TRIALS 10 JUN 19 | FAST CRUISE 11 JUN 19 | CREW REST 12 - 16 JUN 19 | SEA TRIALS 17 -18 JUN 18 | KTR CONTRACT COMPLETE 24 JUN 19 | COMMENTS |
| LEGEND | "I" = Open & Inspect (CFR) | "P"=Production | "T" = Testing | "C"=Certification | ||||||||||||||
| 042-02-001 | Contractors Facility Work Authorization Form (WAF) Requirements; accomplish |
| 042-10-001 | Accountability of Manhour and Material Reservation; accomplish | |||||||||||||
| 042-11-002 | Work Completion Certification Data for Chief of Naval Operations (CNO) Availabilities; provide | C | ||||||||||||
| 042-11-003 | Physical Security at Private Contractor's Facility; accomplish | |||||||||||||
| 042-32-001 | Marine Coatings Containing Heavy Metals Material; remove and dispose | |||||||||||||
| 074-11-001 | Structural Ultrasonic Impact Treatment (UIT) and G67 Sampling; accomplish | |||||||||||||
| 077-11-001 | Hazardous Waste Produced on Naval Vessels; control | |||||||||||||
| 110-11-001 | Structural; repair | P | C | |||||||||||
| 110-11-002 | Structural Repair; accomplish | P | C | |||||||||||
| 110-11-003 | Underwater Hull Inspection, Repair, and Preservation; accomplish | I | P | C | ||||||||||
| 110-11-004 | Structural Bulkhead Non Destructive Testing (NDT); accomplish | |||||||||||||
| 110-21-001 | Structural Shell Plating Repair; accomplish | P | ||||||||||||
| 120-11-001 | Structural Repair and Preservation; accomplish | P | ||||||||||||
| 120-11-002 | Bulkhead; repair | P | ||||||||||||
| 120-11-003 | Bulkhead and Stiffeners; repair | P | ||||||||||||
| 120-11-004 | Structural Repair; accomplish | P | ||||||||||||
| 120-11-005 | Deck and Valve; repair | I | P | T | ||||||||||
| 120-21-001 | Structural Bulkhead; repair | P | ||||||||||||
| 123-11-004 | Fuel Oil Tank Top Modification; accomplished | I | ||||||||||||
| 123-11-006 | Fuel Oil Service and Compensated Tanks; repair and preserve | I | P | C | ||||||||||
| 123-11-008 | Fuel Oil Gravity Head Tank; repair and preserve | I | P | |||||||||||
| 123-12-001 | JP-5 Tank; repair and preserve | I | P | C | ||||||||||
| 123-15-001 | Lube Oil Tank; repair | I | P | C | ||||||||||
| 123-17-003 | Oily Waste Tank Repair and Preserve; accomplish | I | P | |||||||||||
| 123-19-009 | Sounding Tube Valve; replace | I | P | |||||||||||
| 123-21-002 | Accessible Void Repair and Preservation; accomplish | I | P | C | ||||||||||
| 123-21-003 | Void/Cofferdam; repair and preserve | I | P | C | ||||||||||
| 123-22-001 | Access Trunk Preservation; accomplish | P | ||||||||||||
| 130-11-003 | Trimettallic Aircraft Securing Fitting; replace | P | C | |||||||||||
| 130-11-004 | Towed Array Bulkhead and Deck Repair; accomplish | P | ||||||||||||
| 130-11-006 | 5 Inch Ammo Pallet Staging Room Foundation Preservation; accomplish | P | ||||||||||||
| 130-90-001 | ShipAlt CG47 83265.03K Catwalk Removal Fwd/Stbd 03 Level; accomplish | P | ||||||||||||
| 133-11-001 | Deck and Bulkhead; repair and preserve | P | ||||||||||||
| 135-11-002 | Fuel Oil Tank Top Plating Repair; accomplish | I | P | |||||||||||
| 150-11-001 | Superstructure Repair; accomplish | P | ||||||||||||
| 150-11-002 | Deckhouse Bulkhead; repair | P | ||||||||||||
| 150-11-004 | GTM Cooling Fan Foundation Repair; accomplish | P | ||||||||||||
| 150-11-007 | Gear Locker Bulkhead Plating; repair | P | ||||||||||||
| 150-90-001 | ShipAlt CG47-90123.01K, 01 Level-Main Deck Frame 332 & 346 Cracking Mod to Structure; accomplish | P | ||||||||||||
| 150-90-002 | ShipAlt CG47-83506.01K, Superstructure Fatigue and Sensitization Modifications (AFT); accomplish | P | ||||||||||||
| 150-90-003 | ShipAlt CG47-83506.06 Fatigue & Sensitization Mod AFT; accomplish | P | ||||||||||||
| 150-90-004 | ShipAlt CG47-83506.04K, Superstructure Fatigue and Sensitization Modifications (AFT); accomplish | P | ||||||||||||
