RSV_Questions_and_Answers_1_Rev1.docx

DOCX document 25 KB Posted

Attached to
USS ROOSEVELT (DDG 80) Fiscal Year FY 17 Depot Maintenance Period (DMP)
Solicitation number
N00024-17-R-4415
Issued by

About this file

RSV Questions and Answers 1 Rev 1

View the file

Other files

File Type Posted
RSV_Questions_and_Answers_3.docx DOCX document
RSV_Questions_and_Answers_4.docx DOCX document
J-4_Pricing_Spreadsheet_DDG_80_Rev3_LOCKED.xlsx XLSX spreadsheet
RFP_RSV_DDG_80_AMENDMENT_003.docx DOCX document
RFP_RSV_DDG_80_AMENDMENT_0002_FINAL.docx DOCX document
RFP_RSV_DDG_80_AMENDMENT_0001_FINAL.docx DOCX document
RSV_Questions_and_Answers_2.docx DOCX document
RFP_RSV_DDG_80_AMENDMENT_0002.docx DOCX document
J-3_ERL_Final_Rev_DDG_80_Rev2.xlsx XLSX spreadsheet
J-4_Pricing_Spreadsheet_DDG_80_Rev2_LOCKED.xlsx XLSX spreadsheet
RFP_RSV_DDG_80_AMENDMENT_0001.docx DOCX document
J-4_Pricing_Spreadsheet_DDG_80_Rev1_LOCKED.xlsx XLSX spreadsheet
J-5_QASP_DDG_80_Rev1.docx DOCX document
RSV_Questions_and_Answers_1.docx DOCX document
J-3_ERL_DDG_80_Final_Rev_1.xlsx XLSX spreadsheet
S-4_PP_Reference_List.docx DOCX document
S-3_PPI_Form.docx DOCX document
S-1_Technical_Capabilites_Data_Sheet.docx DOCX document
S-2_Past_Performance_Questionnaire.docx DOCX document
FBO_FINAL_RFP.docx DOCX document
S-5_Eligibility_Criteria_Data_Sheet.docx DOCX document
J-3_ERL_DDG_80.xlsx XLSX spreadsheet
J-3_Milestones_DDG_80.xlsx XLSX spreadsheet
J-4_Pricing_Spreadsheet_DDG_80_LOCKED.xlsx XLSX spreadsheet
J-5_QASP_DDG_80.docx DOCX document
FBO_DRAFT_RFP3.docx DOCX document
J-7_RTR_Control_Log_and_Form.doc DOC document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVAL SEA SYSTEMS COMMAND

N00024-17-R-4415

QUESTIONS AND ANSWERS #1

Rev 1 1 November 2016

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

1. Q. Work item 514-80-001 ShipAlt DDG51-76721, TOTS Valves In Chilled Water Risers Replace; accomplish is listed in the J-4 Pricing Spreadsheet but was not included in attachment J-1 Composite Work Package. Please clarify if the Government intends to include this work item as part of the solicitation and if so, make the work item specification available.

A. Work Item 514-80-001 is Cancelled. It is still included in the Index section of Attachment J-1 because NMD issues prevent it from being deleted.

2. Q. It is requested that the proposal due date be extended.

A. The proposal due date has been extended to 2 December 2016.

3. Q. Work item 042-51-001 is listed in the Item Index, but the specification is not included in the composite work package. Will the government please clarify if this work item is included in this solicitation?

A. Work Item 042-51-001 has been removed from the Work Package; the requirements are already delineated in Section C, Statement of Work.

4. Q. Is it the Government’s intent to list any quantities of hazardous waste in paragraph 3.5 of work item 077-11-001?

A. Paragraph 3.5 does list amounts but the table has shifted. The formatting in the table will be corrected via an Errata.

5. RESERVE

6. Q. Is it the Government’s intent to accomplish a SP-6 for all tanks listed in paragraph 1.2 within Work Item 123-12-001 as well as accomplish SP-10 for 50 square feet of plating in each tank listed in 1.2.2 – 1.2.5?

A. Work Item incorrectly identified desired intent. Errata has been generated to correct the WI. SP-6 for tank listed 1.2.1 prior to accomplishing designated structural repairs, power tool clean is authorized 50 SF of preservation for each tank listed 1.2.2 through 1.2.5.

7. Q. Will the Government please provide reference 2.2 PM 390-430, SERMC, Structural Assessment of USS Roosevelt (DGG-80) Internal Hull and Below Waterline from Work Item 110-21-001? The reference CD provided only had the front page of said reference.

A. Enclosure 2 “RSV BWLA Findings BRANDED” and 3 “RSV BWLA Photos Branded” of PM 390-430 provided to Code 400 for distribution. Enclosures are included in J-2 of Amendment 0001.

8. RESERVE

9. RESERVE

10. Q. In Work Item 243-10-00, 1Para. 3.01- Does the Pool intend to provide for paragraphs 3.02, 3.03 and 3.04, or just 3.01?

A. The Level of Effort Pool in para 3.1 is an additional pool for para 3.1 only. Paragraphs 3.2, 3.3 and 3.4 shall be estimated independently.

11. Q. Work Item 980-90-002, Paragraph 3.8 states to provide lockable, weatherproof, storage units with a minimum of 200 square feet of floor space. How many storage units should the contractor provide?

A. The requirement is a minimum of 200 square of storage space, it is incumbent upon the Executing Contractor to determine if multiple units are required to meet that requirement.

12. Q. Paragraph 3.8 states to provide lockable, weatherproof, storage units with a minimum of 200 square feet of floor space, with an 8-foot minimum ceiling, for use by the AIT, from the first day of the contract to the last day of the contract. Is the contractor supposed to price the storage units for the 90 days listed in paragraph 3.1 or for the entire contract listed in paragraph 3.8?

A. Storage unit(s) will only be required for the 90 days as listed in para 3.1. Errata to be generated to clarify para 3.8.

13. Q. Paragraph 3.1 of work item 150-80-001 states for the contractor to accomplish the requirements of 2.2, for location listed in 1.2. Is it the Government’s intent to have contractor replace piece number 1 and piece number 3 from sheet 28 of reference 2.2 or is it the intent of the Government to have the contractor only replace piece number 1 from sheet 28 of reference 2.2?

A. It is the intent to replace both piece numbers 1 and 3 from sheet 28 only from frame 130 to frame 143.

14. Q. Will the government please provide the complete Liaison Action Report number for reference 2.9 within work item 521-80-001?

A. Reference 2.9, LAR 00353/DDG80/1465 is cancelled and will be deleted from the Work Item via Errata One.