INDEX
SHIP: USS MCFAUL NSSA-501-16
ITEMS THAT ARE STRUCK OUT ON THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-16 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE
DATETITLEITEM NO.
009-01 General Criteria; accomplish 02-Jan-15
009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide
02-Jan-15
009-03 Toxic and Hazardous Substances; control 02-Jan-15
009-04 Quality Management System; provide 02-Jan-15
009-05 Temporary Accesses; provide 02-Jan-15
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish
02-Jan-15
009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish
02-Jan-15
009-08 Fire Protection at Contractor's Facility; accomplish 02-Jan-15
009-10 Shipboard Asbestos-Containing Material (ACM); control 02-Jan-15
009-18 Magnetic Material; control 02-Jan-15
009-19 Provisioning Technical Documentation (PTD); provide 02-Jan-15
009-20 Government Property; control 02-Jan-15
009-21 Logistics and Technical Data; provide 02-Jan-15
009-23 Interferences; remove and install 02-Jan-15
009-24 Authorization, Control, Isolation, Blanking, and Tagging Requirements; accomplish
02-Jan-15
009-28 Fire Prevention Requirements; accomplish 02-Jan-15
009-29 Asbestos-Free Pipe Hanger Liner Material; install 02-Jan-15
Page 1 of 12 ERRATA NO. 7
009-34 Fire Protection of Unmanned Vessels at Contractor's Facility;
provide
02-Jan-15
009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish
02-Jan-15
009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/ Component;
provide
02-Jan-15
009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval Facilities; accomplish
02-Jan-15
009-59 Organotin Antifouling Material; control 02-Jan-15
009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration; provide and manage
02-Jan-15
009-61 Shipboard Use of Fluorocarbons; control 02-Jan-15
009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 02-Jan-15
009-65 Polychlorinated Biphenyls (PCBs); control 02-Jan-15
009-67 Integrated Total Ship Testing; manage 02-Jan-15
009-69 Heavy Weather/Mooring Plan; provide 02-Jan-15
009-70 Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish
02-Jan-15
009-72 Physical Security at Private Contractor's Facility; accomplish 02-Jan-15
009-73 Shipboard Electrical/Electronic/Fiber Optic Cable; remove, relocate, repair, and install
02-Jan-15
009-74 Occupational, Safety and Health Requirements; accomplish 02-Jan-15
009-77 Cofferdam Requirements; accomplish 02-Jan-15
009-79 Government Owned Material (GOM); status reporting 02-Jan-15
009-80 Ship's Facilities; provide 02-Jan-15
009-81 Compartment Closeout; accomplish 02-Jan-15
009-82 Data Requirements When Installing an Equal Component Vice Specified Component; provide
02-Jan-15
Page 2 of 12 ERRATA NO. 7
009-83 Wire Rope Fitting Verfication; provide 19-Feb-15
009-84 Accountability of Temporary Fasteners; provide 13-Feb-15
009-86 Recovery of Chlorofluorocarbon (CFC) Refrigerants and Fire Suppressant Halon (H) Materials; accomplish
13-Feb-15
009-87 Chemical disinfection Procedures; accomplish 13-Feb-15
009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify
02-Jan-15
009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes; accomplish
02-Jan-15
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide
02-Jan-15
009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish
02-Jan-15
009-95 Mechanically Attached Fittings (MAF's) for Piping Systems;
install
02-Jan-15
009-97 Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide
02-Jan-15
009-99 Ship Departure Report; provide 02-Jan-15
009-100 Ship's Stability Process Control Procedure (PCP); maintain 02-Jan-15
009-101 Requirements for Entry to and Departure from Contractor's Facility; accomplish
02-Jan-15
009-102 Alteration Verification; provide 02-Jan-15
009-103 Weight and Moment Change Data; provide 02-Jan-15
009-106 Work Authorization Form Coordinator (WAFCOR); provide 02-Jan-15
009-108 Aircraft Carrier Requirements for Entry to, Movement within, and Departure from Contractor's Facility; accomplish
02-Jan-15
009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels; accomplish
02-Jan-15
009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels;
accomplish
02-Jan-15
009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage
02-Jan-15
Page 3 of 12 ERRATA NO. 7
009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards;
accomplish
02-Jan-15
009-118 CG Deck Loading; accomplish 02-Jan-15
009-120 Fact Finding and Critique of Unplanned Events; manage 02-Jan-15
009-121 Ship Assessment/Inspection Requirements; provide 02-Jan-15
Page 4 of 12 ERRATA NO. 7
DATETITLEITEM NO.
