Text version
DATE OF REQUEST:
HULLS/TITLE: USS COWPENS (CG 63) & USS GETTYSBURG (CG 64)
SOLICITATION NO: N00024-18-R-4439
NAVSEA POCs:
Billy Castleberry Craig Barton
NAVSEA POC E-MAIL:
billy.castleberry@navy.mil craig.s.barton@navy.mil
NAVSEA POC #: (202) 781-1248
# HULL Contract Area Question Response
146 CG 63
ITEM NO: 456-01-001
TITLE: AS-3572/SPY-1B
Antenna Array Resurfacing;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 146: Paragraph 3.1.2 states “Provide the services of a qualified Original Equipment Manufacturer (OEM) Technical Representative to provide assistance, special tooling, parts, material, and guidance to accomplish repair and testing for each equipment listed in 1.3, located in 1.2, using 2.2 through 2.5 for guidance.
• Contractor notes that the OEM is Lockheed Martin Corporation, however the specification as written does not list the Point of Contact (POC) information such as Name, Sector, Phone #, E-mail address that is required by this particular OEM in order to obtain a quote for services.
QUESTION: Can the Customer provide clarification as to the disparity identified above regarding the OEM Lockheed Martin Corporation POC information to all bidders and will an Amendment be issued providing a revised specification?
GOVERNMENT RESPONSE:
Bidders shall submit to the OEM in report specified in 009- 90 PARA 3.1.5 and request information.
ITEM NO: Various TITLE: Various PARA. NO: Various
PAGE NO:
CONTRACTOR QUESTION : 291
The following question pertains to work items 643-11-001, 643-11-002, 643-11- 003, 643-11-004, 644-11-001 and 644-11-003 on the USS Cowpens
KTR needs further clarification on the GFM kit referenced in 5.3. The entire document references the USS Gettysburg not the USS Cowpens. Please clarify the reference is indeed supposed to be used for the USS Cowpens. If so please clarify that all material required to accomplish this work item is being provided GFM. KTR cannot interpret what is not GFM on the Kitted material list.
GOVERNMENT RESPONSE:(1) The reference applies to USS Cowpens as well as USS Gettysburg
(2) The material document provided in the work spec lists specific IAF/GFM.
ITEM NO: 241-11-002 &
241-12-003 TITLE: Main Reduction Gear (MRG) No. One and No. 2; flush
PARA. NO: 3.3
PAGE NO: 1 of 4
CONTRACTOR QUESTION: 316
Subcontractor for 009-90 para 3.3 responded with a "no bid" quote.
Please provide guidance for an alternative qualified tech rep.
GOVERNMENT RESPONSE: Changed addressed in Errata 5 CG 64, OEM added to 4.1 and correction made to paragraph to indicate (para. 4.1) with OEM information.
ITEM NO: Various
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 318
The following material as of 11/28/17 is long lead:
150-11-004: Cap screw 1 1/4" x 8 1/2" (42 days) 332-11-001: AE VLA Flight Deck light bar (120 days) 332-11-001: Window heater (42 days) 343-13-001: GTG expansion joint (35 days) 343-13-001: Screw cap 1/2" x 2 1/4" (49 days) 343-13-001: Nut hex heavy 1/2"-13UNC (49 days) 450-90-001: Stud welding internal 3/8" x 1 1/4" (42 days) 514-11-005: Mount, resilient type 7E450 (70 days) 521-90-001: Sleeve internal support for hose (126 days) 521-90-001: Flange assy swivel (126 days)
GOVERNMENT RESPONSE: The goverment is requesting to procure the material listed. Item 332-11-001 referenced does not call out for replacement of material referenced in bidder question. The material listed under 450-90-001 and 521-90-001is GFM.
Pre-Proposal Information (PPI)
# HULL Contract Area Question Response
ITEM NO: 521-90-001
"TITLE: ShipAlt CG47- 86960K Upgrade to Titanium Fire Pumps;
accomplish"
PARA. NO: 3.1
PAGE NO: 2
CONTRACTOR QUESTION: 326
Paragraph 3.1 states "Accomplish the requirement of 2.2 through 2.6, using material listed in 2.7 and 5.3."
Note: Other ShipAlts also have the statement "Accomplish the requirement of drawings.... using material listed in..."
Is the intent to only accomplish removal & installation of material listed as GFM?
