DATE OF REQUEST: Friday, January 26, 2018
HULLS/TITLE: USS COWPENS (CG 63) & USS GETTYSBURG (CG 64)
SOLICITATION NO: N00024-18-R-4439
NAVSEA POCs:
Billy Castleberry Craig Barton
NAVSEA POC E-MAIL:
billy.castleberry@navy.mil craig.s.barton@navy.mil
NAVSEA POC #: (202) 781-1248
# HULL Contract Area Question Response
ITEM NO:
TITLE: Government's Critical Path / Availability Analysis
PARA. NO:
PAGE NO: 31 of 135
CONTRACTOR QUESTION 170: In several locations in the Solicitation, the government references "the Government's Critical Path to complete the Availability". Can the Government provided the LMAs a copy of the Planning Yard Availability Analysis handbook for both the USS GETTYSBURG and USS
COWPENS EDSRA / MODPRD?
GOVERNMENT RESPONSE: Availability Analysis provided 1/25/2018
ITEM NO: 997-11-001
TITLE: Drydocking and Undocking
PARA. NO: 3.1.1
PAGE NO:
CONTRACTOR QUESTION : 235
Paragraph 3.1.1 identifies information that is submitted "…at the time of bid or proposal of this solicitation…"which is not required by Section L of the solicitation nor scheduled to be evaluated under section M of the solicitation.
Recommend deleting paragraph 3.1.1 and incorporating all proposal instructions in Section L and all evaluation factors for award in Section M of the solicitation.
GOVERNMENT RESPONSE: Addressed in Errata 6 CG64.
Requirement for docking and facility certification is already an noted in NSI 009-01 (Dry dock related inspection reports shall be submitted no later than the first 20 percent of the scheduled docking period). Sentence "at the time of bid or proposal of this solicitation" was removed in CG64 item via Errata 6 and replace with (3.1.1 Submit one legible copy, in hard copy or approved transferrable media, of a report of the drydock certification certificate and a report of a description of the drydocking facility to be used to the SUPERVISOR 14 calendar days prior to commencing drydocking evolution.)
254 CG63 ITEM NO: 631-11-006
CONTRACTOR QUESTION : 254
Paragraphs 3.3 and 3.8 call out damping tile but 2.4 does not identify damping tile in this location.
GOVERNMENT RESPONSE: Addressed in Errata 4 CG 63.
Deleted 3.3 and 3.8. There is no Sound Dampening Tile in this location.
263 CG63
ITEM NO: 721-11-003
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION : 263
Paragraphs 3.1.1 and 3.24 call out 009-78 but 5.1 provides no material.
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG
63. Deleted 3.2.4.
Pre-Proposal Information (PPI)
# HULL Contract Area Question Response
ITEM NO:
TITLE: GETTYSBURG
MODPRD Period of Performance
PARA. NO: J-6
PAGE NO:
CONTRACTOR QUESTION : 292
In the GETTYSBURG MODPRD J-6, the start date of the MODPRD is identified as “no earlier than 16 March 2018”. It later stipulates that the awardee could start the availability up to 15 days later then than the 16 March date. Thus the start date could run from 16 March to 31 March 2018. There is nowhere else in the Solicitation where it references the start date of the MODPRD. The J-6 also identifies two completion dates; one on 19 June 2019 and another on 24 July 2019. Awarding the MODPRD on 2March after Questions and BAFO would allow the Awardee less than 30 to commence this complex Availability. The acceleration of USS GETTYSBURG by three months, without discussion with Industry, puts the start of the availability in a highly congested, resource-constrained window in the Port of Norfolk. CNRMC/SEA21 Private Sector Workload Estimate dated 21 July 2017 and the NDE printout of 1 August 2017 have the period of performance of the USS GETTYSBURG MODPRD as 17 June 2018 through 27 September 2019. Please clarify the period of performance. If flexibility exists, it would be appreciated if the Period of Performance could be moved to the dates briefed Industry at Industry Day and IAW CNRMC/SEA21 Private Sector Workload Estimate and promulgated a new J-6. This would bring consistent and predictable work to the Industrial Base and allow better pricing for the Government.
GOVERNMENT RESPONSE: "Offerors are provided significant flexibility to propose USS Gettysburg MODPRD milestones, including the Availability Start milestone.
Milestone flexibility is provided to allow offerors discretion to best manage their resource constraints. The Government has provided a list of constraints around Availability Start (e.g. a minimum number of days from the contract award and vessel available milestones and Availability Start). These limits constrain how early the Availability may commence.