CATEGORY II. FY-15 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER
009-09 Process Control Procedure (PCP); provide and accomplish 06-Jan-14
009-09 Process Control Procedure (PCP); provide and accomplish 02-Jan-15
009-11 Insulation and Lagging Requirements; accomplish 02-Jan-15
009-11 Insulation and Lagging Requirements; accomplish 17-Jan-13
009-12 Welding, Fabrication, and Inspection Requirements;
accomplish
09-Sep-15
009-12 Welding, Fabrication, and Inspection Requirements;
accomplish
09-Sep-15
009-12 Welding, Fabrication, and Inspection Requirements;
accomplish
07-Nov-13
009-12 Welding, Fabrication, and Inspection Requirements;
accomplish
02-Jan-15
009-12 Welding, Fabrication, and Inspection Requirements;
accomplish
02-Jan-15
009-13 Meters; repair and certify calibration 02-Jan-15
009-13 Meters; repair and certify calibration 02-Jan-15
009-13 Meters; repair and certify calibration 02-Jan-15
009-14 Gages, Switches, and Thermometers; repair and certify calibration
02-Jan-15
009-14 Gages and Thermometers; repair and certify calibration 17-Jan-13
009-16 Electronic Equipment; repair 02-Jan-15
009-16 Electronic Equipment; repair 02-Jan-15
009-17 Rotating Electrical Equipment; repair 02-Jan-15
009-22 Shipboard Electric Cable; test 17-Jan-13
009-25 Structural Boundary Test; accomplish 02-Jan-15
009-25 Structural Boundary Test; accomplish 02-Jan-15
009-25 Structural Boundary Test; accomplish 02-Jan-15
009-25 Structural Boundary Test; accomplish 02-Jan-15
Page 5 of 12 ERRATA NO. 7
009-25 Structural Boundary Test; accomplish 17-Jan-13
009-25 Structural Boundary Test; accomplish 02-Jan-15
009-26 Deck Covering Requirements; accomplish 02-Jan-15
009-26 Deck Covering Requirements; accomplish 02-Jan-15
009-26 Deck Covering Requirements; accomplish 17-Jan-13
009-26 Deck Covering Requirements; accomplish 02-Jan-15
009-26 Deck Covering Requirements; accomplish 02-Jan-15
009-32 Cleaning and Painting Requirements; accomplish 07-Nov-13
009-32 Cleaning and Painting Requirements; accomplish 02-Jan-15
009-32 Cleaning and Painting Requirements; accomplish 17-Jul-15
009-32 Cleaning and Painting Requirements; accomplish 17-Jul-15
009-32 Cleaning and Painting Requirements; accomplish 17-Jul-15
009-36 Controller; repair 29-Jul-11
009-36 Controller; repair 02-Jan-15
009-43 Engineering Plant Production Completion Date (PCD), Light-Off Assessment (LOA) Support; provide
02-Jan-15
009-47 Gate Valve; repair 29-Jul-11
009-50 Horizontal Swing Check Valve; repair 29-Jul-11
009-51 Globe, Globe Angle, and Globe Stop Check Valve; repair 17-Jan-13
009-52 Relief Valve; repair 29-Jul-11
009-55 Regulating/Reducing Valve; repair 30-Jul-10
009-57 Reduction Gear Security Requirements; accomplish 02-Jan-15
009-57 Reduction Gear Security Requirements; accomplish 02-Jan-15
009-63 Lubricating Oils and Hydraulic Fluids; analyze 02-Jan-15
009-71 Testing Requirements for Piping Systems; accomplish 21-Jul-15
009-71 Testing Requirements for Piping Systems; accomplish 21-Jul-15
Page 6 of 12 ERRATA NO. 7
009-71 Testing Requirements for Piping Systems; accomplish 17-Jan-13
009-71 Testing Requirements for Piping Systems; accomplish 02-Jan-15
009-76 Waveguide and Transmission Line Temporary Lay-Up, Pressurization, and Purging; accomplish
02-Jan-15
009-76 Waveguide and Transmission Line Temporary Lay-Up, Pressurization, and Purging; accomplish
29-Jul-11
009-78 Passive Countermeasures System (PCMS) Material Repair/Installation Requirements; accomplish