| 150-90-005 | ShipAlt CG47-83506.07 Fatigue & Sensitization Mod AFT;accomplish | P | ||||||||||||
| 150-90-006 | ShipAlt CG47-83503.02K and CG47-83503.03K Superstructure Fatigue and Sensitization Modifications (Fwd); accomplish | P | ||||||||||||
| 150-90-008 | ShipAlt CG47-83506.03K, Superstructure Fatigue and Sensitization Modifications (AFT); accomplish | P | ||||||||||||
| 154-90-001 | ShipAlt CG47-00386K, Modify Bulkhead Frame 248 at 03 Level Structural Mod; accomplish | P | ||||||||||||
| 165-11-002 | Sonar Dome Rubber Window (SDRW); inspect | I | P | C | ||||||||||
| 165-11-004 | Lower Sonar Dome Access Scuttle; repair | I | P | |||||||||||
| 167-11-004 | Quick Acting Watertight Door (QAWTD), Steel; replace | P | ||||||||||||
| 167-11-011 | Scuttle, Steel, Flush, Spring-Balanced, Quick-Acting; repair | P | ||||||||||||
| 168-11-001 | Hatch and Scuttle Replacement; accomplish | P | ||||||||||||
| 168-12-001 | Structural Door, Hatch and Scuttle Replacement; accomplish | P | ||||||||||||
| 168-12-002 | Door and Scuttle Repair; accomplish | P | ||||||||||||
| 168-12-003 | ShipAlt CG47-83308K, QAWTT Aluminum Door Upgrade Mod to Door: accomplish | P | ||||||||||||
| 171-11-001 | Main Mast IFF Platform; repair | P | ||||||||||||
| 171-11-002 | Main Mast; repair | P | C | |||||||||||
| 191-90-001 | ShipAlt CG47-89577.01K, Weight and Moment Compensation; accomplish | |||||||||||||
| 220-11-001 | Calibration Services; provide | P | ||||||||||||
| 241-11-002 | Main Reduction Gear (MRG) No. One; flush | P | C | |||||||||||
| 241-12-001 | Main Reduction Gear (MRG) and Controllable Pitch Propeller (CPP) Lube Oil Purifier Heater Controller clean and calibrate: accomplish | |||||||||||||
| 241-12-002 | Number 2 Main Reduction Gear Input Coupling Shaft Oil Seal (2B); replace | P | C | |||||||||||
| 241-12-003 | Main Reduction Gear (MRG) No. 2; Flush | P | C | |||||||||||
| 242-11-001 | Number One Main Reduction Gear (MRG) Multiple Disc Brake and Bleed Air Valve; replace | P | C | |||||||||||
| 242-12-001 | Number 2 Main Reduction Gear (MRG) Multiple Disc Brake and Bleed Air Valve; replace | P | C | |||||||||||
| 243-11-001 | Port and Starboard Waterborne Propulsion Shafting; replace | I | P | C | ||||||||||
| 243-11-002 | Main Propulsion Shaft and Rudder Locking Device; remove | P | ||||||||||||
| 244-11-002 | Line Shaft Bearing (LSB) Sampling Valve; replace | P | ||||||||||||
| 244-11-002 | Line Shaft Bearing (LSB) Sampling Valve Stem; replace | P | ||||||||||||
| 245-10-001 | Controllable Reversible Pitch Propeller (CRP) Hydraulic Oil Tank; repair | P | ||||||||||||
| 245-11-001 | Controllable Reversible Pitch (CRP) Hydraulic System Valves; replace | P | ||||||||||||
| 245-11-004 | Controllable Reversible Pitch (CRP) No. One Hydraulic & Electric Pump/Motor; repair | I | P | |||||||||||
| 245-11-006 | Controllable Reversible Pitch (CRP) No. 2 Hydraulic & Electric Pump/Motor; repair | |||||||||||||
| I | P | |||||||||||||
| 245-11-007 | Controllable Reversible Pitch Hydraulic System Flexible Hose; replace | I | P | |||||||||||
| 245-11-008 | Controllable Pitch (CPP) Propeller; repair | I | P | |||||||||||
| 251-80-001 | CG47 Class AER 68155, GTM Blow-In Door and Louver Heater Controller Relocation; accomplish | P | ||||||||||||
| 252-90-001 | ShipAlt CG47-84251K, ECP-187 Bridge Wing Display Unit Upgrade (SPLITALT); accomplish | |||||||||||||
| P | ||||||||||||||
| 252-90-002 | ShipAlt CG47-80054K Integrated Ship Control SS9 MCS-UPS Redistribution; accomplish | P | T | |||||||||||
| 259-10-001 | Gas Turbine Main (GTM) Exhaust Mixing Tubes Insulation; replace | P | ||||||||||||
| 260-11-001 | Diaphragm Control Pilot Operated Valve; repair | P | ||||||||||||
