DDG-60_Mod_Critical_Path_Turnover_Schedule.pdf

PDF 78 KB Posted

Attached to
USS PAUL HAMILTON (DDG 60) EDSRA
Solicitation number
N00024-16-R-4400
Issued by

About this file

Response to Questions (DDG - 60 Mod Critical Path Turnover Schedule)

View the file

Other files

File Type Posted
N55236_170001_FBO.pdf PDF
N00024_170014_FBO.pdf PDF
N00024_170015_FBO.pdf PDF
N00024_170019_FBO.pdf PDF
N00024_170024_FBO.pdf PDF
N00024_170023_FBO.pdf PDF
N00024_170017_FBO.pdf PDF
N00024_170016_FBO.pdf PDF
N000024_170012_FBO.pdf PDF
N00024_170013.pdf PDF
N55236_170025_FBO.pdf PDF
N55236_17006_FBO.pdf PDF
JA_215N_redact.pdf PDF
JA_270N_redact.pdf PDF
JA_222N_redact.pdf PDF
JA_3_REDAC6.pdf PDF
JA_4_REDACT.pdf PDF
Redacted_Hamilton_JA2.pdf PDF
JA_PAUL_HAMILTON_REDACT.pdf PDF
DDG-60_RFP_Q_AND_A_-_FINAL.docx DOCX document
J-4_Pricing_Spreadsheet__(Amend_0010).xlsx XLSX spreadsheet
Amend_0010.pdf PDF
Amend_0010_conformed.pdf PDF
J A_DDG_60_Directed_Subcontractors.pdf PDF
DDG-60_RFP_Q_AND_A_-__357_-_361.pdf PDF
Amendment_0009.pdf PDF
Amend_0009.pdf PDF
Amend_0009_conformed.pdf PDF
J-3_Execution_Milestones_(Amend_0008).xlsx XLSX spreadsheet
Amend_0008_Conformed.pdf PDF
Amend_0008.pdf PDF
DDG-60_RFP_Q_AND_A_356.docx DOCX document
N00024-16-R-4400-0007_Released.docx DOCX document
N00024-16-R-4400_CONFORMED_0007.docx DOCX document
DDG-60_RFP_Q_AND_A_-___250_-_345.pdf PDF
813-11-001_-_ALO_Compartment_Release_Schedule.pdf PDF
DDG_60_AC_Conversion_POAM_plants__1_and__4.mpp MPP file
SI_Index_0204.pdf PDF
Amend_0006.pdf PDF
Amend_0006_Conformed.pdf PDF
Amendment_0005.pdf PDF
J-7_Quality_Assurance_Surveillance_Plan_Amend_0005.pdf PDF
Amendment_0005_Conformed.pdf PDF
DDG-60_RFP_Q_AND_A_-___98_-_249_FBO.pdf PDF
Amend_0004_conformed.pdf PDF
Amend_0004.pdf PDF
J-4_Pricing_Spreadsheet__(Amend_0003).xlsx XLSX spreadsheet
J-7_Quality_Assurance_Surveillance_Plan_(Amend_0003).pdf PDF
Amend_0003.pdf PDF
J-5_Award_Fee_Intra_Availability_(Amend_0003).pdf PDF
Show 40 more

Latest 50 of 74 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scheduled Revised Actual End A+ Dates 1 SCHEDULED AVAIL START Monday, July 11, 2016 0 2 DOCK SHIP Monday, August 08, 2016 28 3 SPS -73 SAOP REMOVAL (PHD) Tuesday, August 16, 2016 36 4 TURNOVER 1 Wednesday, September 07, 2016 58 5 TURNOVER 2 Wednesday, September 21, 2016 72 6 GEDMS SOFTWARE LOAD (INITIAL) (NAVSSES ISEA) Monday, September 26, 2016 77 7 GEDMS MESH B POWER UP (NAVSSES ISEA) Wednesday, September 28, 2016 79