02-Jan-15
009-78 Passive Countermeasures System (PCMS) Material Repair/Installation Requirements; accomplish
02-Jan-15
009-78 Passive Countermeasures System (PCMS) Material Repair/Installation Requirements; accomplish
07-Nov-13
009-90 Technical Representative; provide 02-Jan-15
009-90 Technical Representative; provide 07-Nov-13
009-90 Technical Representative; provide 02-Jan-15
009-90 Technical Representative; provide 02-Jan-15
009-90 Technical Representative; provide 02-Jan-15
009-98 Monel Fasteners; inspect 30-Jul-10
009-98 Monel Fasteners; inspect 02-Jan-15
009-107 Piping System Cleanliness (Non-Nuclear); accomplish 02-Jan-15
009-107 Piping System Cleanliness (Non-Nuclear); accomplish 02-Jan-15
009-107 Piping System Cleanliness (Non-Nuclear); accomplish 17-Jan-13
009-117 Support for Combat Systems Light-Off; provide 02-Jan-15
Page 7 of 12 ERRATA NO. 7
ITEM NO. TITLE
110-11-002 Trap Door Repair; accomplish
110-90-001 ShipAlt DDG51-70438 Bow Strengthening Modifications and Material List; accomplish
113-11-001 Machinery Space Bilge Drain Well; repair and preserve
120-10-001 Tank Top Plating and Margin Plate; repair
123-11-002 Fuel Oil & Exp Ovfl Tanks, Group One; inspect, repair and preserve
123-11-003 Fuel Oil Tanks, Group 2; inspect and preserve
123-11-004 Fuel Oil Tanks, Group 3; inspect and preserve
123-11-007 Fuel Oil Tank, Group 6; inspect and preserve
123-11-009 Fuel Oil Bolted Plate Manhole Cover; repair
123-11-011 Oily Waste Drain Collecting Tank Bolted Plate Manhole Cover;
replace
123-17-001 Contaminated Oil and Waste Tanks; inspect, repair and preserve
150-11-002 SLQ 32 Platform; inspect, repair and preserve
150-11-003 02 Level Deck; repair and preserve
150-11-004 02 LVL Deck and Bulkhead Area; repair and preserve
150-11-005 Exterior Foundation Repair; accomplish
150-11-006 02 Level structure; repair and preserve
150-11-009 02 Level Deck and Non-Skid; repair
150-11-010 Interior Bulkhead and Side Shell Repair; accomplish
150-11-016 Structural Repair; accomplish
163-11-002 Waster Sleeve; replace
163-80-001 S/A 85309D, Bubble Shield Optimal Configuration; accomplish
165-11-002 Sonar Dome Pressurization System Valves; replace
Page 8 of 12 ERRATA NO. 7
167-11-001 Bolted Equipment Removal Plate (BERP) Repair; accomplish
167-80-002 ShipAlt DDG51-72424D, MAFO-Holtkamp Door Installation;
accomplish
167-80-004 ShipAlt DDG51-76258D, MAFO-Holtkamp Door Installation;
accomplish
168-11-001 Cargo Door; repair
245-11-001 Controllable Pitch Propeller (CPP) System, STBD Propeller Hub;
replace
245-11-002 Controllable Pitch Propeller (CPP) System, STBD; repair
245-12-001 Controllable Pitch Propeller (CPP) System, Port Propeller Hub;
replace
245-12-003 Controllable Pitch Propeller (CPP) System, PORT; repair
251-31-002 Intake; preserve
251-31-003 Air Intake and Exhaust Louver; preserve
259-11-001 Engine Room No.One Uptake; repair and preserve
259-11-003 Uptake Engine Room / Ship Service Gas Turbine Generator Exhaust Flange Gasket and Fasteners; replace
259-11-004 Uptake; preserve
262-11-001 Main Reduction Gear (MRG) Lube Oil Cooler; repair
262-90-001 ShipAlt DDG51-76253K, Install Lube Oil Coalescing Filter;
accomplish
300-11-001 Cable and Cableway Inspection; accomplish
321-80-001 DDG51 Class AER 64201D, Stuffing Tube Replacement (Partial);
accomplish
411-90-001 ShipAlt DDG51-77427K, DDGM Digital Indicators Installation:
accomplish
421-80-001 ShipAlt DDG51-76853D, Magnetic Compass Tec Refresh;
accomplish.