GOVERNMENT RESPONSE: Accomplish the requirements of the drawings and references, with material identified in paragraph 5 as type of GFM. Additional material required to perform work is indicated in the drawings in General Notes as being IAF furnished.
ITEM NO: 150-90-001
TITLE: ShipAlt CG47- 78449.03K, Deckhouse Insert Plate Installation to Bulkhead; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 332
Paragraph 3.1.3 states “Fabricate and fit all raw material provided as GFM in 5.3 to the appropriate size for install”.
• Contractor notes that 5.3 does not list any Kitted Material.
QUESTION: Can the Customer provide clarification as to the disparities identified above regarding the requirements of paragraphs 3.1.3 and 5.3, and will an Amendment be issued providing a revised specification?
GOVERNMENT RESPONSE: Work item and material provision is completed in conjunction with 251-11-004. No material is provided in 5.3 - Addressed in Errata 4.
ITEM NO: 665-90-002
TITLE: ShipAlt CG47- 83541K, Provide a Crew Resource Learning Center;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 337
Paragraph 3.1.1 states “Fabricate, fit and install from raw material provided by 2.15, 2.16 and 5.3, for accomplishing the requirements of 2.2 through 2.9.
• Contractor notes that reference 2.16, 4720-CG63-FY18-SACG63/EDA18 Rev 5, Ship Alteration Material Summary (4720/3) list no Kitted Material for ShipAlt
CG47-83541K.
QUESTION: Can the Customer provide clarification as to the disparities identified above regarding the requirements of paragraphs 3.1.1 and reference 2.16, and will an Amendment be issued providing a revised specification?
GOVERNMENT RESPONSE: Kitted material identified in paragraph 5.3 applies to paragraph 3.1.1. No ammendment required.
ITEM NO: 980-90-018
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 368
COWPENS: The Government response to Question No. 68 (COW GET Bidders' Questions 20171219) appears to state that work item 980-90-018 is cancelled, however, this work item still appears on Attachment J-7 and the work item has not been formally cancelled by Amendment or Errata, including on Errata Two as the response indicates. Please clarify.
GOVERNMENT RESPONSE: 980-90-018 CANCELED
ON CG63 ERRATA 3
ITEM NO: 980-11-006
TITLE: NSWC Alteration Installation Team (AIT) Crane Support, AER 84293 and AER 84893 Support;
provide
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 370
Paragraph 3.10 states “Install and maintain temporary electrical power, 440 Volts AC, 60 Hertz, 30 Amp service, 3 Phase, consisting of 2 duplex outlets at each of the locations listed in 1.2.1 through 1.2.24 at the direction of the
SUPERVISOR.”
• Contractor notes that 1.2 location of work lists only spaces 1.2.1 through
1.2.18. QUESTION: Can the Customer provide clarification as to the disparities identified above regarding the Location of work? and will an Amendment be issued providing a revised specification?
GOVERNMENT RESPONSE: Concur with contractor -correction to work item will change 1.2.24 to 1.2.18 in paragraph 3.10 via errata 6 CG 63.
ITEM NO: 456-90-003
TITLE: Errata 2, Shipalt
CG47-78510.03K AWS:
ACB12/TI12 CIC Display Upgrades; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 374
Paragraph 3.2 states “Accomplish the requirements of 2.2 through 2.29 29, 2.62,
2.63 and applicable portions of SA 78510.03K in 2.43 and 2.44 including all general, local, special, test and rip-out notes, using 2.42 and 2.45 through 2.58 for guidance”.
• Contractor notes that ERRATA_2 added references 2.62 RLAR 78510.03- CG63-P345, RLAR to Update Drawings 183-8711062, 184- 8711064, and 184- 8711066 and 2.63 RLAR 78510.03-CG63-P352, RLAR to Remove Temporary Access Cover in CIC DWG 153-8648166
• Contractor notes that references 2.62 and 2.63 have not been provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 612-80-001
TITLE: Shipalt CG47 Class AER 68115, Helo Deck Safety Net Repair and Replacement; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 375
Paragraph 3.1 states “Accomplish the requirements of 2.2 and 2.5 including all general, local, special, test and rip-out notes, using 2.3 as guidance and using materials specified in reference 2.4”.
• Contractor notes that reference 2.4 4720-CG63-FY18-AER68115, Ship Alteration Material Summary (4720/3) was not provided on reference disc’s.
QUESTION: Can the Customer provide the above listed missing reference to all bidders?
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG 63. No material is provided via 4720 for this work item.