The offeror may elect to propose an Avail Start date later than those minimum constraints."
294 CG 64
ITEM NO: 411-90-002
TITLE: Integrated Design Modification to deck covering and Passive Countermeasures (PCMS);
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 294
J-7 for pricing has item description as ShipAlt CG47-83712K PEOC41 COMSEC KW46 Replacement; accomplish. Specification received for package has the item description as Integrated Design Modification to deck covering and Passive Countermeasures (PCMS); accomplish. Please clarify.
GOVERNMENT RESPONSE: J7 corrected with the composite package requirements. WI 411-90-002 is for "Integrated Design Modification to deck covering and Passive Countermeasures (PCMS)".
ITEM NO: 428-90-001
TITLE: ShipAlt CG64-MA
84636 K ISC SIIG PCI
CARD REMOVAL,
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 301
The following item is listed on J-7, but there is no work item in the package: 428- 90-001. Please review and advise.
GOVERNMENT RESPONSE: WI 428-90-001 is "ShipAlt CG47-86418K, Navigation Sensor System Interface Removal; accomplish". J7 was updated to reflect updated composite work package.
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION : 340
The COWPENS and GETTYSBURG availabilities are very similar in scope and duration, but there are significant disparities in the Interport differentials to each availability. For example, the Interport differential for accomplishing COWPENS in Mayport is roughly half the Interport differential of accomplishing essentially the same work, in the same duration, at the same period of time on Gettysburg. Likewise, to accomplish substantially similar availabilities in Pascagoula has the Interport differential for COWPENS that is less than 20% of the Interport differential for GETTYSBURG. Please explain the Government’s methodology for calculating the Interport differentials and why such a huge disparity exists between the values assigned to COWPENS and GETTYSBURG for nearly identical out-of-homeport efforts.
GOVERNMENT RESPONSE: "The categories of cost that make up the Inter-port Differential are set forth in the RFP.
Specific values are considered sensitive and are not publicly disclosed. However, please note that the interport differential values for the COWPENS and GETTYSBURG reflect the differentials to complete those Availabilities away from their current homeports (San Diego, CA for USS COWPENS, Norfolk, VA for USS GETTYSBURG). Amongst other differences, a significant factor in the differences between the interport differential values for the COWPENS and GETTYSBURG are therefore created by the differences for Navy costs between those two homeports, such different values for Basic Allowance for Housing.
ITEM NO: RFP Section J (Cowpens)
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 357
Attachment 002 to this question provides a list of 25 missing or discrepancies with drawings/references identified in Errata provided. Please provide.
GOVERNMENT RESPONSE: Revision of J7 provided.
358 CG63
ITEM NO: 171-11-002
TITLE: Main Mast Deferred Interference Installation;
accomplish
PARA. NO: 3.1
PAGE NO: 1
CONTRACTOR QUESTION: 358
Paragraph 3.1 states "accomplish the reinstallation of the equipment removed in SSRA 16 using 2.2 through 2.4 for guidance.
For estimating purposes, please provide the attachment 150-90-007 prelim 359-interference details and 150-90-007 prelim 359895-sub from CFR E-BAES-1535 of 2.2
GOVERNMENT RESPONSE: Reference provided in ERRATA 5 Reference Package
ITEM NO: Attachment J-
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 359
Attachment J-7, tab 1 work items 042-11-002, 042-12-001, 045-11-001, 077-11- 001, 110-11-001, 110-11-003, 110-11-004, 110-11-005, 110-11-006, 110-11- 009, 110-11-010 and 110-11-011 are listed twice. Please clarify or correct.
GOVERNMENT RESPONSE: J7 updated to reflect updated composite work package. Work items are listed once.
ITEM NO: Attachment J-
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 360
Attachment J-7 tab 1; several of the descriptions of the work items are different than the descriptions on the latest revisions of the specifications. Please clarify or correct.
GOVERNMENT RESPONSE: J7 updated to reflect updated composite work package.
ITEM NO: Attachment J- 7 (Rev1)
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 361
Work Items 423-90-001, 561-11-006 and 982-31-002 were added to tab 1 of the rev 1 of Attachment J-7 but the specifications were never provided. Please provide these specifications as soon as possible or delete them from Attachment J- 7.
GOVERNMENT RESPONSE: Composite work item provided 1/24/2018. J7 updated to reflect updated composite work package.
