Planning
USS ROOSEVELT (DDG 80)
FY17 DMP
| 17Apr17 - 13Jul18 (452 days) | ||||||
| 452 Calendar Days / XX Production Days (M-F) | ||||||
| Start Date: | 17-Apr-17 | |||||
| PLANNING MILESTONES | ||||||
| Key Event/Milestone | JFMM (FFP) | Proposed | Actual Completion | |||
| A- | Date | A- | Date | A- | Date | |
| Task/Fund 3PP | N/A | N/A | 42842 | |||
| Send HAB Project Adv Planning Notice | 420 | 22-Feb-16 | 42842 | 42842 | ||
| Request Adv Planning Funding | 410 | 3-Mar-16 | 42842 | 42842 | ||
| Provide Avail Financial Target Control | 360 | 22-Apr-16 | 42842 | 42842 | ||
| Issue Letter of Authorization (Including AITs) | 360 | 22-Apr-16 | 42842 | 42842 | ||
| Establish Avail in NMD | 360 | 22-Apr-16 | 42842 | 42842 | ||
| A-360 IPTD Event | 360 | 22-Apr-16 | 42842 | |||
| Task/Fund SID Development | 330 | 22-May-16 | 42842 | 42842 | ||
| Modernization Ship Checks Complete | 300 | 21-Jun-16 | 42842 | 42842 | ||
| Provide Incremental Funding for LLTM | 270 | 21-Jul-16 | 42842 | 42842 | ||
| TSRA 1 Complete | 240 | 20-Aug-16 | 42842 | 42842 | ||
| 50% D-Level Lock | 240 | 20-Aug-16 | 42842 | 42842 | ||
| 50% Lock IPTD Event (2 days) | N/A | N/A | 42842 | 42842 | ||
| 3PP Complete Work Assigned at 50% Lock | N/A | N/A | 42842 | 42842 | ||
| Issue/Deliver SIDs to NSA for KTRs and AITs | 240 | 20-Aug-16 | 42842 | 42842 | ||
| Submitt A-240 Deferral Letter | 230 | 30-Aug-16 | 42842 | 42842 | ||
| 80% D-Level Lock | 220 | 9-Sep-16 | 42842 | 42842 | ||
| IGE Submitted in Support of 50% Lock | 215 | 14-Sep-16 | 42842 | 42842 | ||
| 80% Lock IPTD Event (2 days) | N/A | N/A | 42842 | 42842 | ||
| 3PP Complete Work Assigned at 80% Lock | N/A | N/A | 42842 | 42842 | ||
| IGE Submitted in Support of 80% Lock | 215 | 14-Sep-16 | 42842 | 42842 | ||
| Request Exec Funding for Repair & Modernization | N/A | N/A | 42842 | 42842 | ||
| TSRA 2 Complete | 210 | 19-Sep-16 | 42842 | 42842 | ||
| LOA Change 1 Issued | 210 | 19-Sep-16 | 42842 | 42842 | ||
| Late Add Impact Assessment | N/A | N/A | 42842 | 42842 | ||
| Identify AIT Support Reqts/POA&M Provided | 210 | 19-Sep-16 | 42842 | 42842 | ||
| All Modernization Risk Assessments Submitted | 205 | 24-Sep-16 | 42842 | 42842 | ||
| A-180 Risk Letter Submitted to CNRMC | 200 | 29-Sep-16 | 42842 | 42842 | ||
| 100% D-Level Lock | 200 | N/A | 42842 | 42842 | ||
| Final Specs Delivered to Govt Planners | N/A | N/A | 42842 | 42842 | ||
| Planning Pkg Verified & Ready for Solicitation | N/A | N/A | 42842 | 42842 | ||
| Contract Specialist Issues RFP | N/A | N/A | 42842 | 42842 | ||
| Addendum Package Lock | N/A | N/A | 42842 | 42842 | ||
| Final Work Item Review/Approval | 197 | 2-Oct-16 | 42842 | 42842 | ||
| 100% Planned & Estimated | 197 | 2-Oct-16 | 42842 | 42842 | ||
| 3PP Complete Work Assigned at 100% Lock | 196 | 3-Oct-16 | 42842 | 42842 | ||
| IGE Submitted in Support of Addendum Pkg | 195 | 4-Oct-16 | 42842 | 42842 | ||
| All Modernization Risk Assessments Approved | 196 | 3-Oct-16 | 42842 | 42842 | ||
| Award AIT for Work Not Done by Prime KTR | 196 | 3-Oct-16 | 42842 | 42842 | ||