ITEM NO: 438-90-001
TITLE: Errata 2, Shipalt
CG47-73856.03K,
Integrated Ship Controls Upgrade; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 377
Paragraph 3.2 states “Accomplish the requirements of 2.2 through 2.18 and 2.33 and applicable portions of SA 73856.03K in 2.19 through 2.22 including all general, local, special, test and rip-out notes, using 2.23 through 2.27 for guidance.
• Contractor notes that reference 2.21, drawing 304-8416995, CG47 Class Integrated Design Dwg For CG63 Cable Routing (EDSRA18) has been changed from Revision – to Revision A.
• Contractor notes that ERRATA_2 has added reference 2.33 RLAR 73856.03- CG63-P348, RLAR to Move Chilled Water System Mod from SA 74392.03K to
73856.03K DWG 558-8710386
• Contractor notes that references 2.21 Rev_A and 2.33 have not been provided by the Customer.
QUESTION: Can the Customer provide the above missing references to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 517-90-001
TITLE: Errata 2, Shipalt CG47-83219.03K, Electric Conversion of Waste Heat Boilers; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 378
Paragraph 3.2 states “Accomplish the requirements of 2.2 through 2.28, 2.37,
2.38 and applicable portions of SA 832190.3K in 2.29 including all general, local, special, test and rip-out notes, using 2.30 through 2.33 and 2.39 for guidance”.
• Contractor notes that ERRATA_2 added references 2.37, RLAR 83219.03/CG63/P339, Update to List of Materials, reference 2.38, RLAR 83219.03/CG63/P356, RLAR to Update Fuel Oil TFR HTR 2 Wiring, and reference 2.39, LAR 83219.02/CG63/0057 Rev A, LAR to Remove FOF-33 Fuel Oil Valve Bonnet for Foundation Installation - MODPRD18 Guidance.
• Contractor notes that references 2.37, 2.38 and 2.39 have not been provided by the Customer.
QUESTION: Can the Customer provide the above missing references to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 665-90-003
TITLE: Errata 2, Shipalt CG47-85640.03K, Crew Physical Fitness Center;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 379
Paragraph 3.2 states “Accomplish the requirements of 2.3 through 2.19 19. 2.32,
2.33 and applicable portions of ShipAlt 85640.03K in 2.20 through 2.22, including all general, local, special, test and rip-out notes, using 2.23 through
2.26 for guidance and using material listed in 2.30 and 2.31”.
• Contractor notes that reference 2.21, drawing 320-8416997 Rev A, CG47 Class Integrated Design Dwg For CG63 60/400HZ Power System (EDSRA18) was not received on the initial disc provided by the Customer.
• Contractor notes that ERRATA_2 added references 2.32 drawing 436-8646049, CG47-85640.03K Misc IC Blk & Elem Wrg Diag W/Pre-Fab and 2.33 RLAR 85640.03/CG63/P359, RLAR to Update Deck Covering Ripout Schedule.
• Contractor notes that references 2.21, 2.30 and 2.31 have not been provided by the Customer.
QUESTION: Can the Customer provide the above missing references to all bidders?
ITEM NO: 721-90-002
TITLE: Shipalt CG47- 87438.03K, BL 7 Phase 1C VLS Upgrade; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 380
Paragraph 3.2 states “Accomplish the requirements of 2.2 through 2.7, and applicable portions of SA 87438.03K in 2.8 through 2.10, including all general, local, special, test and rip-out notes, using 2.11 for guidance.
• Contractor note that references 2.8, drawing 401-8416999, CG47 Class Integrated Design Drawing for CG63 Computer Central MOD to ARR (EDSRA18), and 2.9, drawing 302-8649050, CG47 Class Integrated Design Drawing For CG63 60/400HZ Power System (EDA18), along with 2.10, drawing 304-8649047, CG47 Class Integrated Design Drawing For CG63 Cable Routing (EDSRA18), was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing references to all bidders?
GOVERNMENT RESPONSE: Reference 401-8416999 provided 1/18/18. Reference 2.9 302-8649050 has been replaced by 320-8416997 Rev A; Reference 2.10 304- 8649047 has been replaced by 304-8416995 Rev A. Both references provided 1/1/18. Work item will be corrected via in ERRATA 6 CG 63.