8 TURNOVER 3 Wednesday, October 05, 2016 86 9 GEDMS TEMPORARY 4GMG (COMMS AVAILABLE/ NAVSSES ISEA) Thursday, October 06, 2016 87 10 25% CONFERERNCE Tuesday, October 18, 2016 99 11 TURNOVER 4 Wednesday, October 19, 2016 100 12 CONDUCT TIE IN/CTM INSTALL #1 SWBD, LC 31) A+105-106 Monday, October 24, 2016 105 13 CONDUCT TIE IN/CTM INSTALL #3 SWBD LC 11, 21) A+107-108 Wednesday, October 26, 2016 107 14 CONDUCT TIE IN/CTM INSTALL #2, 1SA SWBD start 2nd shift) A+109-111 Friday, October 28, 2016 109

15 START FDS INITIAL HARNESS CHECKS (NAVSSES ISEA) Tuesday, November 01, 2016 113 16 TURNOVER 5 Wednesday, November 02, 2016 114 17 TURNOVER 6 Wednesday, November 16, 2016 128

MCS/EC/FDS POWER UP, EP/ MCS/EC/SW LOAD (includes TIWS) (NAVSSES ISEA) Tuesday, November 29, 2016 141

COLD PLANT TESTING (14 WEEKS A+141- 239) (MCS/EC GROUND ISO/SIG

VER MER1/2) Tuesday, November 29, 2016 141

20 START DC SENSOR TESTING (NAVSSES ISEA) Tuesday, November 29, 2016 141 21 GEDMS MESH A POWER UP (NAVSSES ISEA) Tuesday, November 29, 2016 141 22 TURNOVER 7 Wednesday, November 30, 2016 142 23 LOFSP SA 76253 Installed Wednesday, November 30, 2016 142 24 MRG LOP Heat Exchanger mod complete S/A85973 Wednesday, November 30, 2016 142 25 2 TANK GROUPS TURNED OVER Ready for Testing TDR/TLI Wednesday, November 30, 2016 142 26 PW SYSTEM (electronics only) Wednesday, December 07, 2016 149 27 2 TANK GROUPSTURNED OVER Ready for Testing TDR/TLI Wednesday, December 07, 2016 149 28 TLI/FCS TESTING Tuesday, December 13, 2016 155 29 FINAL 2 TANK GROUPS TURNED OVER Ready for Testing TDR/TLI Wednesday, December 14, 2016 156 30 UNDOCK Thursday, December 29, 2016 171 31 START SYSTEM RESTORATION (A+179-280) Friday, January 06, 2017 179 32 ICAS SW LOAD (NAVSSES ISEA) Tuesday, January 17, 2017 190 33 DIU/NEW EQUIPMENT CALIBRATION Tuesday, January 17, 2017 190 34 50% CONFERENCE Wednesday, January 25, 2017 198 35 START DVSS TESTING (NAVSSES ISEA) Tuesday, February 14, 2017 218 36 IBNS POWER UP (NAVSSES ISEA) Tuesday, February 14, 2017 218 37 START IBNS SIGNAL VERIFICATION/ S/W LOAD (NAVSSES ISEA) Tuesday, February 21, 2017 225 38 DIGITAL INDICATORS Friday, February 24, 2017 228 39 DVSS Training (NAVSSES ISEA) Wednesday, March 08, 2017 240 40 RUDDER SWING CHECKS Wednesday, March 08, 2017 240

41 MACHINERY SPACE PHASED TURNOVER (A+255-279) Thursday, March 23, 2017 255

START COMMAND & CONTROL TESTING (NAVSSESS ISEA) (6 WEEKS

A+255-297) Thursday, March 23, 2017 255

Ventilation System Machinery spaces complete, All circuit tie-ins complete and ready for power up in Eng spaces, CPS Z4 Exhaust and suppy IOT refuel/HPT Friday, April 07, 2017 270