| 261-11-001 | Machinery Room Chain Hoist Weight Test; accomplish | P | ||||||||||||
| 261-12-001 | Fuel Oil Service Valve and Actuator Overhaul; accomplish | P | ||||||||||||
| 261-12-002 | 1A and 1B Gas Turbine Main (GTM) Engine and Enclosure; repair | P | ||||||||||||
| 261-12-003 | 2A and 2B Gas Turbine Main (GTM) Engine and Enclosure; repair | P | ||||||||||||
| 261-20-001 | Fuel Oil System (1A,1B,2A,2B) Magnetic Motor Controller Overhaul; accomplish | P | ||||||||||||
| 261-20-002 | Fuel Oil Service Pump No. 2, Coalescer and Prefilter; repair | P | ||||||||||||
| 261-20-003 | Fuel Oil Service Pump No. One, Coalescer and Prefilter; repair | P | ||||||||||||
| 262-11-002 | Lube Oil Valve; replace | P | ||||||||||||
| 262-41-002 | Main Reduction Gear (MRG) Lube Oil Equalizer Valve and Mechanical Seal; repair | P | ||||||||||||
| 262-42-001 | Main Reduction Gear (MRG) Lube Oil Equalizer Valve and Mechanical Seal; repair | P | ||||||||||||
| 290-11-001 | Gas Turbine Water Wash System Valve; replace | P | ||||||||||||
| 311-31-001 | Gas Turbine Generator One, 2 and 3 Isolator Assembly Mount Repair and Preserve; accomplish | P | ||||||||||||
| 311-31-002 | Gas Turbine Generator Main Reduction Gear (MRG); flush | P | C | |||||||||||
| 311-33-001 | Gas Turbine Generator Set (GTG) No. 3 Enclosure Repair; accomplish | P | ||||||||||||
| 313-11-001 | Uninterruptible Power Supply (UPS) Battery; install | P | ||||||||||||
| 313-80-002 | ShipAlt CG47-81260K, MHE Battery Charger; replace | P | ||||||||||||
| 321-11-001 | Multiple Cable Transit (MCT); repair | P | C | |||||||||||
| 321-90-001 | ShipAlt CG47-88891K, Electronic Ground Fault Detectors Replacement; accomplish | P | ||||||||||||
| 324-80-001 | CG47 Class AER 76101D Replace Dossert Lug Connectors; accomplish | P | ||||||||||||
| 331-11-001 | Topside lighting; repair | P | ||||||||||||
| 331-11-005 | Electrical Protective Conduit; replace | P | ||||||||||||
| 332-11-001 | Flight Deck Lighting and Electrical; repair | P | T | C | ||||||||||
| 332-11-002 | Restoration of Battle Lanterns; accomplish | P | ||||||||||||
| 343-11-001 | Pump and Motor Shipment and Installation; accomplish | P | ||||||||||||
| 343-11-004 | Gas Turbine Generator (GTG), Blow-in Door; repair | P | ||||||||||||
| 343-11-007 | Generator Air Box, Gear Oil and Lube Oil Cooler Cleaning; accomplish | P | ||||||||||||
| 343-13-001 | Generator Exhaust Expansion Joint; replace | P | ||||||||||||
| 411-90-001 | ShipAlt CG47-78510.03K AWS: ACB12/TI12 CIC Display Upgrades (SPLITALT); accomplish | P | ||||||||||||
| 411-90-002 | ShipAlt CG47-83712K PEOC41 COMSEC KW46 Replacement; accomplish | P | ||||||||||||
| 412-90-001 | ShipAlt CG47-86539.03K, Common Data Link Management System Installation (SPLITALT); accomplish | P | ||||||||||||
| 422-11-002 | Temporary Navigation Light System for Towing; remove | P | ||||||||||||
| 423-14-001 | Speed and Miles traveled Indicator; replace | P | ||||||||||||
| 423-90-001 | Shipalt CG47-71386K, Advanced Digital Antenna Production (ADAP),(SPLITALT); accomplish | P | ||||||||||||
| 424-90-001 | ShipAlt CG47-86222.03K, NGF Backfit Phase I; accomplish | P | ||||||||||||
| 428-90-001 | ShipAlt CG64-MA 84636 K ISC SIIG PCI CARD REMOVAL, accomplish | P | ||||||||||||
| 428-90-002 | ShipAlt CG64-86418K, Navigation Sensor System Interface Removal (SplitAlt); accomplish | P | ||||||||||||
| 430-90-003 | ShipAlt CG47-87106.03K, Interior Voice Communication System (IVCS) Upgrade (SPLITALT); accomplish | P | ||||||||||||
| 432-12-001 | Kickpipe; replace | P | ||||||||||||
| 432-12-002 | Sound Powered and Integrated Voice Communication System (IVCS) Jack Box; replace | P | ||||||||||||
| 432-12-003 | Kickpipe; replace | P |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.