ITEM NO: 643-11-002
TITLE: NAVSEA
Habitability Improvement Program BENL-S3179;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 383
Paragraph 3.1 states “Accomplish the requirements of 2.2, 2.3, 2.6, and 2.8 through 2.12 at locations listed in 1.2, using 2.4, 2.5, 2.7, 2.13 through 2.16 for guidance and material requirements (See Notes 4.1 and 4.2)”.
• Contractor notes that Note 4.1 states “Reference 2.17 is a parts list of kitted material for this Work Item” however reference 2.17, Project No. BENL-S7361 / HENL-S7367, Parts List for Crew Complex 2-149-0-L BENL/HENL Projects was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 643-11-003
TITLE: NAVSEA
Habitability Improvement Program; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 384
Paragraph 3.1 states “Accomplish the requirements of 2.2 through 2.6, and 2.8 through 2.10 at locations listed in 1.2.1 through 1.2.5 using 2.7, and 2.11 through
2.15 for guidance and material requirements (See Notes 4.1 and 4.2)”.
• Contractor notes that Note 4.1 states “Reference 2.12 is the parts list of kitted material for this Work Item” however reference 2.12, Project No. BENL-S7312 / HENL-S7313, Parts List for Crew Complex 1-356-0-L BENL/HENL Projects was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 643-11-004
TITLE: NAVSEA
Habitability Improvement Program 3-346-0-L;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 385
Paragraph 3.1 states “Accomplish the remaining deferred requirements of 2.2 through 2.6 and 2.8 through 2.10, using 2.7, 2.11, and 2.12 for guidance and material requirements. (See notes 4.1 and 4.2)”.
• Contractor notes that Note 4.1 states “Reference 2.12 is a parts list of kitted material for this Work Item” however reference 2.12, Project No. BENL-S7372 / HENL-S7373, Parts List for Crew Complex 3-346-0-L BENL/HENL Projects was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 644-11-001
TITLE: NAVSEA
Habitability Improvement Program; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 386
Paragraph 3.1 states “Accomplish the remaining deferred requirements of 2.2 through 2.6 and 2.8 through 2.10, using 2.7, 2.11, and 2.12 for guidance and material requirements. (See notes 4.1 and 4.2)”.
• Contractor notes that Note 4.1 states “Reference 2.12 is a parts list of kitted material for this Work Item” however reference 2.12, Project No. BENL-S7369 / HENL-S7369, Parts List for Crew Complex 2-346-01-L BENL/HENL Projects was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
ITEM NO: 644-11-003
TITLE: NAVSEA
Habitability Improvement Program; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 387
Paragraph 3.1 states “Accomplish the remaining deferred requirements of 2.2, 2.3, 2.6 through 2.8 and 2.10 through 2.12 at locations listed in 1.2 using 2.4, 2.5, 2.9, and 2.13 for guidance and material requirements (See Notes 4.1 and 4.2)”.
• Contractor notes that Note 4.1 states “Reference 2.12 is a parts list of kitted material for this Work Item” and appears to be a typo and is believed that the correct reference should be 2.14, Project No. BENL-S7370 / HENL-S7371, Parts List for Crew Complex 3-46-0-L BENL/HENL Projects however reference 2.14, Project No. BENL-S7369 / HENL-S7369, Parts List for Crew Complex 2-346-01- L BENL/HENL Projects was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 641-90-001
TITLE: NAVSEA
Habitability Improvement Program Officer Berthing;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 388
Paragraph 3.1 state “Accomplish the requirements of 2.2 through 2.14 and 2.16 through 2.22 and 2.28 through 2.31 at locations listed in 1.2.
Contractor notes that ERRATA_2 added Reference 2.28, RLAR OHAB-CG63- P355, RLAR for HVAC Modifications Deconfliction with SA 83506.05k HVAC MOD, and reference 2.29, RLAR OHAB-CG63-P377, RLAR for Correction to Shower Heads and Sink Mounting Bracket Details, along with reference 2.30, RLAR OHAB-CG63-P334, RLAR for HVAC Design Updates, and reference 2.31, RLAR OHAB-CG63-P346, RLAR for Seawater Flushing Sys Mod Piping Change.
• Contractor notes that reference 2.28 through 2.31 has not been provided by the Customer.
Paragraph 3.1 also states” Government Furnished Material is listed in 2.26 and unless designated as prefab, will be raw stock and requires fabrication to meet existing ships conditions”.
• Contractor notes that reference 2.26, 4720-CG63-FY18-SAOHABK, Ship Alteration Material Summary (4720/3) was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing references to all bidders?