44 EOSS CHECKS (NAVSSES ISEA) (A+274-281) Tuesday, April 11, 2017 274 45 VENT SYSTEM (Zones 1,2 & 3 complete to Support HAB, CPS) Friday, April 14, 2017 277 46 AHSS SYSTEM COMPLETE (INCUDING VENT MOD) Friday, April 14, 2017 277 47 MACHINERY SPACE TURNOVER COMPLETE Sunday, April 16, 2017 279 48 ALL SYSTEM RESTORATION COMPLETE Monday, April 17, 2017 280 49 LOFSP Testing/Training (OEM/ISEA) Tuesday, April 18, 2017 281 50 FCS TRAINING FOR SHIPS FORCE (NAVSSES ISEA) Tuesday, April 18, 2017 281 51 DFC TRAINING (NAVSSES ISEA) Tuesday, April 18, 2017 281 52 SPS-73 ISEA Connectorize SAOP Monday, April 24, 2017 287 53 PCD Monday, April 24, 2017 287 54 AHSS VENT VELOCITY TESTING Commence (MSR) 14 DAYS Monday, April 24, 2017 287 55 DCMA 1 Tuesday, April 25, 2017 288 56 FUEL SHIP (A+288-291) Tuesday, April 25, 2017 288 57 RSC TRAINING (NAVSSES ISEA) Tuesday, April 25, 2017 288 58 ALO COMPARTMENT RELEASE TURNOVER #1 Friday, April 28, 2017 291 59 SAFE TO STEAM (294-298) Monday, May 01, 2017 294 60 ALO COMPARTMENT RELEASE TURNOVER #2 Monday, May 01, 2017 294 61 TIWS TRAINING (NAVSSES ISEA) Tuesday, May 02, 2017 295 62 75% CONFERENCE Thursday, May 04, 2017 297 63 AHSS CALIBRATION/TESTING/TRAINING (ISEA/OEM) Monday, May 08, 2017 301 64 ALO COMPARTMENT RELEASE TURNOVER #3 Monday, May 08, 2017 301 65 HAB COMPLETE Monday, May 08, 2017 301 66 GALLEY MOD COMPLETE Monday, May 08, 2017 67 HOT PLANT TESTING (NAVSSES 302-330) Tuesday, May 09, 2017 302 68 ALO COMPARTMENT RELEASE TURNOVER #4 Monday, May 15, 2017 308

DDG MOD CROTCAL PATH EQUIPMENT TURNOVER SCHEDULE

MAJOR MILESTONES REV: (15) DATE: (10/22/15)

69 AEGIS LIGHT OFF/CANES POWER UP Monday, May 15, 2017 308 70 ICAS TESTING/TRAINING (NAVSSES ISEA) Tuesday, May 16, 2017 309 71 AHSS CERTIFICATION (NHRC REP JAY HEANEY) Tuesday, May 16, 2017 309

72 MOVE ABOARD COMMENCE/HAB COMPLETE TBD

73 COMMENCE NETWORK MIGRATION - CANES Tuesday, May 30, 2017 323 74 NAVSSI/67/73 RADAR AVAILABLE FOR IBNS TESTING (NAVSSES ISEA) Wednesday, May 31, 2017 324 75 DCMA 2 Monday, June 05, 2017 329 76 COMPLETE NETWORK MIGRATION - CANES Tuesday, June 06, 2017 330 77 HOT PLANT TESTING COMPLETE Tuesday, June 06, 2017 330 78 BEGIN LOA PREP (A+331-344) Wednesday, June 07, 2017 331