362 CG63
ITEM NO: 437-21-001
TITLE: Oily Waste Drain Tank Level Indicator (TLI) System; repair
PARA. NO:
PAGE NO: 2
CONTRACTOR QUESTION: 362
Para 3.4 states "Accomplish the replacement of the TLI system, identified in 1.3, for the Oily Waste Drain Tanks listed in 1.2, using 2.7 for guidance and material requirements, in accordance with Section 8 of 2.X0965-LP-109-1010 Rev 3, Tank Level Indicating (TLI) System, Type No. 36000X and Technical Representatives' instructions. The quantity of material shall be determined and provided by the vendor at time of installation.
Question 1. there is no reference 2.7 on the specs. What document is being referenced?
Question 2. Is the contractor replacing all 13 TLI or will the quantity of material be determined and provided by the vendor after doing open and inspect as indicated in the last sentance of paragraph 3.4?
Please Advise.
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG
63. Reference 2.6 replaced 2.7. Quantity of material identified in 1.3.
ITEM NO: Attachment J-7
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 364
COWPENS: This question is a repeat of a previously asked question that hasn’t been answered. Work Item 423-90-001, 561-11-006 and 982-31-002 are on the COWPENS Attachment J-7 but the specifications and drawing references havent been provided. Please provide the necessary GFI or remove these work items from the COWPENS Attachment J-7.
GOVERNMENT RESPONSE: Composite work item provided 1/24/2018. J7 updated to reflect updated composite work package.
ITEM NO: Various
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 365
COWPENS: This question is a repeat of a previously asked question that hasn’t been answered. Work Items 042-11-002, 042-12-001, 045-11-001, 077-11-001, 110-11-001, 110-11-003, 110-11-004, 110-11-005, 110-11-006, 110-11-009, 110- 11-010 and 110-11-011 are listed twice on the COWPENS Attachment J-7.
Please clarify or correct.
GOVERNMENT RESPONSE: J7 updated to reflect updated composite work package. Work items are listed once.
ITEM NO: Attachment J-7
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 366
COWPENS: Attachment J-7 contains two "Trial" items; 982-31-001 and 982-31-
002. Please clarify that both are required or if one should be deleted.
GOVERNMENT RESPONSE: WI 982-31-001Dock Trial, Fast Cruise, and Sea Trial; accomplish refers to support to the actual dock trials events. 982-31-002 refers to discrepancy corrections based on Dock trials. Both items will stay in the package.
367 CG63
ITEM NO: 992-11-004
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 367
COWPENS; The Government response to Question No. 65 (COW GET Bidders' Questions 20171219) is for a different question. Please respond to original question of "The fuel depot in San Diego does not allow contractor supplied barges to enter or tow their barges. How are contractors to price this work item in view of that?"
GOVERNMENT RESPONSE: Errata 5 addresses statement.
Ship force to arrange fuel barge and towing services.
ITEM NO: 980-11-006
TITLE: NSWC Alteration Installation Team (AIT) Crane Support, AER 84293 and AER 84893 Support;
provide
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 370
Paragraph 3.10 states “Install and maintain temporary electrical power, 440 Volts AC, 60 Hertz, 30 Amp service, 3 Phase, consisting of 2 duplex outlets at each of the locations listed in 1.2.1 through 1.2.24 at the direction of the
SUPERVISOR.”
• Contractor notes that 1.2 location of work lists only spaces 1.2.1 through
1.2.18. QUESTION: Can the Customer provide clarification as to the disparities identified above regarding the Location of work? and will an Amendment be issued providing a revised specification?
GOVERNMENT RESPONSE: Concur with contractor -correction to work item will change 1.2.24 to 1.2.18 in paragraph 3.10 via Errata 5 CG 63.
372 CG63
ITEM NO: 721-11-004
TITLE: Harpoon HGMS/LSU Support Equipment Repair;
accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 372
Paragraph 3.2 states “Accomplish repairs of damaged/missing fasteners, cable tags, and damaged shrink boots on cables/connectors pending results of report from 3.1 using 2.5 through 2.5 as guidance”.
• Contractor notes the costs for materials and/or labor to accomplish the requirements of this paragraph cannot be determined at this time and are typically subject to equitable adjustment upon receiving the results of the report submitted.
QUESTION: Can the Customer provide clarification of the intent of paragraph 3.2?