| IGE Submitted in Support of 100% Lock | 195 | 4-Oct-16 | 42842 | 42842 | ||
| Solicit Bids | 188 | 11-Oct-16 | 42842 | 42842 | ||
| LOA Change 2 Issued | 185 | 14-Oct-16 | 42842 | 42842 | ||
| A-120 Risk Letter Submitted to CNRMC | 185 | 14-Oct-16 | 42842 | 42842 | ||
| Cutoff for Bidders Questions | 164 | 4-Nov-16 | 42842 | 42842 | ||
| Submit Bids | 145 | 23-Nov-16 | 42842 | 42842 | ||
| Cost Team Completes Cost Evaluation | 138 | 30-Nov-16 | 42842 | 42842 | ||
| Cost Team Completes Tech | 138 | 30-Nov-16 | 42842 | 42842 | ||
| Cost/Tech (SSEB) Report Reviewed | 132 | 6-Dec-16 | 42842 | 42842 | ||
| Late Add Impact Assessment | 132 | 6-Dec-16 | 42842 | 42842 | ||
| I-Level Work Fully Brokered | 130 | 8-Dec-16 | 42842 | 42842 | ||
| I-Level Work Fully Accepted | 115 | 23-Dec-16 | 42842 | 42842 | ||
| 100% O-Level Lock | 115 | 23-Dec-16 | 42842 | 42842 | ||
| SSA Briefs & Discussions Recommendation | 119 | 19-Dec-16 | 42842 | 42842 | ||
| Contract Specialist Submits Pre-BCM | 104 | 3-Jan-17 | 42842 | 42842 | ||
| BCM Approved/Govt Completes Discussions | 101 | 6-Jan-17 | 42842 | 42842 | ||
| Bidders/Govr Completes Discussions | 94 | 13-Jan-17 | 42842 | 42842 | ||
| Provide Avail Funding for Repair & Modernization | 75 | 1-Feb-17 | 42842 | 42842 | ||
| Govt Requests Final Proposal Revisions | 90 | 17-Jan-17 | 42842 | 42842 | ||
| Bidders Submit Final Proposal Revisions | 84 | 23-Jan-17 | 42842 | 42842 | ||
| Cost/Tech (SSEB) Report Reviewed | 80 | 27-Jan-17 | 42842 | 42842 | ||
| SSA Selects Source | 76 | 31-Jan-17 | 42842 | 42842 | ||
| Contract Specialist Submits BCM | 73 | 3-Feb-17 | 42842 | 42842 | ||
| BCM Approved | 69 | 7-Feb-17 | 42842 | 42842 | ||
| Submit I-Level Work Pkg for Integration | 60 | 16-Feb-17 | 42842 | |||
| Award Contract Basic Package/Addendum Package | 60 | 16-Feb-17 | 42842 | 42842 | ||
| Post-Award Conference (Govt Only) | N/A | N/A | 42842 | |||
| Post-Award Conference (Govt & KTR) | N/A | N/A | 42842 | |||
| PICOs Complete | N/A | N/A | 42842 | 42842 | ||
| Deliver LLTM/Kitted Material | 30 | 18-Mar-17 | 42842 | 42842 | ||
| A-30/WPER IPTD Event (2 days) | 30 | 18-Mar-17 | 42842 | 42842 | ||
| Barge Arrives | N/A | N/A | 42842 | 42842 | ||
| Arrival Conference | N/A | N/A | 42842 | 42842 | ||
| AVAIL START DATE | 0 | 17-Apr-17 | 42842 | 42842 |
Execution
USS ROOSEVELT (DDG 80)
FY17 DMP
| 17Apr17 - 20Apr18 (368 days) | |||||||
| 368 Calendar Days / 265 Production Days (M-F) | |||||||
| Start Date: | 17-Apr-17 | ||||||
| EXECUTION MILESTONES / KEY EVENTS | |||||||
| Key Event/Milestone | Current | Revised | Revised | ||||
| Week | A+ | Date | A+ | Date | A+ | Date | |
| AVAIL START DATE | 0 | Monday, April 17, 2017 | |||||
| Ship Arrives at KTR Plant | 0 | Monday, April 17, 2017 | 12 | ||||
| Defueling Complete | 0.57 | 4 | Friday, April 21, 2017 | ||||
| Crew move Ashore Comp | 1.00 | 7 | Monday, April 24, 2017 | ||||
| Dock (NLT) | 2.43 | 17 | Thursday, May 04, 2017 | ||||
| HM&E Turnover One | 10.00 | 70 | Monday, June 26, 2017 | ||||