79 CREW MOVE ABOARD COMPLETE TBD

80 LOA PHASE 1 (GO-NO GO/MOCK LOA) Tuesday, June 20, 2017 344 81 LOA PHASE 2 (A+350-353) Monday, June 26, 2017 350 82 IBNS TRAINING FOR SHIPS FORCE (NAVSSES ISEA) (5 DAYS) Tuesday, July 11, 2017 365 83 IOS (3 DAYS) / IBNS OPERATOR BUFFER (NAVSSES ISEA) (2 DAYS) Monday, July 17, 2017 371 84 DOCK TRIALS Thursday, July 27, 2017 381 85 FAST CRUISE Friday, July 28, 2017 382 86 SEA TRIALS (A+385-389) Monday, July 31, 2017 385 87 IBNS U/W TRAINING (NAVSSES ISEA) (A+385-389) Monday, July 31, 2017 385

88 MOVE SHIP TO NAVSTA TDB

89 END OF AVAIL Friday, August 11, 2017 396

99 TLI TESTING (FUELING AT SEA) TBD TBD

100 IBNS MAINTENANCE TRAINING (NAVSSES ISEA) (9 DAYS) Post Sea Trials TBD 101 FINAL SW LOAD (NAVSSES ISEA) Post Sea Trials TBD

25Aug09 3of7

Equipment A + Date Comments

SPS-73 ISEA's Disconnect SAOP for relocation 36 16-Aug-16

All Power Sources and Terminal Boxes for Equipment in A+48, A+62 & A+76 to also include new and upgrades sources*

58 07-Sep-16 Power requirements for turnovers 1.2 & 3 are provided in attachment #1 of this document

GEDMS Mesh B (BSE 1-10) T/O 58 07-Sep-16

GEDMS Mesh A BSE's (BSE A3, A4 & A10) and power cables affecting 1st T/O IOU's 58 07-Sep-16

Mount BSE enclosure and provide J2 Connector and cable for IOU power. Fiber not required until MESH A light off (BSE A3:

J2: 3-210-2-1L-C) (BSE A10: J2: 3-210-2-1L-G) (BSE A4: J2:

LC25-1L-A8)

IOU's 31, 32, 34, 42, 72, 82 58 07-Sep-16

C-DR Boxes 12, 13, 14, 14A, 15, 16, 24,37 58 07-Sep-16 Install FDS ITB Mod kit for the following ITBs 12,13,14,15,16,17,&

USEs 31A, 31B, 32A, 32B, 34A, 34B, 42A, 72A, 82A & All Associated UPSs, Relay Enclosures, Junction Boxes & C/O Switches

58 07-Sep-16

UCCs 1 & 2 72 21-Sep-16

RSC&UPS DCC, C/O Switch, Printer & Speaker 72 21-Sep-16 Hold monitors and keyboard for later installation per SMR

RSC & UPS Repair 5, C/O Switch, Speaker 72 21-Sep-16 Hold monitors and keyboard for later installation per SMR TIWS (CCS) 72 21-Sep-16 LAN Drop & power to receptacle IOUs: 73, 74, 83, 84, 94 72 21-Sep-16

C-DR Boxes 7, 8, 8A, 11, 25, 26, 72 21-Sep-16 Install FDS ITB Modification Kit for the following ITB's; 2,4,6 7, 8, 11, 26, USEs 73A, 74A, 74C, 83A, 83B, 84A, 94A & All Associated UPSs, Relay Enclosures, Junction Boxes & C/O Switches

72 21-Sep-16

GEDMS Mesh A BSE's (A6 & A9) and power cables affecting 2nd T/O IOU's 72 21-Sep-16

Mount BSE enclosure and provide J2 Connector and cable for IOU power. Fiber not required until MESH A light off (BSE A9:

J2: LC33-1L-H5) (BSE A6: J2: 3- LC25-1L-A12)

Electric Plant DIU 1 (Power/Network/Shipside cabling) 86 05-Oct-16

Propulsion DIU 4 (Power/Network/Shipside cabling) 86 05-Oct-16

UCC 3 86 05-Oct-16 ECs 1A, 1B (Power ISO XFMRS /Network/ Shipside cabling) 86 05-Oct-16

