Attachment J-5 – Award Fee Intra-Availability Milestones
Required completion date Maximum Award Fee
A+171 $225,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
Undocking This milestone is considered complete when all work and testing is complete, OQE is completely reviewed and is on file and all work has been properly certified, as described in the Work Items listing below. All MSR contractor related production work must be complete (and satisfactorily tested with required OQE submitted certified and accepted by the SUPERVISOR in accordance with NSSAINST 5400.1). The term complete is defined to mean the accomplishment of contractor responsible work that makes it possible to safely undock the vessel in accordance with the NSA approved plan and MIL-STD-1625D. The Master Ship Repair (MSR) shall certify by signature and serialized letter to the PCO that all work specification requirements (production, checkpoints, inspections, testing reports, WAFs) associated with the Key Event milestone have been satisfactorily completed. The availability Event Readiness List (ERL) shall be used to associate work specifications and testing to the specific Undocking Key Event.
IAW the following work items:
437-90-001; SA 77829K, Install Radar and TDR TLI’s for DFM, JP-5 and Potable Water 541-90-001; SA 70403K, Digital Fuel Control System Installation 593-90-001; SA 73622K, Installation of H2S Detectors in VCHT Rooms
Required completion date Maximum Award Fee
See Below $725,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
Required Reports Complete
1) This incentive is considered complete when all Required Reports that could result in a change in work to be accomplished or additional material to be procured are accepted and approved by the Supervisor. The contractor shall complete the preliminary work and submit one legible copy of all Required Reports, in approved transferrable media no later than the first 25 percent point of the availability (A+80).
2) Dry dock and Tank related required inspection reports shall be submitted no later than the first 30 days of the scheduled docking period.
3) Dry dock related reports which contain readings (final, thickness, etc.), clearances, alignments, paint data sheets, or other such data for work certification must be submitted and approved by the Supervisor prior to pre-flood/undocking (A+157).
All reports across paragraphs 1, 2 and 3 above must be provided by their associated due dates to successfully complete this milestone.
A+58 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #1
In the following Compartments:
• 4-174-0-E; MER-1
• 4-254-0-E; MER-2
• 1-158-4-Q; OPS Office
• 1-206-3-A; Repair-5
• 1-268-0-C; Central Control Station
• 1-300-0-C; Combat Systems Equipment Room #3
• 4-370-6-A; Supply Department Storeroom #4
• 3-310-2-L; Crew Berthing #5
• 3-220-2-Q; Supply Support Center
• 3-126-2-Q; Power Supply Conversion Room
• 3-97-02-L; Crew Berthing #2
• 4-94-0-C; IC/GYRO Room #1
• 4-126-0-E; AUX-1
• 3-220-01-A; Supply Dept Storeroom #1
• 3-300-1-L; Crew Berthing #4
• 3-338-1-L; Crew Berthing #6
• 2-300-01-L; Crew Berthing #3
• 1-254-6-L; Passageway
• 1-174-01-L; Passageway
• 1-258-3-Q; Engineering Department Office
Complete the following contractor responsible work, in accordance with the work item listed below:
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation and Hydrostatic testing of hydraulic piping disturbed by the installation of GEDMS Maintenance Group.
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this turnover.
• Preservation and painting of new and disturbed foundations and disturbed surfaces.
• Installation of GTM Main Engine Digital Fuel Controls
431-90-001; SA 73088K Gigabit Ethernet Data Multiplex System (GEDMS) Upgrade 980-90-008; ShipAlt EC 70619K Alteration Installation Team (AIT) Support Service
A+72 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #2
In the following Compartments:
• 4-174-0-E; MER-1
• 1-206-3-A; Repair-5
• 1-268-0-C; Central Control Station
• 01-130-2-Q; Admin Office
• 01-130-0-Q; Combat System Maintenance Central
• 4-126-0-E; AUX-1
• 1-78-01-L; Passageway
• 1-84-1-Q; Weapons Department Office
• 01-122-0-L; Passageway
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
• Installation and hydro testing of piping systems removed as interferences or relocated.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this turnover.