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG
63. Additional information provided in paragraph 3.2-3.5.
373 CG63
ITEM NO: 314-11-002
TITLE: 2STCB Cooler Control Board; replace
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 373
Paragraph 3.1 states “Accomplish the repairs of equipment listed in 1.3, located in 1.2, using 2.2 for guidance”.
• Contractor notes that this paragraph does not identify what repairs are to be accomplished to the equipment listed in 1.3.1 other than to accomplish the requirements of 3.1.1 through 3.1.3.
• Contractor notes that at this time it cannot determine the cost of materials or labor to accomplish repairs until the equipment is inspected and/or tested and that typically this is subject to equitable adjustment.
QUESTION: Can the Customer provide clarification of the intent of paragraph 3.1?
GOVERNMENT RESPONSE: Additional information provided in paragraph 3.1, addressed in ERRATA 5 CG 63
376 CG63
ITEM NO: Electric Capstan and Motor, overhaul
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 376
Paragraph 3.8 states “Accomplish an operational test of the Capstan using 2.14 as guidance”.
• Contractor notes that Reference 2.14 582 M04599, Electric Capstan, Model Number LC-40 Functionality Test has not been provided.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: Reference provided in ERRATA 5 CG 63 Reference Package
ITEM NO: 721-90-002
TITLE: Shipalt CG47- 87438.03K, BL 7 Phase 1C VLS Upgrade; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 380
Paragraph 3.2 states “Accomplish the requirements of 2.2 through 2.7, and applicable portions of SA 87438.03K in 2.8 through 2.10, including all general, local, special, test and rip-out notes, using 2.11 for guidance.
• Contractor note that references 2.8, drawing 401-8416999, CG47 Class Integrated Design Drawing for CG63 Computer Central MOD to ARR (EDSRA18), and 2.9, drawing 302-8649050, CG47 Class Integrated Design Drawing For CG63 60/400HZ Power System (EDA18), along with 2.10, drawing 304-8649047, CG47 Class Integrated Design Drawing For CG63 Cable Routing (EDSRA18), was not received on the initial disc provided by the Customer.
QUESTION: Can the Customer provide the above missing references to all bidders?
GOVERNMENT RESPONSE: Reference 401-8416999 provided 1/18/18. Reference 2.9 302-8649050 has been replaced by 320-8416997 Rev A; Reference 2.10 304- 8649047 has been replaced by 304-8416995 Rev A. Both references provided 1/1/18. Work item will be corrected via in ERRATA 5 CG 63.
ITEM NO: Attachment J-6 TITLE: Milestones
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 395
The Government has provided requirements for a start date no later than March 31st in the homeport if award is made on March 16th. If award is made on April 6th, it would seem that the job must start no later than April 21st if awarded to a homeport offeror. Is this correct, or is there a possibility that the job is actually scheduled to start in JUNE 2018 ? Please confirm and/or proivide the Government required commencement dates or options.
GOVERNMENT RESPONSE: Offerors have NOT been provided requirements for a start date no later than March 31st. Offerors have been provided significant flexibility to propose USS Gettysburg MODPRD milestones, including the Availability Start milestone. Milestone flexibility is provided to allow offerors discretion to best manage their resource constraints. The Government has provided a list of constraints around Availability Start (e.g. a minimum number of days from the contract award and vessel available milestones and Availability Start). These limits constrain how early the Availability may commence. The offeror may elect to propose an Avail Start date later than those minimum constraints.
396 COW
ITEM NO: 245-11-005
TITLE: Port and Starboard OD Boxes
PARA. NO: 3.5-3.8
PAGE NO: 2-4
CONTRACTOR QUESTION: 396
The contractor has contacted the OEM Rolls Royce for the shop rebuild of the OD boxes. Rolls Royce has stated they are currently rebuilding OD boxes for the USS COWPENS. The contractor would like clarification on how to bid the paragraphs. Recent specs from other ships only require the contractor to ship the OD boxes to the OEM and the new OD boxes are GFM. Please advise
GOVERNMENT RESPONSE: OD boxes will be provided as
GFM.
401 COW
ITEM NO: 171-11-002
TITLE: Main Mast Deferred Interference Installation;
accomplish
PARA. NO: 3.1
PAGE NO:1
CONTRACTOR QUESTION: 401
Para 3.1 states " accomplish the reinstallation of the equipment removed in SSRA 16 using 2.2 through 2.4 for guidance. This item is unbidable, For estimating purposes please provide file attachment 150-90-007 Prelim 359-interference details. And 150-90-007 prelim 359895-sub from CFR E-BAES-1535 of 2.2.