437-90-001 ShipAlt DDG51-77829K, Installation of Radar and Time Domain Reflectrometer (TDR), Tank Level Indicator (TLI) for Diesel Fuel Marine (DFM), JP-5 and Potable Water Tanks; accomplish
438-90-001 ShipAlt DDG51-71726K, DDG Mod Full IBS Upgrade, Single Bridge Watchstander; accomplish
438-90-002 ShipAlt DDG51-73088K, Gigabit Ethernet Data Multiplex System (GEDMS) Upgrade; accomplish
Page 9 of 12 ERRATA NO. 7
441-90-001 ShipAlt DDG51-81443K Navy Multiband Terminal(NMT) AN/WSC-9(V)1 X/KA Installation via ShipAlt DDG51-01102 Common Radio IDD; accomplish (OPTION ITEM)
451-11-001 AN/SPS-67(V)5 Surface Search Radar; replace
456-90-001 ShipAlt DDG51-84530K, AWS: Peripherals Upgrade to SPRS (OJ-839(V)1/U) Installation; accomplish (OPTION ITEM)
463-80-001 SHIPALT DDG51-76231D, Sonar Stave Cable Connectorization and Transducer Element Replacement; accomplish
468-90-001 ShipAlt DDG51-83192K, AN/SQQ-89A(V)15 W/TI-12 Hardware on DDG 54, 56 and 77; accomplish (OPTION ITEM)
508-11-001 Pipe Lagging; replace
508-11-002 Chill Water Pipe Lagging; replace
520-11-001 Sea Valve; repair and replace
523-80-001 ShipAlt DDG51-64245D Countermeasure Washdown Bulkhead Penetration Sleeve Installation; accomplish
526-11-001 Low Pressure Air Station Filter/Regulator/Lubricator; replace
541-90-001 ShipAlt DDG51-70403K, Digital Fuel Control System Installation;
accomplish
562-11-001 Rudder Bearing Seal and Rudderstock Seal; Repair
583-11-001 Boat Handling and Stowage System; repair and preserve
593-11-001 Vacuum, Collecting, Holding, and Transfer (VCHT) and Plumbing Drain Tanks; repair and preserve
602-11-001 Label Plate; replace
622-12-001 Nomex Deck Panel; replace
622-12-002 Nomex Deck Panel; replace
622-12-003 Nomex Deck Panel; replace
624-11-001 Balanced Joiner Door; remove, store, repair and install
631-11-001 Pressure Zone (PZ) Fan Room; prepare and preserve
631-11-002 Laundry Bulkhead Structure and Deck Covering; repair and preserve
631-11-003 Fan Room; repair and preserve
631-11-007 Collective Protection System (CPS) Zone One Fan Room; repair and preserve
Page 10 of 12 ERRATA NO. 7
631-11-009 Collective Protection System (CPS) Zone 2 Fan Room; repair and preserve
631-11-010 Number One Vacuum, Collection, Holding and Transfer (VCHT) Room Deck; preserve
631-11-011 Collective Protection System (CPS) Zone 4 Fan Room; repair and preserve
631-11-012 Collective Protection System (CPS) Zone 3 Fan Room; repair
631-11-015 Shaft Alley Bilge; preserve
631-41-001 Freeboard Preservation; accomplish
633-11-002 Zinc Anode; replace
634-11-017 Terrazzo Deck Covering System; install
634-21-002 Flight Deck Nonskid; replace
644-11-001 Sheathing and Bulkhead; clean and repair
651-90-001 ShipAlt DDG51-71605K, DDG Mod Advanced Galley Installation;
accomplish
654-11-001 Cosmetic Polymeric Deck Covering System; replace
654-90-001 ShipAlt DDG51-71604K, DDG Mod MCS/DCS Upgrades, Single Central Control Station (CCS) Watchstander; accomplish
