COW_GET_Bidders'_Questions_20180130.pdf
PDF 43 KB Posted
- Attached to
- USS COWPENS (CG 63) and USS GETTYSBURG (CG 64) Modernization Period (MODPRD) Availabilities
- Solicitation number
- N00024-18-R-4439
About this file
COW GET Bidders' Questions 20180130
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE OF REQUEST: Tuesday, January 30, 2018
HULLS/TITLE: USS COWPENS (CG 63) & USS GETTYSBURG (CG 64)
SOLICITATION NO: N00024-18-R-4439
NAVSEA POCs:
Billy Castleberry Craig Barton
NAVSEA POC E-MAIL:
billy.castleberry@navy.mil craig.s.barton@navy.mil
NAVSEA POC #: (202) 781-1248
# HULL Contract Area Question Response
273 CG63
ITEM NO: 168-11-002
TITLE: Scuttle & Hatch, Exterior, Flush, Quick- Acting; replace
PARA. NO: 3.2.7.3
PAGE NO: 4
CONTRACTOR QUESTION : 273
HATCH 1.3.1 (02-351-1) IS IDENTIFIED FOR CHROMATE CONVERSION
COATING/ FSA UNDER 3.2.7.3, AND UNDER 3.2.7 FOR PRESERVATION
IAW 009-32
PLEASE PROVIDE DIRECTION ON REQUIREMENTS
GOVERNMENT RESPONSE: Addressed in Errata 5 CG 63.
ITEM NO: 475-11-002
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 381
Work item 475-11-002 directs contractor to accomplish visual inspections, disconnections, measurements and submit report. It then instructs the contractor to identify, isolate and remove each cable designated for removal or replacement by the direction of the supervisor.
Contractor cannot determine material or labor requirements until direction of the supervisor is accomplished.
All material and labor for replacement of new materials should be subject to equitable adjustment.
GOVERNMENT RESPONSE: Addressed in ERRATA 6 CG
63. Applies for RTR to replace cable that were identified during inspection.
ITEM NO: 314-11-001
TITLE: Errata 3, Electrical Power Supply Cables;
replace
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION: 382
Paragraph 3.1 states “Disconnect electrically and mechanically, remove existing and install new electrical power supply cables identified in 1.3 and located in 1.2, in accordance with --- 2.2 and 2.2,9, using 2.3 through 2.7 for guidance”.
• Contractor notes that ERRATA_3 added Reference 2.9, LAR 83505.02/CG63/0108, Cables ripped out below 01 Level, CFR 0822
• Contractor notes that reference 2.9 has not been provided by the Customer.
QUESTION: Can the Customer provide the above missing reference to all bidders?
GOVERNMENT RESPONSE: Reference provided 1/26
397 COW
ITEM NO: 343-11-003
TITLE: SSTG Lube Oil Coolers Clean
PARA. NO: 1.3.4-1.3.6,
paragraphs 3.1
PAGE NO:1-2
CONTRACTOR QUESTION: 397
There are three Lube oil coolers listed for the MRGs, the ship only has two MRGs. The MRG lube oil coolers are normally done in place since they are to big to remove from the ship. Please advise.
GOVERNMENT RESPONSE: Addressed in ERRATA 6 CG
398 COW
ITEM NO: 551-11-006
TITLE: Air Valves Repair
PARA. NO: 3.2.1
PAGE NO:1
CONTRACTOR QUESTION: 398
The contractor has tried numerous sources to obtain technical support. Please supply contact information for the 009-90 requirements or make this technical representative government furnished..
GOVERNMENT RESPONSE: Addressed in ERRATA 6 CG 63. 009-90 Deleted.
399 COW
ITEM NO: 529-11-015
TITLE: Valve Hydraulic Operator
PARA. NO: 3.2-3.2.1
PAGE NO:1
CONTRACTOR QUESTION: 399
The contractor has tried numerous sources to obtain technical support. Please supply contact information for the 009-90 requirements or make this technical represenative government furnished
GOVERNMENT RESPONSE: Addressed in ERRATA 6 CG 63. 009-90 Deleted.
Pre-Proposal Information (PPI)
# HULL Contract Area Question Response
400 COW
ITEM NO: 311-31-001,
311-31-0002, 311-31-003 TITLE: Gas Turbine Generator Install
PARA. NO: 3.1-3.1.1
PAGE NO: 1
CONTRACTOR QUESTION: 400
The contractor would like to know if the 009-90 services will be provided by the SWRMC gas turbine shop?
GOVERNMENT RESPONSE: Addressed in ERRATA 6 CG 63. 009-90 Deleted.
411 COW
ITEM NO: 045-11-001
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 411:
Paragraphs 3.3 and 3.3.1 appear to require all personnel to have either a CAC card, a Homeland Security PIV card, or an EID Passport Issues Rapid Gate card in order to access the vessel. All of these are either not generally issued or are no longer being issued to contractor personnel. Recommend deleting these paragraphs and having access requirements be in accordance with NSI 009-72.
GOVERNMENT RESPONSE: Addressed in Addendum1 CG
63. Work spec 045-11-002 replaced by 045-11-002.
412 COW
ITEM NO: 042-11-001
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 412:
Paragraph 3.2.5 contains schedule submission requirements which deviate from NSI 009-60. As a result, this a paragraph requires a that a the 009-60 A-0 schedule submission be submitted 14 days prior to the estimated contract award date. Recommend that this paragraph be deleted.
GOVERNMENT RESPONSE:1) Award is not planned at A-
30. Offerors shall propose their own schedule (including the timeline between award and start) based on the constraints of vessel availability and contract award provided in attachment J-3.
414 COW
ITEM NO: 813-11-001
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 414:
The response to bidder’s question #223 states that the Attachment A “ALO Compartment Release Schedule” is included as pages 5 and 6 of the work item.
This is only correct for GETTYSBURG work item 813-11-001. COWPENS work item 813-11-001 consists of only 3 pages and does include Attachment A.
Please provide Attachment A for COWPENS work item 813-11-001
GOVERNMENT RESPONSE: Refrence provided 1/26
ITEM NO: Mulitple
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 416:
Multiple bidder’s questions noted discrepancies between the work packages provided and the Attachment J-7 pricing work sheet. The response to these questions state the a revision of the J-7 has been provided, but no such revision has been issued since 11/22/2017 and that version of J-7 still contains many of those noted discrepancies. Please issue a revised J-7 as soon as possible.
GOVERNMENT RESPONSE: J7 provided on 1/26/2018
417 COW
ITEM NO: 130-11-008
(errata 4) TITLE: Main Mast Pad Replacement
PARA. NO: 3.4
PAGE NO:
CONTRACTOR QUESTION: 417
Paragraph 3.4 states; "Accomplish the removal of temporary shoring installed at locations listed in 1.2 as detailed by 2.5", Contractor question; accomplishment of reference 2.5 is not called out on the spec, therefore accomplishment of reference 2.5 and paragraph 3.4 and unless otherwise directed will not be included on the estimate and it will be subject to an equitable adjustment. Please review and advise.
GOVERNMENT RESPONSE: Addressed in ERRATA 4 CG 63.
File details come from the government source that posted it.