FADC 1 86 05-Oct-16 RSC Repair 2, C/O Switch, Speaker 86 05-Oct-16 Hold monitors and keyboard for later installation per SMR TIWS (MER 1) 86 05-Oct-16 LAN Drop and Receptacle

L/O Valves Associated with SCD 71604 (MER1) 86 05-Oct-16 MRG, L/O, CRP, & F/O Filter Sep outlet

RSC & UPS CSMC, C/O Switch, Speaker & Access Cut 86 05-Oct-16 Hold monitors and keyboard for later installation per SMR

Fire Detection System ITB Upgrade Electrical Mods & Cabling for IOU's in T/O's 1,2,3 86 05-Oct-16

IOUs: 22, 33, 53, 61, 62 86 05-Oct-16

GEDMS Mesh A BSE's (A2) and power cables affecting 3rd T/O IOU's 86 05-Oct-16

Mount BSE enclosure and provide J2 Connector and cable for IOU power. Fiber not required until MESH A light off (BSE A2:

J2: (3-210--2-1L-D)

C-DR Boxes 5, 5A,19, 21, 22, 23, ; C-DR Boxes for Digital Indictaors 32, 33, 34, 35 & 36 86 05-Oct-16 nstall FDS ITB Modification Kit for the following ITB's; 5, 19, 20, 22, 23, & 24 USEs 22A, 33A, 61A, 62A & All Associated UPSs, Relay Enclosures, Junction Boxes & C/O Switches

86 05-Oct-16

USS Hamilton DDG-60

DDGM BF Critical Path Equipment/Cable SY to AIT & Test Requirement Turnover Schedule

Turnover 1

Turnover 2

Turnover 3

25Aug09 4of7

USS Hamilton DDG-60

DDGM BF Critical Path Equipment/Cable SY to AIT & Test Requirement Turnover Schedule

Electric Plant DIU 2 (Power/Network/Shipside Cabling

100 19-Oct-16

Electric Plant DIU 3 (Power/Network/Shipside Cabling

100 19-Oct-16

Propulsion DIU 5 (Power/Network/Shipside Cabling) 100 19-Oct-16

Fuel Oil Lab PC 100 19-Oct-16

All Power Sources and Terminal Boxes for Equipment in A+90, A+104, A+118 & A+132 100 19-Oct-16 Power requirements for turnovers 4,5,6 & 7 are provided in attachment #2 of this document

UCC 4 100 19-Oct-16 RSC & UPS Repair 3, C/O Switch, Speaker 100 19-Oct-16 Hold monitors and keyboard for later installation per SMR ECs 2A, 2B (Power ISO XFMRS/Network/ Shipside Cabling) 100 19-Oct-16

ADACS Control Unit 100 19-Oct-16 FADCs 2 & 3 100 19-Oct-16 TIWS (MER 2) 100 19-Oct-16 LAN Drop & power to receptacle

L/O Valves Associated with SCD 71604 (MER2) 100 19-Oct-16 MRG, L/O, CPP & F/O Filter Sep outlet

After Steering Unit 100 19-Oct-16 Local Control Units (LCU's1 - 4) 100 19-Oct-16 IOUs: 11, 13, 14, 41, 51, 81 100 19-Oct-16

C-DR Boxes 1, 10, 17, 27, 28, 28A & 30 100 19-Oct-16 Install FDS ITB Modification Kit for the following ITB's; 1, 9, 10, 18, 27, 28, & 30.

USE 11A, 13A, 14A, 41A, 51A, 81A And all associated UPSs, Relay Enclosures, Junction Boxes & C/O Switches

100 19-Oct-16

NR 1 Switchboard, Load Centers and Special Frequency Switchboard (91-92) 105 24-Oct-16

Complete SWBD tie-in and CTM install in #1 SWBD and LC31 IOT support Ground Isolation TP#3B324C013/EP DIU1 Power Up

NR3 Switchboard, Load Centers and Special Frequency Switchboard (93-94) 107 26-Oct-16

Complete SWBD tie-in and CTM install in #3 SWBD and LC's 11 & 21 IOT support Ground Isolation TP#3B324C013/EP DIU3 Power Up

NR2 Switchboard, Load Centers and Special Frequency Switchboard (95-97) 109 28-Oct-16 Conduct all tie-ins and install Thermal Monitoring System.

