Attachment J-4 – Award Fee Intra-Availability Milestones
Required completion date Maximum Award Fee
A+151 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
Undocking
This milestone is considered complete when all work and testing is complete, OQE is completely reviewed and is on file and all work has been properly certified, as described in the Work Items listing below. All MSR contractor related production work must be complete (and satisfactorily tested with required OQE submitted certified and accepted by the SUPERVISOR in accordance with
NSSAINST 5400.1). The term complete is defined to mean the accomplishment of contractor responsible work that makes it possible to safely undock the vessel in accordance with the NSA approved plan and MIL-STD-1625D. The MSR shall certify by signature and serialized letter to the PCO that all work specification requirements (production, checkpoints, inspections, testing reports, WAFs) associated with the Key Event milestone have been satisfactorily completed. The availability Event Readiness List (ERL) shall be used to associate work specifications and testing to the specific Undocking Key Event.
Undocking Work Items
110-11-003 Freeboard Structure Repair
110-11-004 Strut inspect and repair
110-90-001 SA 70438K
113-11-001 Machinery Space Bilge Drain Well
123-11-002 Groups one and three inspect, repair and preserve
123-11-003 Group 2 inspect, repair and preserve
123-11-004 Group 3 inspect, repair and preserve
123-11-005 Group 4 inspect, repair and preserve
123-11-006 Group 5 inspect, repair and preserve
123-11-007 Group 6 inspect, repair and preserve
123-11-008 Accessible voids and cofferdam inspect, repair and preserve
123-11-009 FO Bolted plate manhole cover
123-11-010 FO Service tank inspect and preserve
123-14-002 Potable water tank inspect and preserve
123-17-001 Contaminated oil tank inspect, repair and preserve
150-11-008 Inner Bottom plate repair
161-80-001 SA 64204D
163-11-001 Sea chest inspect and preserve
163-11-002 Waster sleeve replace
165-11-001 Lower Sonar Dome access scuttle repair
165-11-002 Sonar Dome valve replace
243-11-001 Stern tube shaft seals
243-11-003 Shafting
243-12-003 Shafting
243-80-002 SA 73395D
244-11-001 Bearing clearance
244-12-001 Shaft alignment
245-11-001 CPP STBD
245-12-001 CPP Port
437-21-001 TLI replace and test
437-90-001 SA 77829K
520-11-001 Sea valve repair and replace
521-80-002 SA 75829D
562-11-001 Rudder bearing seal
562-11-002 Rudder repair
562-11-003 Rudder Stock Bearing
562-80-001 AER 64269
593-11-001 VCHT tanks
593-11-002 VCHT tank level switch
593-11-003 VCHT chemical flush
631-11-004 Underwater log trunk preserve
631-11-005 Tank top repairs
631-13-001 Chain locker repair and preserve
631-41-001 Freeboard preservation
633-11-002 Zinc anodes
See Below $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set
Required Reports Complete
1) This incentive is considered complete when all Required Reports that could result in a change in work to be accomplished or additional material to be procured are accepted and approved by the Supervisor. The contractor shall complete the preliminary work and submit one legible copy of all Required Reports, in approved transferrable media no later than the first 25 percent point of the availability (A+66).
2) Dry dock and Tank related required inspection reports shall be submitted no later than the first 30 days of the scheduled docking period.
3) Dry dock related reports which contain readings (final, thickness, etc.), clearances, alignments, paint data sheets, or other such data for work certification must be submitted and approved by the Supervisor prior to pre-flood/undocking (A+151).
All reports across paragraphs 1, 2 and 3 above must be provided by their associated due dates to successfully complete this milestone.
A+55 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #1
In the following Compartments:
4-254-0-E; MER-2
1-158-4-Q; OPS Office
1-206-3-A; Repair-5
1-268-0-C; Central Control Station
1-300-0-C; Combat Systems Equipment Room #3
3-300-0-C; IC/Gyro Room #2
4-370-6-A; Supply Dept Storeroom #4
3-310-2-L; Crew Berthing #5
3-220-2-Q; Supply Support Center
3-126-2-Q; Power Supply Conversion Room
3-97-02-L; Crew Berthing #2
4-94-0-C; IC/GYRO Room #1
4-126-0-E; AUX-1
3-220-01-A; Supply Dept Storeroom #1
3-300-1-L; Crew Berthing #4
3-338-1-L; Crew Berthing #6
2-300-01-L; Crew Berthing #3
1-254-6-L; Passageway
1-174-01-L; Passageway
Complete the following contractor responsible work, in accordance with the work item listed below:
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation and Hydrostatic testing of hydraulic piping disturbed by the installation of GEDMS Maintenance Group.