GOVERNMENT RESPONSE: Reference provided in ERRATA 5 Reference Package
402 COW
ITEM NO: 437-21-001
TITLE: Oily Waste Drain Tank Level Indicator (TLI) System; repair
PARA. NO:
PAGE NO: 2
CONTRACTOR QUESTION: 402
Para 3.4 states "Accomplish the replacement of the TLI system, identified in 1.3, for the Oily Waste Drain Tanks listed in 1.2, using 2.7 for guidance and material requirements, in accordance with Section 8 of 2.X0965-LP-109-1010 Rev 3, Tank Level Indicating (TLI) System, Type No. 36000X andTechnical Representatives' instructions. The quantity of material shall be determined and provided by the vendor at time of installation.
1. there is no reference 2.7 on the specs
2. Is the contractor replacing all 13 TLI or quantity of material shall be determined and provided by the vendor after doing open and inspect? Please advise
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG
63. Reference 2.6 replaced 2.7. Quantity of material identified in 1.3.
403 COW
ITEM NO: 533-11-007
TITLE: Brominator and Tank Inlet/Outles Flex Hose Replacment
PARA. NO: 3.1.5
PAGE NO: 2
CONTRACTOR QUESTION: 403
Accomplish the requirements of Section 8 of 2.8 for hydrostatic test of each flexible hose assembly identified in 1.3. Nominal operating pressure is 1200 PSI.
Hose clamps can not hold that psi what is the working psi for testing this flex hose
GOVERNMENT RESPONSE: Addressed in errata 5 CG 63.
500 psi for suction and recirculate and 700 psi for discharge.
404 COW
ITEM NO: 245-11-005
TITLE: Port and Starboard OD Boxes
PARA. NO: 3.5-3.8
PAGE NO: 2-4
CONTRACTOR QUESTION: 404
The contractor has contacted the OEM Rolls Royce for the shop rebuild of the OD boxes. Rolls Royce has stated they are currently rebuilding OD boxes for the USS COWPENS. The contractor would like clarification on how to bid the paragraphs. Recent specs from other ships only require the contractor to ship the OD boxes to the OEM and the new OD boxes are GFM. Please advise
GOVERNMENT RESPONSE: OD boxes will be provided as
GFM.
405 COW
ITEM NO: 343-11-003
TITLE: SSTG Lube Oil Coolers
PARA. NO: 1.3.4-1.3.6
PAGE NO: 1
CONTRACTOR QUESTION: 405
The title of the specification the is for the SSGTG lube Oil Coolers. The contractor questions why the coolers in paragraphs 1.3.4-1.3.6 are even included in this specification since they are for the MPGT MRG.
GOVERNMENT RESPONSE: Work item Title corrected to include MRG. Addressed in ERRATA 5 CG 63.
406 COW
ITEM NO: 110-11-017
TITLE: Structural Repairs, Pump Rm #1; accomplish
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 406
Accomplishment of CAT 2 NAVSEA Standard Item 009-12 to support the repairs accomplished by this work item is not called out in the specification.
Unless otherwise directed, contractor will not include it in the estimate and it will be subject to an equitable adjustment. Please review and advise.
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG63. 009-12 specified in the work item.
407 COW
ITEM NO: 897-11-001
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 407
Work item 897-11-001 appears to be a MSMO hold-over type specification and contains requirements not necessarily applicable to a firm fixed price availability.
Recommend deleting this work item from the availability (and J-7).
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG63. Work Item 897-11-001 is cancelled..
408 COW
ITEM NO: 897-11-001
TITLE:
PARA. NO: 3.1
PAGE NO:
CONTRACTOR QUESTION: 408
Work item 897-11-001, paragraph 3.1 period of performance doesnt match the revised RFP period of performance. Please advise. .
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG63. Work Item 897-11-001 is cancelled..
410 COW
ITEM NO: 042-11-002
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 410:
Milestones listed in paragraph 3.1.1.1 do not match the milestones provided as Solicitation Attachment J-3. Please clarify
GOVERNMENT RESPONSE: Use J-3 and RFP for all milestone commitments. 042 work item para 3.1.1.1 will be revised when contract has been awarded and actual start date has been released.
413 COW
ITEM NO: 992-11-004
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 413:
The response to bidder’s question #65 does not address the question asked as it only repeats the response to the unrelated bidder’s question #64. Please answer bidder’s question #65.
