J-3_Execution_Milestones_(Amend_0003).xlsx

XLSX spreadsheet 13 KB Posted

Attached to
USS PAUL HAMILTON (DDG 60) EDSRA
Solicitation number
N00024-16-R-4400
Issued by

About this file

J-3 Attachment (Amend 0003)

View the file

Other files

File Type Posted
N55236_170001_FBO.pdf PDF
N00024_170014_FBO.pdf PDF
N00024_170015_FBO.pdf PDF
N00024_170019_FBO.pdf PDF
N00024_170024_FBO.pdf PDF
N00024_170023_FBO.pdf PDF
N00024_170017_FBO.pdf PDF
N00024_170016_FBO.pdf PDF
N000024_170012_FBO.pdf PDF
N00024_170013.pdf PDF
N55236_170025_FBO.pdf PDF
N55236_17006_FBO.pdf PDF
JA_215N_redact.pdf PDF
JA_270N_redact.pdf PDF
JA_222N_redact.pdf PDF
JA_3_REDAC6.pdf PDF
JA_4_REDACT.pdf PDF
Redacted_Hamilton_JA2.pdf PDF
JA_PAUL_HAMILTON_REDACT.pdf PDF
DDG-60_RFP_Q_AND_A_-_FINAL.docx DOCX document
J-4_Pricing_Spreadsheet__(Amend_0010).xlsx XLSX spreadsheet
Amend_0010.pdf PDF
Amend_0010_conformed.pdf PDF
J A_DDG_60_Directed_Subcontractors.pdf PDF
DDG-60_RFP_Q_AND_A_-__357_-_361.pdf PDF
Amendment_0009.pdf PDF
Amend_0009.pdf PDF
Amend_0009_conformed.pdf PDF
J-3_Execution_Milestones_(Amend_0008).xlsx XLSX spreadsheet
Amend_0008_Conformed.pdf PDF
Amend_0008.pdf PDF
DDG-60_RFP_Q_AND_A_356.docx DOCX document
N00024-16-R-4400-0007_Released.docx DOCX document
N00024-16-R-4400_CONFORMED_0007.docx DOCX document
DDG-60_RFP_Q_AND_A_-___250_-_345.pdf PDF
813-11-001_-_ALO_Compartment_Release_Schedule.pdf PDF
DDG_60_AC_Conversion_POAM_plants__1_and__4.mpp MPP file
DDG-60_Mod_Critical_Path_Turnover_Schedule.pdf PDF
SI_Index_0204.pdf PDF
Amend_0006.pdf PDF
Amend_0006_Conformed.pdf PDF
Amendment_0005.pdf PDF
J-7_Quality_Assurance_Surveillance_Plan_Amend_0005.pdf PDF
Amendment_0005_Conformed.pdf PDF
DDG-60_RFP_Q_AND_A_-___98_-_249_FBO.pdf PDF
Amend_0004_conformed.pdf PDF
Amend_0004.pdf PDF
J-4_Pricing_Spreadsheet__(Amend_0003).xlsx XLSX spreadsheet
J-7_Quality_Assurance_Surveillance_Plan_(Amend_0003).pdf PDF
Amend_0003.pdf PDF
Show 40 more

Latest 50 of 74 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILESTONES

DDG 60 FY16 EDSRA Milestones

Milestone Date A+ Dates

START AVAILABILITYMonday, July 11, 20160
CREW MOVE ASHORETuesday, July 12, 20161
DOCKMonday, August 08, 201628
HM&E TURNOVER #1Wednesday, September 7, 201658
HM&E TURNOVER #2Wednesday, September 21, 201672
OPEN & INSPECT COMPLETEThursday, September 29, 201680
HM&E TURNOVER #3Wednesday, October 05, 201686
25% CONFERENCETuesday, October 18, 201699
HM&E TURNOVER #4Wednesday, October 19, 2016100
HM&E TURNOVER #5Wednesday, November 02, 2016114
HM&E TURNOVER #6Wednesday, November 16, 2016128
HM&E TURNOVER #7Wednesday, November 16, 2016142
UNDOCKThursday, December 29, 2016171
50% CONFERENCEWednesday, January 25, 2017198
HABITABILITYFriday, April 07, 2017270
PCDMonday, April 24, 2017287
ALO COMPARTMENT RELEASE #1Friday, April 28, 2017291
ALO COMPARTMENT RELEASE #2Monday, May 01, 2017294
75% CONFERENCEThursday, May 04, 2017297
ALO COMPARTMENT RELEASE #3Monday, May 08, 2017302
ALO COMPARTMENT RELEASE #4Monday, May 15, 2017308
AEGIS LIGHT OFFMonday, May 15, 2017308
CREW MOVE ABOARDTBDTBD
LOAMonday, June 26, 2017350
DOCK TRIALSThursday, July 27, 2017381
FAST CRUISEFriday, July 28, 2017382
SEA TRIALS STARTMonday, July 31, 2017385
SEA TRIALS ENDFriday, August 04, 2017389
SEA TRAILS CORRECTION PERIODFriday, August 04, 2017389
END OF AVAILFriday, August 11, 2017396