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this turnover.
Preservation and painting of new and disturbed foundations and disturbed surfaces.
IAW the following work items:
438-90-002; 73088K, GEDMS Upgrade
A+69 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth
HM&E Turnover #2
4-174-0-E; MER-1
1-206-3-A; Repair-5
1-268-0-C; Central Control Station
1-97-1-A; Repair-2
01-130-2-Q; Admin Office
01-130-0-Q; Combat System Maintenance Central
4-126-0-E; AUX-1
1-78-01-L; Passageway
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
654-90-001; 71604K, Machinery Control System Upgrade (MCS)
A+83 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth
HM&E Turnover #3
4-174-0-E; MER-1
1-97-1-A; Repair-2
01-130-0-Q; Combat System Maintenance Central
4-126-0-E; AUX-1
4-442-0-E; Steering Gear Room
2-381-2-Q; Electrical Workshop
2-410-2-A; Repair-3
1-304-2-A; Repair-5A / DC Equip Office
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
A+99 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth
HM&E Turnover #4
4-254-0-E; MER-2
4-442-0-E; Steering Gear Room
2-410-2-A; Repair-3
3-370-0-E; #3 Generator Room
4-94-0-C; IC/Gyro Room #1
2-126-2-C; Combat Systems Equipment Room #2
3-300-0-C; IC/Gyro Room #2
02-133-1-L; Passageway
03-142-2-Q; Electronic Workshop #1
1-126-0-C; Combat Information Center
04-130-0-C; Pilot House
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
438-90-001; 71726K, Integrated Bridge Navigation System Upgrade (IBNS)
A+111 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth
HM&E Turnover #5
2-53-1-C; Combat Systems Equipment Room #1
03-142-2-Q; Electronic Workshop #1
1-126-0-C; Combat Information Center
04-130-0-C; Pilot House
2-370-3-A; Supply Dept Storeroom #2
2-78-01-L; Crew Berthing #1
1-18-0-Q; Sonar Equipment Room #1
01-130-0-Q; Combat System Maintenance Center
2-338-1-L; Passageway
4-370-5-A; Supply Storeroom #3
2-126-1-C; Radio Central
1-84-1-Q; GSE WKSHP / Inert Gas Cylinder Storeroom
2-116-1-T; Access Trunk
03-128-0-C; RADAR Room #1
03-142-0-C; RADAR Room #2
03-128-1-Q; Array Room #1
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
A+121 $400,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth
HM&E Turnover #6
2-53-1-C; Combat Systems Equipment Room #1
4-126-0-E; AUX-1
4-174-0-E; MER-1
4-254-0-E; MER-2
3-370-0-E; #3 Generator Room
03-142-2-Q; Electrical Load Center Room #1
1-254-2-Q; Electrical Load Center Room #2
3-126-2-Q; Power Conversion Room #1
3-319-0-Q; Power Conversion Room #2
3-300-0-C; IC/Gyro Room #2
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
654-90-001; 71604K, Machinery Control System Upgrade (MCS)
; 80612K, Integrated Conditioning and Assessment System Install (ICAS)
A+145 $280,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth
HM&E Turnover #7
3-18-0-Q; Sonar Room #3
4-126-0-E; AUX-1
4-174-0-E; MER-1
4-220-0-E, AUX-2
4-254-0-E; MER-2
5-300-01-E; A/C Machinery Room
3-370-0-E; #3 Generator Room
4-442-0-E; Steering Gear Room
1-191-0-Q; Crew Galley
02-158-6-L; Wardroom Galley
1-238-1-Q; Scullery
2-414-0-Q; Laundry
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
654-90-001; 71604K, Machinery Control System Upgrade (MCS)
541-90-001; Shipalt DDG51-70403K, Digital Fuel Control System Installation, accomplish
437-90-001; Shipalt DDG51-77829K, Installation of RADAR & TDR TLIs for DFM, JP-5 and Potable Water Tanks, accomplish
A+181 $520,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set
Hot Plant Testing
Complete contractor responsible work on the following HM&E support systems, to facilitate Generator Light-Off (GLO) and