| 20% Open & Inspect Complete | 10.57 | 74 | Friday, June 30, 2017 | ||||
| HM&E Turnover 2 | 12.00 | 84 | Monday, July 10, 2017 | ||||
| 25% Conference | 13.43 | 94 | Thursday, July 20, 2017 | ||||
| HM&E Turnover 3 | 14.00 | 98 | Monday, July 24, 2017 | ||||
| NMT Turnover One | 15.00 | 105 | Monday, July 31, 2017 | ||||
| HM&E Turnover 4 | 16.00 | 112 | Monday, August 07, 2017 | ||||
| NMT Turnover 2 | 19.43 | 136 | Thursday, August 31, 2017 | ||||
| FM Light Off | 19.57 | 137 | Friday, September 01, 2017 | ||||
| HM&E Turnover 5 | 21.00 | 147 | Monday, September 11, 2017 | ||||
| Undock (NLT) | 21.43 | 150 | Thursday, September 14, 2017 | ||||
| HM&E Turnover 6 | 23.00 | 161 | Monday, September 25, 2017 | ||||
| HM&E Turnover 7 | 25.00 | 175 | Monday, October 09, 2017 | ||||
| HM&E Support Systems Restoration | 25.57 | 179 | Friday, October 13, 2017 | ||||
| 50% Conference | 26.43 | 185 | Thursday, October 19, 2017 | ||||
| HED KTR Complete | 28.00 | 196 | Monday, October 30, 2017 | ||||
| ADNS Turnover | 28.00 | 196 | Monday, October 30, 2017 | ||||
| CANES FDN/PPG Complete | 28.00 | 196 | Monday, October 30, 2017 | ||||
| CS Turnover One | 29.57 | 207 | Friday, November 10, 2017 | ||||
| Production Completion Date | 31.00 | 217 | Monday, November 20, 2017 | ||||
| CS Turnover 2 | 31.57 | 221 | Friday, November 24, 2017 | ||||
| Fuel One | 32.00 | 224 | Monday, November 27, 2017 | ||||
| ISIC Safe to Operate | 32.00 | 224 | Monday, November 27, 2017 | ||||
| CS Turnover 3 | 32.57 | 228 | Friday, December 01, 2017 | ||||
| Combat Systems Support Equipment | 32.57 | 228 | Friday, December 01, 2017 | ||||
| Hot Plant Testing - Start | 33.00 | 231 | Monday, December 04, 2017 | ||||
| CS Turnover 4 | 33.57 | 235 | Friday, December 08, 2017 | ||||
| Hab Complete | 34.00 | 238 | Monday, December 11, 2017 | ||||
| CS Turnover 5 | 34.43 | 241 | Thursday, December 14, 2017 | ||||
| AEGIS Light Off | 34.57 | 242 | Friday, December 15, 2017 | ||||
| Crew Move Aboard Commence | 35.00 | 245 | Monday, December 18, 2017 | ||||
| 75% Conference | 39.43 | 276 | Thursday, January 18, 2018 | ||||
| Hot Plant Testing - Complete | 39.86 | 279 | Sunday, January 21, 2018 | ||||
| CANES Light Off/SW Load | 40.00 | 280 | Monday, January 22, 2018 | ||||
| CANES SIPR Migration | 43.43 | 304 | Thursday, February 15, 2018 | ||||
| CANES NIPR Migration | 44.43 | 311 | Thursday, February 22, 2018 | ||||
| LOA Preps | 46.00 | 322 | Monday, March 05, 2018 | ||||
| Light Off Assessment | 50.00 | 350 | Monday, April 02, 2018 | ||||
| CANES Testing Complete | 50.86 | 356 | Sunday, April 08, 2018 | ||||
| Fuel Ship | 51.00 | 357 | Monday, April 09, 2018 | ||||
| Dock Trials | 51.29 | 359 | Wednesday, April 11, 2018 | ||||
| Fast Cruise | 51.43 | 360 | Thursday, April 12, 2018 | ||||
| Crew Rest | 51.71 | 362 | Saturday, April 14, 2018 | ||||
| KTR Sea Trials Begin | 52.00 | 364 | Monday, April 16, 2018 | ||||
| KTR Sea Trials Complete | 52.57 | 368 | Friday, April 20, 2018 | ||||
| KTR End Date | 52.57 | 368 | Friday, April 20, 2018 |