GOVERNMENT RESPONSE: Addressed in Errata 5 CG
63. Contractor statement is correct, Ship force to arrange fuel barge and towing services.
415 COW
ITEM NO: Multiple
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 415:
Multiple work items indicate in paragraph 5 that GFM will be provided as indicated by a referenced 4720 which is either missing or clearly incomplete.
The response to bidder’s question #290 states that the 4720’s should be considered “living documents” and updated versions will be provided.
However, in order for contractors to prepare a fixed price proposal, the Government must provide a fixed scope of work including a fixed definition of what material will be provided. It is requested that a final definitive list of all material intended to provided by the Government be issued as soon as possible.
GOVERNMENT RESPONSE: Concur with contractor.
Latest versions of 4720s will be provided as soon as they are released by the design authority.
420 GET
ITEM NO: 495-90-004
TITLE: Ship Alt 84924K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 420:
To date Reference 2.2 Rev A has not been provided to contractor.
GOVERNMENT RESPONSE: References provided on 1/26/2018.
ITEM NO: J-7 Pricing Spreadsheet
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 433:
Upon Contractor's review of Bidder's Question responses provided for “CONTRACTOR QUESTION 5” on “N00024-18-R-4439 - Bidder Questions - 1 DEC 2017” and “COW_GET_Bidders'_Questions_20171219”, both state the Government Response as “Revision of J7 provided”; the following observations remain;
1) Contractor notes that upon review of J- 7_Pricing_Spreadsheet_CG63_&_CG64_Rev_1 issued on 11/22/17 that there have been no changes to the USS Cowpens (CG-63) J-7 Pricing Spreadsheet from the original document issued on 10/06/17 and that the following issues remain unresolved;
a. Contractor notes that Work Items 042-11-002, 042-12-001, 045-11-001, 077- 11-001, 110-11-001, 110-11-003, 110-11-004, 110-11-005, 110-11-006, 110-11- 009, 110-11-010, and 110-11-011 appear to be duplicated.
b. Contractor notes that upon receipt and review of the Specification package, the following disparities with the J-7 document, as written, still remain;
(a) Work Item 042-32-001, Marine Coatings Containing Heavy Metals Material; remove and dispose is not listed.
(b) Work Item 423-90-001, Shipalt CG47-71386K, Advanced Digital Antenna Production (ADAP); accomplish is listed however was not provided in the Specification package or on ERRATA’s 1, 2, 3 or 4.
(c) Work Item 561-11-006, Steering Gear Hydraulic System; flush is listed however was not provided in the Specification package or on ERRATA’s 1, 2, 3
GOVERNMENT RESPONSE: J7 updated to reflect updated composite work package.
434 COW
ITEM NO: 711-90-002
TITLE: Ship Alt 78818.02K
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 434:
Contractor notes that upon review of USS Cowpens (CG-63) ERRATA_4, Work Specifications, the following 4720’s have not been provided.
• Work Item # 110-90-002, ShipAlt CG47-83307K, Increase Fatigue Strength Frame 138, 01 Level; accomplish Reference 2.11, 4720-CG63-FY18-SA83307 Rev 29, Ship Alteration Material Summary (4720/3)
• Work Item # 441-90-006, ShipAlt CG47-80897.03K, PEOC41 NMT AN/WSC- 9(V)XX Multiband Terminal Alteration; accomplish Reference 2.16, 4720-CG63-FY18-SA80897.03K Rev 27, Ship Alteration Material Summary (4720/3)
• Work Item # 443-90-001, ShipAlt CG47-86316K, Replace Air Horn with Electric Horn; accomplish Reference 2.14, 4720-CG63-FY18-SA86316K Rev 29, Ship Alteration Material Summary (4720/3)
• Work Item # 452-90-001, Shipalt CG47-87310.03 AN/SPS-49(V)8 Air Search Radar Removal; accomplish Reference 2.15, 4720-CG63-FY18-SA87310.03K Rev 27, Ship Alteration Material Summary (4720/3)
• Work Item # 517-90-001, ShipAlt CG47-83219.03K, Electric Conversion for Waste Heat Boilers; accomplish Reference 2.34, 4720-CG63-FY17-SA83219-03 Rev 27, Ship Alteration Material Summary (4720/3)
GOVERNMENT RESPONSE: Addressed in ERRATA 5 CG
63. No material is provided via 4720 for work item 612-80-
001. Additional 4720 provided.