Install ADACS control unit

Turnover 4

25Aug09 5of7

USS Hamilton DDG-60

DDGM BF Critical Path Equipment/Cable SY to AIT & Test Requirement Turnover Schedule

Ship Control Console 114 02-Nov-16 BCCS 114 02-Nov-16 Hold monitor and joy stick for later installation per SMR HFS 114 02-Nov-16 Hold monitor and joy stick for later installation per SMR IBNS Racks 1 & 2 Including High Security Firewall, UPS, C/O & Synchro Switch 114 02-Nov-16

IBNS Radar Rack 114 02-Nov-16 Trigger/Video Amp/Nulka/Break out box 114 02-Nov-16 IBNS LAN Drop (PH) & power to receptacle 114 02-Nov-16 IBNS LAN Drop (Chart Room) & power to receptacle 114 02-Nov-16

IBNS LAN Drop (CIC) & power to receptacle 114 02-Nov-16 IBSN LAN Drop(CO's Laptop) & power to receptacle 114 02-Nov-16

NAVSSI & Inputs to SAOP 114 02-Nov-16 SPS-73 SAOP, Ethernet Switch, C/O Switch & UPS 114 02-Nov-16

ELS LAN Drops & power to receptacles 114 02-Nov-16 RSC & UPS CIC, C/O Switch & Speaker 114 02-Nov-16 Hold monitors and keyboard for later installation per SMR IBNS TR & Pilot House RSC 30 114 02-Nov-16 Hold monitor and keyboard for later installation per SMR

IOUs: 21, 23, 71, 91, 93 114 02-Nov-16

GEDMS Mesh A BSE's (A1.A5, A7 & A8)and power cables affecting 5th T/O IOU's 114 02-Nov-16

Mount BSE enclosure and provide J2 Connector and cable for IOU power. Fiber not required until MESH A light off (BSE A1:

J2: 3-210-2-1L) (BSE A8: J2: 3- LC33-1L-F) (BSE A7: J2:

LC25-1L-A10) (BSE A5: J2: LC25-1l-A11)

C-DR Boxes 4, 6, 9, 18, 20, 114 02-Nov-16 Install FDS ITB Modification Kit for the following ITB's; 4, 6, 9, 19, 19A, 21, & 21A.

Fire Detection System ITB Upgrade Electrical Mods & Cabling for IOU's in T/O's 4,5,6 128 16-Nov-16

GEDMS Maintenance Group 128 16-Nov-16 ICAS EQUIPMENT 128 16-Nov-16 GEDMS Mesh A T/O 128 16-Nov-16 IOU 92 128 16-Nov-16 C- DR Boxes 2, 2A 128 16-Nov-16 Install FDS ITB Modification Kit for the following ITB; 2

DVSS - All VIROEs, Cables & Camera mounts 128 16-Nov-16 Install all DVSS cameras as directed by SMR

FCS 2 Tank Groups, TB's, C-DR Boxes, PT's, Fuel Flow Meters, Valve Control Panel and Fuel Oil Lab PC

142 30-Nov-16

Radar TLI's - All TLIs Including Redundant Radar/TDR & Associated TB's for Tank Groups DFM, OW, MRG & CPP Systems

142 30-Nov-16 SCD 77829k, Including all cabling, CDR Boxex ect, from sensor to DIU

FCS 2 Tank Groups, TB's, C-DR Boxes, PT's and Fuel Flow Meters 149 07-Dec-16

Radar TLI's - All TLIs Including Redundant Radar/TDR & Associated TB's for Tank Groups DFM, OW, MRG & CPP Systems