GOVERNMENT RESPONSE: References provided 1/18/18
ITEM NO: 897-11-001
TITLE: Program and Production Management Services; provide
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 389
Contract notes that the USS Gettysburg (CG-64) specification package does not contain this work item specification and that typically these requirements are applied to Cost Contracts and not Firm Fixed Price (FFP).
Contractor notes that recent (FFP) RFP’s that have been issued that include this type of specification generally deleted these requirements by follow on Amendments.
QUESTION: Can the Customer provide clarification as the disparities identified above regarding between the USS Cowpens (CG-63) and the USS Gettysburg (CG-64) specification packages and will an Amendment be issued deleting this Work item?
GOVERNMENT RESPONSE: Work item removed on
ERRATA 1 CG 64.
ITEM NO: 813-11-001
TITLE: AEGIS Light Off (ALO) Compartment Release Schedule; provide
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 390
Work Item # 813-11-001, AEGIS Light Off (ALO) Compartment Release Schedule; provide
Paragraph 3.3 states “Accomplish ALO Compartment Release in accordance with Attachment A”
• Contractor notes that Attachment A was not provided with the specification or was listed and provided as a reference.
QUESTION: Can the Customer provide the above missing Attachment A to all bidders?
GOVERNMENT RESPONSE: Reference provided 1/18/18.
Attachment is on Sheet 5 of 7 for the work item
ITEM NO: 191-90-001
TITLE: SA 89577.01K
Weight and Moment Compensation
PARA. NO: 5.3
PAGE NO: 2
CONTRACTOR QUESTION: 391
Para 5.3 states there is kitted material in the 4720. The 4720 states "This shipalt does not have Government Furnished Material. Please confirm, the contractor is to purchase the Lead.
GOVERNMENT RESPONSE: Will remove GFM reference
ERRATA 6 CG 64.
ITEM NO: 437-21-003
TITLE: Oily Waste Drain Tank Level Indicator (TLI) System; repair
PARA. NO: 3.1.1, 3.1.2,
3.2 & 5.1 PAGE NO: 1, 2 of 3
CONTRACTOR QUESTION: 392
In errata #2 there are several discrepancies in the subject item: 1] Para 3.1.1 states to replace parts listed in 1.3.1 listed in 1.2.1 thru 1.2.5 (1.2.5 is the IC Gyro Rm. perhaps this should read listed in 1.3.1.1 to replace 5 GFM transducers listed in 5.1.1, only 3 receivers are listed) 2] Para 3.1.2 states to install new parts listed in 1.3.2 with parts listed in 5.1.2. We assume this para should read equipment listed in para 1.3.1.2 (as para 1.3.2 does not exist). 3] Para 3.2 states to accom.
009-13 to equip. listed in 1.3 (there are no meters listed in 1.3. Change para 3.2 to read Calibrate each receiver meter IAW 009-13 for tanks listed in 1.2.1 thru
1.2.4 and 1.2.6). 4] Para 5.1.1 reads 3 Gems Receivers p/n 37030 (there are 18 transmitters and 5 receivers in the listed tanks, perhaps this should read 18 TLI transmitters or 5 receivers).
GOVERNMENT RESPONSE: Correction addressed in Errata 6 CG 64. Material corrected in para. 3.1.1 and 3.1.2.
ITEM NO: 243-11-001
TITLE: P/S Waterborne Propulsion Shafting
PARA. NO: 3.9.1
PAGE NO: 8
CONTRACTOR QUESTION: 393
Para 3.9.1 States to remove existing and install new equipment identified in 1.3.13, using parts listed in 5.1. Para 1.3.13 is for 1 port and 1 starboard Stern Tube Seals. There is only one kit listed in 5.1. Recommend para 5.1 be changed to 2 each MX9 Major Overhaul Kits.
GOVERNMENT RESPONSE: Addressed ERRATA 5 CG 64; change to quantity of 2 each.
ITEM NO: 514-23-001 &
514-24-001 TITLE: AC Plants 3 & 4
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 394
The Chill Compressors listed in pargraph 1.3.4 have a 15 month delivery, suggest getting these on order and making them GFM.
GOVERNMENT RESPONSE: Addressed ERRATA 5 CG 64; added to GFM List via Errata 5.