438-90-002; SA 71604K DDG Modification MCS/DCS Upgrades Single Watchstander
A+86 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #3
In the following Compartments:
• 4-174-0-E; MER-1
• 1-97-1-A; Repair-2
• 01-130-0-Q; Combat System Maintenance Central
• 4-126-0-E; AUX-1
• 4-442-0-E; Steering Gear Room
• 2-381-2-Q; Electrical Workshop
• 2-410-2-A; Repair-3
• 1-304-2-A; Repair-5A / DC Equip Office
• 2-395-2-A; Electrical Tool Issue
• 2-116-1-T; Access Trunk
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
• Installation and hydro testing of piping systems removed as interferences or relocated.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
A+100 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #4
In the following Compartments:
• 4-254-0-E; MER-2
• 4-442-0-E; Steering Gear Room
• 2-410-2-A; Repair-3
• 3-370-0-E; #3 Generator Room
• 4-94-0-C; IC/Gyro Room #1
• 2-126-2-C; Combat Systems Equipment Room #2
• 3-300-0-C; IC/Gyro Room #2
• 03-133-1-L; Passageway
• 03-142-2-Q; Electronic Workshop #1
• 1-126-0-C; Combat Information Center
• 04-130-0-C; Pilot House
• 2-174-8-Q; Test Lab
• 03-142-2-Q; Electrical Load Center No.1
• 03-154-2-L; Passageway
• 02-154-1-L; Passageway
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
• Installation and hydro testing of piping systems removed as interferences or relocated.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
441-90-001; SA 71726K DDG Modification Full IBS Upgrade Single Bridge Watchstander
A+114 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #5
In the following Compartments:
• 2-53-1-C; Combat Systems Equipment Room #1
• 1-126-0-C; Combat Information Center
• 04-130-0-C; Pilot House
• 2-370-3-A; Supply Department Storeroom #2
• 2-78-01-L; Crew Berthing #1
• 1-18-0-Q; Sonar Equipment Room #1
• 01-130-0-Q; Combat System Maintenance Center
• 2-338-1-L; Passageway
• 4-370-5-A; Supply Storeroom #3
• 2-126-1-C; Radio Central
• 03-128-0-C; RADAR Room #1
• 03-142-0-C; RADAR Room #2
• 03-128-1-Q; Array Room #1
• 04-150-0-C; Chart Room
• 02-146-1-L; CO Cabin In Port
• 04-158-01-L; CO Cabin At-Sea
• 1-100-2-Q; Security Force Issue Room
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
• Installation and hydro testing of piping systems removed as interferences or relocated.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
441-90-001; SA 71726K DDG Modification Full IBS Upgrade Single Bridge Watchstander
A+128 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #6
In the following Compartments:
• 2-53-1-C; Combat Systems Equipment Room #1
• 4-126-0-E; AUX-1
• 4-174-0-E; MER-1
• 4-220-0-E; AUX-2
• 4-254-0-E; MER-2
• 3-370-0-E; Generator Room
• 3-300-0-C; IC/Gyro Room #2
• 3-18-0-C; Sonar Equipment Room #3
• 1-78-01-L; Passageway
• 1-84-1-Q; Weapons Department Office
• 1-174-01-L; Passageway
• 1-220-5-L; Passageway
• 1-300-01-L; Passageway
• 4-110-0-E; VCHT Room #1
• 4-300-0-E; VCHT Room #2
• 5-300-01-E; A/C Machinery Room
• 2-338-4-L; Crew Library
• 4-442-0-E; Steering Gear Room
• 2-410-0-L; Passageway
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
• Installation and hydro testing of piping systems removed as interferences or relocated.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this
431-90-001; SA 73088K, Gigabit Ethernet Data Multiplex System (GEDMS) Upgrade 438-90-002; SA 71604K, DDG Modification MCS/DCS Upgrades Single Watchstander 441-90-001; SA 71726K, DDG Modification Full IBS Upgrade Single Bridge Watchstander 980-90-009; SA 71615K, DDG Mod Digital Video Surveillance System (DVSS) 438-90-003; SA 80612K, Integrated Conditioning and Assessment System Install (ICAS)
A+142 $150,000
Award fee criteria for this intra-availability milestone is set forth in HQ B-2-0003 Determination of Fee Paragraph (f), using the ratings set forth in Paragraph (h) to determine the award fee earned.
HM&E Turnover #7
In the following Compartments:
• 4-126-0-E; AUX-1
• 4-174-0-E; MER-1
• 4-220-0-E, AUX-2
• 4-254-0-E; MER-2
• 5-300-01-E; A/C Machinery Room
• 3-370-0-E; #3 Generator Room
• 4-442-0-E; Steering Gear Room
• Fuel Oil Tank Groups 1-6
• JP-5 Storage, Service and Stripping Tanks
• Potable Water Tanks
• NR1 and NR2 MRG L/O Sumps
• Port and Starboard CPP L/O Sumps
• All Waste Drain Collecting Tanks
• Fuel Oil Service Tanks and Generator Head Tanks (Two Tank Groups at A+142, A+149 and A+156)
• Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
• Installation of interferences disturbed by the ripout and/or installation of equipment under this turnover.
• Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
• Installation and hydro testing of piping systems removed as interferences or relocated.
• Installation and welding complete of new cableways to include cable trays / ladders.
• Installation of lagging removed or disturbed by the ripout and/or installation of foundations or equipment under this turnover.
• Preservation and painting of new and disturbed foundations and disturbed surfaces.
• Installation of Radar, TDR and Redundant TLIs in all tanks
• Modifications and repairs to JP-5 piping, valves and tanks
• Complete all work associated with fan rooms associated with Engineering spaces and CPS Zones 1, 2, 3 and 4
• Installation of Main Reduction Gear/Controllable Pitch Propeller Lube Oil Filter Separators
• Modification to lube oil Purifier Heat Exchangers
262-90-001; SA 76253K, Main Reduction Gear/Controllable Pitch Propeller Lube Oil Purifier Replace with Filter Separator 264-90-001; SA 85973K, DDG Lube Oil Purifier Heat Exchanger Modification 431-90-001; SA 73088K, Gigabit Ethernet Data Multiplex System (GEDMS) Upgrade 437-90-001; SA 77829K, Installation of RADAR & TDR TLIs for DFM, JP-5 and Potable Water Tanks, accomplish 437-90-002; SA 77269K, Installation of Redundant Tank Level Indicators (TLI) on Generator Head Tanks 438-90-002; SA 71604K DDG Modification MCS/DCS Upgrades Single Watchstander 541-90-001; SA 70403K, Digital Fuel Control System Installation, accomplish 542-90-001; SA 76034K, Modify JP-5 Piping to Allow Emergency JP-5 Supply to Number 3 Gas Turbine Generator Head Tank and ML