Main Engine Light-off (MELO) for Hot Plant Testing in accordance with the work items listed below:
Generator and Main Engine Intake, Uptake, and Exhaust
VCHT/Plumbing Waste Drain Tanks, Pumps, and System
Firepumps and Firemain System
Main Sea Water Service Pumps and System
Potable Water Tanks, Pumps, Brominators, and System
Low Pressure Air Compressors and System
High Pressure Air Compressors and System
Chill Water Circulating Pumps, Expansion Tanks, and System
Air Conditioning Units
Bleed Air System
Fan Rooms, Plenums, Ducting, and Fans for Engineering and CPS Zones 1-4
Lube Oil Service Pumps, Sumps, Filters, Purifiers, Heaters, Coolers, and System
Controllable Reversible Pitch Propeller Pumps, Sumps, Heaters, Filters, Hubs, Blades, Oil Distribution Box, Power
Module, and System
Fuel Oil Storage Tank Banks, Purifiers, Transfer Pumps, and Fill & Transfer System
Fuel Oil Service Tanks, Pumps, Filters, and System
Gas Turbine Generators, Modules, and Onboard Support Systems
60HZ Switchboards and Load Centers
Main Gas Turbine Engines, Modules, and Onboard Support Systems
Main Propulsion Shafting and Shaft Seals
110-11-002; Trap Door Repair, accomplish
123-11-001; Sounding Tube Plumb Bob Stuck in Sounding Tube, report and remove
123-12-001; JP-5 Tank, inspect and preserve
123-14-001; Potable Water Tanks Suction Line, repair
234-11-001; Main Propulsion Gas Turbine Module (GTM) Resilient Mount, replace
259-11-001; Engine Room No. One Uptake, repair and preserve
259-11-002; Gas Turbine (GTRB) Exhaust Duct Collector, repair
259-80-001; Shipalt DDG51-76087D, Gas Turbine (GTRB) and Ship Service Gas Turbine Generator (SSGTG)
Boundary Layer Infrared Suppression System (BLISS) Cap Modification, accomplish
259-80-002; Shipalt DDG51-64215D, Gas Turbine (GTRB) Uptake Flange Bolting Replacement, accomplish
262-11-001; Main Reduction Gear (MRG) Lube Oil Cooler, repair
262-11-002; Main Reduction Gear (MRG) Lube Oil Cooler, repair
Hot Plant Testing, cont’
437-90-003; Shipalt DDG51-77269K, Installation of Redundant Tank Level Indicators (TLI) on Generator Head
Tanks, accomplish
512-11-003; Galley and Laundry Ventilation Cleaning, accomplish
512-80-001; Shipalt DDG51-64238D, Collective Protection System Supply/Exhaust Hoods, replace
512-90-001; Shipalt DDG51-77419K, Textile Ducting Installation, accomplish
514-80-001; Shipalt DDG51-64216D, Fan Room Condensation Drainage Modifications, accomplish
514-80-002; Shipalt DDG51-76721D, TOTS Valve Installation, accomplish
521-11-001; Firemain Electric Motor Operated Valve Repair, accomplish
521-80-002; Shipalt DDG51-73738D, Installation of Additional Bulkhead Cutout Valves, accomplish
523-80-001; Shipalt DDG51-64254D, Countermeasure Washdown Bulkhead Penetration Sleeve Installation, accomplish
526-11-001; Low Pressure Air Supply Piping, replace
528-80-002; Shipalt DDG51-77690D, 02 Level Intake and Uptake Drains, accomplish
528-80-004; Shipalt DDG51-64240D, Uptake Drain Piping Overboard Routing, accomplish
532-11-001; Potable Water (FWC) Valve and Air Conditioning Chilled Water Circulation (CWR) Valve, replace
593-90-001; Shipalt DDG51-73622K, VCHT H2S Detector Installation, accomplish
624-11-001; Balanced Joiner Door, remove, store, repair, and install
631-11-001; Pressure Zone (PZ) Fan Rooms, prepare and preserve
631-11-003; Fan Room, repair and preserve
634-11-001; Cosmetic Polymeric Deck Covering System (Oil Lab), resurface
992-31-002; Off-Load, Testing, Storage, and On-Load of Ship’s Petroleum Fuels and Lubricants, accomplish
262-90-001; Shipalt DDG51-76253, Install L/O Coalescing Filter, accomplish
; Shipalt DDG51-85973K, L/O Purifier Heater Heat Exchanger, replace