418 GET
ITEM NO: 634-21-002
TITLE: Flight Deck Nonskid Replace
PARA. NO: 3.6
PAGE NO: 2 of 4
CONTRACTOR QUESTION 418:
Work item states that the location listed in 1.2.1 is to have all deck perimeter, waterway bar, deck combing, strustural closure combings and 6" on all vertical surfaces to an SSPC-SP6 cleanliness. In order to accomplish this, the contractor will be required to open nozzle blast to achieve an SSPC-SP6 cleanliness. Is the contractor to be allowed to open nozzle blast or will an SSPC-SP11 be sufficient to satisfy the criteria?
GOVERNMENT RESPONSE: Normal cleanliness is accomplished using a deck crawler for removal of existing deck covering, however contractor method of blasting to achieve requirement is up to the contractor. Containment requirements per NSI will still need to be utilized either way.
419 GET
ITEM NO: Various TITLE: Various Shipalts
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 419:
Contractor received additional drawings with Amendment 0003 through AMRDEC for the Cowpens, but didn't for the Gettysburg. The following Gettysburg items have Rev A drawings that have not been provided:
150-90-002 150-90-003 150-90-004 150-90-005
Please advise.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
421 GET
ITEM NO: 150-90-002
TITLE: Ship Alt 83506.01K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 421:
To date Reference 2.2 & 2.3 Rev A has not been provided to contractor.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
422 GET
ITEM NO: 150-90-004
TITLE: Ship Alt 83506.04K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 422:
To date References 2.2 - 2.5, 2.7 - 2.10, 2.12 & 2.15 - 2.19 Rev A has not been provided to contractor.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
423 GET
ITEM NO: 150-90-005
TITLE: Ship Alt 83506.07K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 423:
To date References 2.2, 2.6 & 2.7 Rev A has not been provided to contractor.
Also missing is Reference 2.12
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
424 GET
ITEM NO: 150-90-008
TITLE: Ship Alt 83506.03K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 424:
To date References 2.2, & 2.13 Rev A has not been provided to contractor.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
425 GET
ITEM NO: 430-90-003
TITLE: Ship Alt 87106.03K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 425:
To date References 2.9 Rev A has not been provided to contractor. Also missing are References 2.14 and 2.15
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
426 GET
ITEM NO: 456-90-003
TITLE: Ship Alt 77614.03K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 426:
To date References 2.19 has not been provided to contractor.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
427 GET
ITEM NO: 642-11-001
TITLE: Hab and Berthing
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 427:
To date References 2.10 has not been provided to contractor.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
428 GET
ITEM NO: 643-11-002
TITLE: Hab and Berthing
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 428:
To date References 2.21 has not been provided to contractor.
GOVERNMENT RESPONSE: Reference provided 1/19/2018
429 GET
ITEM NO: 643-11-003
TITLE: Hab and Berthing
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 429:
To date References 2.28 has not been provided to contractor.
GOVERNMENT RESPONSE: Reference provided 1/19/2018
430 GET
ITEM NO: 645-90-001
TITLE: Hab and Berthing
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 430:
To date References 2.16 Rev A has not been provided to contractor.
GOVERNMENT RESPONSE: Reference provided 1/19/2018
431 GET
ITEM NO: 711-90-002
TITLE: Ship Alt 78818.02K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 431:
To date References 2.2 Rev A has not been provided to contractor.
GOVERNMENT RESPONSE: GOVERNMENT
RESPONSE: References provided and identified in Errata 2
CG 64.
432 COW
ITEM NO: Mising 4720s TITLE: Ship Alt 78818.02K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 432:
To date the following 4720 references to identifying GFM have not been received. Please provide.
Work Item No. Document Number 110-90-002E4 4720-CG63-FY18-SA8307 Rev29 441-90-006E4 4720-CG63-FY18-SA80897.03K Rev27 443-90-001E4 4720-CG63-FY18-SA86316K Rev29 452-90-001 4720-CG63-FY18-SA87310.03K Rev2 452-90-001E4 4720-CG63-FY18-SA87310.03K Rev27 463-80-001 4720-CG63-FY18-SA76231D Rev2 517-90-001E4 4720-CG63-FY17-SA83219-03 Rev27 555-90-001 4720-CG63-FY18-SA81435K Rev2 583-90-001E4 4720-CG63-FY18-SA80917K Rev29
612-80-001 4720-CG63-FY18-AER68115
641-90-001 4720-CG63-FY18-SAOHABK
665-90-003E4 4720-CG63-FY18-SA85640.03K Rev29
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG
63. No material is provided via 4720 for work item 612-80-
001. Additional 4720 provided.