149 07-Dec-16 SCD 77829k, Including all cabling, CDR Boxes ect, from sensor to DIU

FCS 2 Tank Groups, TB's, C-DR Boxes, PT's and Fuel Flow Meters 156 14-Dec-16

Radar TLI's - All TLIs Including Redundant Radar/TDR & Associated TB's for Tank Groups, DFM, JP-5, PW, OW, MRG & CPP Systems

156 14-Dec-16 SCD 77829k, Including all cabling, CDR Boxes ect, from sensor to DIU

Potable Water System Including TBs, Relay Enclosure & Pump Motor Controller Modification 142 30-Nov-16 Commence testing

Turnover 7

Turnover 6

Turnover 5

4-94-0-C IC & Gyro Room #1 (FWD) A+291 28-Apr-17 3-300-0-C IC & Gyro Room #2 (AFT) A+291 28-Apr-17 3-126-2-Q Power Supply/Conversion Room A+291 28-Apr-17 3-319-0-Q Power Conversion Room A+291 28-Apr-17 4-42-0-Q Sonar Cooling Equipment Room A+291 28-Apr-17 03-142-1-Q Electronic Workshop #1 A+291 28-Apr-17 1-268-0-C CCS (VLS Alarms) A+291 28-Apr-17 1-314-0-C HWS Equipment Room A+291 28-Apr-17

4-126-0-E Auxiliary Machinery Room #1 (CND & SPY Skids) A+291 28-Apr-17

4-220-0-E Auxiliary Machinery Room #2 A+291 28-Apr-17 03-142-2-Q Electric Load Center #1 A+291 28-Apr-17 03-142-3-Q Fan Room A+291 28-Apr-17 03-142-4-Q Fan Room A+291 28-Apr-17 01-110-3-Q Fan Room PZ#1 A+291 28-Apr-17 01-126-3-Q Fan Room PZ#2 A+291 28-Apr-17 01-158-0-Q Fan Room A+291 28-Apr-17 01-240-01-Q Fan Room PZ#3 A+291 28-Apr-17 01-300-4-Q Fan Room PZ#4 A+291 28-Apr-17 1-78-1-Q Fan Room A+291 28-Apr-17 1-78-2-Q Fan Room A+291 28-Apr-17 1-358-2-Q Fan Room A+291 28-Apr-17 1-359-1-Q Fan Room A+291 28-Apr-17 1-364-2-Q Fan Room A+291 28-Apr-17

3-338-0-M VLS Magazine #2 (AFT) A+294 1-May-17 3-335-2-T VLS Access Trunk A+294 1-May-17 3-97-2-T VLS Access Trunk A+294 1-May-17 1-97-2-Q VLS Service Interface Room (FWD) A+294 1-May-17 3-78-0-M VLS Magazine #1 (FWD) A+294 1-May-17 01-130-0-Q Combat Systems Maintenance Central A+294 1-May-17 2-53-1-C CSER #1 A+294 1-May-17 2-126-2-C CSER #2 A+294 1-May-17 1-300-0-C CSER #3 A+294 1-May-17 1-126-0-C Combat Information Center A+294 1-May-17 1-18-0-Q Sonar Equipment Room #1 A+294 1-May-17 2-126-1-C Communications Center A+294 1-May-17 2-158-1-C Radio Transmitter Room A+294 1-May-17 2-200-1-Q LAN Equipment Room A+294 1-May-17 1-158-0-C TSCSI A+294 1-May-17 03-128-0-C Radar Room #1 A+294 1-May-17 03-142-0-C Radar Room #2 A+294 1-May-17 01-274-1-C Radar Room #3 A+294 1-May-17 03-128-1-Q SPY Array Room #1 (FWD/STBD) A+294 1-May-17 03-128-2-Q SPY Array Room #2 (FWD/PORT) A+294 1-May-17 03-158-3-Q SPY Array Room #3 (AFT/STBD) A+294 1-May-17 03-158-0-C SPY Array Room #4 (AFT/PORT) A+294 1-May-17 02-126-4-L Wardroom A+294 1-May-17 1-100-2-Q VLS Security Station (FWD) A+294 1-May-17 1-330-0-Q VLS Service Interface Room (AFT) A+294 1-May-17 1-330-2-Q VLS Security Station (AFT) A+294 1-May-17