813-11-001 AEGIS Light-Off (ALO) Compartment Release Schedule; provide
857-11-007 Berthing Barge Towing and Support Services; provide
980-11-002 Ship's Force Office Space, Class Room and Parking Facilities Ashore; provide
980-90-002 ShipAlt DDG-51 LM2500 Digital Fuel Control (EC-70619), Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
980-90-003 ShipAlt DDG-74 SCD-81301, BEWT II Hardware Install, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
980-90-004 DDG51 Class OrdAlt 20353, ELEC CNTRL VLVS on C&D WTR CLR), Alteration Installation Team (AIT) Support Service; provide (OPTION
ITEM)
980-90-005 SHIPALT DDG51-70403K, 71604K, 71726K, 73088K, 77829, 77427
Asset Recovery; provide.
980-90-006 ShipAlt DDG-51-84530K, AWS: Peripherals Upgrade to SP, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
Page 11 of 12 ERRATA NO. 7
980-90-007 SHIPALT DDG51-71615K, DDG MOD, Digital Video Surveillance System (DVSS) SHIPALT DDG51-76869K, 1MC Announcing System Upgrade SHIPALT DDG51-76974K, Moriah HW for DDG MOD SHIPALT DDG51-77259K, EM Log RPL AN/WSN-9(V)1 DHYSL SHIPALT DDG51-71688K, SIWCS, Alteration Installation Team (AIT) Support Service; provide
980-90-008 ShipAlt DDG51-79686K, Close In Weapon System (CIWS) Block 1B Next Generation, and Ordalt 78221 Close, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
980-90-010 ShipAlt DDG-51-81077K, SSEE INCR E, BLADE SERVER UPGRADE, Alteration Installation Team (AIT) Support Service; provide
(OPTION ITEM)
980-90-012 ShipAlt DDG-51-77333K, CKT3TV Camera System Install, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
980-90-013 ShipAlt DDG-51-83940K, AWS: Peripheral Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
980-90-014 DDG51 Class OrdAlt-82668, ASTAB COTS Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
980-90-016 ShipAlt DDG-51-80315, AFFF and CMWD SOPV Replacement, Alteration Installation Team (AIT) Support Service; provide (OPTION
ITEM)
980-90-017 ShipAlt DDG51-75913K, BFTT T46D Upgrade, Alteration Installation Team Support (AIT); provide (OPTION ITEM)
980-90-018 SHIPALT DDG51-70403K, 71604K, 71726K, 73088K, 77829, 77427
Alteration Installation Team (AIT) Support Services; provide.
982-31-003 Machinery Space Production Completion and Requirement for Light-Off Assessment (LOA)(Complex); accomplish
992-11-012 Crane, Rigging and Forklift Service for MK82 Directors; provide
992-21-001 TYCOM and Mid Atlantic Regional Maintenance Center (MARMC) Office Space; provide
992-21-002 Small Boat Storage and Repair Facility; provide (Option Item)
992-21-004 Regional Maintenance Center (RMC) Office Space With Computer, in plant/downriver availability; provide
992-26-001 Fleet Technical Assessment (FTA) Team Support; provide
992-31-001 Cleaning, Pumping and Gas Free; accomplish
993-11-005 TYCOM Warehouse Storage Space; provide
993-11-006 NAVSEA Warehouse Storage Space; provide
993-31-003 Temporary Main Reduction Gear (MRG) Dehumidifier System; provide
Page 12 of 12 ERRATA NO. 7