FWD, STBD, PORT, AFT AN/SPY-1A Antenna Arrays A+301 8-May-17 2-50-2-C Sonar Control Room A+301 8-May-17 2-18-0-Q Sonar Equipment Room #2 A+301 8-May-17 3-18-0-Q Sonar Equipment Room #3 A+301 8-May-17 04-150-0-C Chart Room A+301 8-May-17 06-157-0-T Main Mast and Access Trunk A+301 8-May-17

TURNOVER 3

COMPARTMENT NUMBER COMPARTMENT NAME A = SOA

ACTUAL DATE (SOA =

7/11/16)

TURNOVER 1

TURNOVER 2

04-130-0-C Pilot House A+301 8-May-17 05-131-0-Q Director Equipment Room #1 A+301 8-May-17 04-272-0-Q Director Equipment Room #2 A+301 8-May-17 03-282-0-Q Director Equipment Room #3 A+301 8-May-17 1-46-0-M 5"/62 CAL Loader Drum & Fan Room A+301 8-May-17 2-442-0-Q TACTAS Hoist Room A+301 8-May-17 01 LVL FR 338-370 Missile Deck (AFT) A+301 8-May-17 01 LVL FR 78-110 Missile Deck (FWD) A+301 8-May-17 01-(46-78)-0-M 5"/54 CAL Gun Mount (MT 51) A+301 8-May-17 3-68-1-M 5"/54 CAL Propellant Mag #1 A+301 8-May-17 3-68-2-M 5"/54 CAL Propellant Mag #2 A+301 8-May-17 06-150-0 FCS Director #1 A+301 8-May-17 05-280-0 FCS Director #2 A+301 8-May-17 04-292-0 FCS Director #3 A+301 8-May-17 3-42-0-M 5"/54 CAL Projectile Magazine A+301 8-May-17

03-112-0-C CIWS Control Room #1 A+308 15-May-17 02-299-0-C CIWS Control Room #2 A+308 15-May-17 01-342-1-M Torpedo Tube (STBD) A+308 15-May-17 01-342-2-M Torpedo Tube (PORT) A+308 15-May-17 2-450-1-Q NIXIE Room A+308 15-May-17 2-153-2-C Tomahawk Equipment Room A+308 15-May-17 02-(200-220)-1 Decoy Launchers (STBD) A+308 15-May-17 02-(200-220)-2 Decoy Launchers (PORT) A+308 15-May-17 03-(142-158)-3 EW Array SLQ-32 (STBD) A+308 15-May-17 03-(142-158)-4 EW Array SLQ-32 (PORT) A+308 15-May-17 03-(112-128)-0 CIWS (MT 21) FWD A+308 15-May-17 02-(300-316)-0 CIWS (MT 22) AFT A+308 15-May-17 01-300-1-Q CIWS Workshop #2 A+308 15-May-17 02-112-0-Q CIWS Workshop #1 A+308 15-May-17 01-(318-338)-0 Harpoon Launcher A+308 15-May-17 6-0-0-Q Transducer Compartment A+308 15-May-17 6-10-0-Q Transducer Cylinder A+308 15-May-17 2-442-4-Q Bathythermograph Room A+308 15-May-17 0 1/2-28-0-Q Dome Equipment Room A+308 15-May-17 5-28-0-T Sonar Dome Access Trunk A+308 15-May-17 1-370-8-M Torpedo Magazine A+308 15-May-17

TURNOVER 4

Shipbd Test Major Milestones
EquipCable TO
ALO CRS TO