This document is a Government Responses to Industry Questions spreadsheet for Solicitation N0001925R0003, dated 20 May 2025, addressing three specific industry inquiries related to the C-40A Contractor Logistics Support (CLS) contract. The responses focus on technical and pricing details, specifically:

  1. Clarification of CLIN 0031 unit price calculations, recommending changes to spreadsheet formulas and ensuring alignment between Attachments L-2 and L-6. 2. Similar calculation guidance for CLIN 0032 unit pricing. 3. Confirmation that CLIN 0015 is to be priced for the entire detachment support team, with contractors required to provide at least two personnel per detachment and price accordingly on a per-day basis. Each response emphasizes that while evaluation purpose values may differ from contract ceiling values, offerors must ensure unit prices are consistent across attachments.

View the file

Other files

File Type Posted
N0001925R0003-0008 Conformed.pdf PDF
Govt Responses to Industry Questions 11.pdf PDF
Att. (1) - PWS (2025.10.28) Tracked Changes.pdf PDF
Att. (1) - PWS (2025.10.28) Clean.pdf PDF
N0001925R0003-0009 Conformed.pdf PDF
Govt Responses to Industry Questions 12.pdf PDF
N0001925R0003-0008.pdf PDF
N0001925R0003-0009.pdf PDF
N0001925R0003-0007.docx DOCX document
N0001925R0003-0007 Tracked Changes.pdf PDF
Att. (3) - Anticipated Annual Ordering Quantities (2025.06.06).pdf PDF
N0001925R0003-0007 Conformed.docx DOCX document
Att. L-2 Vol 1 CPA Tables (2025.06.06).xlsx XLSX spreadsheet
Govt Responses to Industry Questions 9.pdf PDF
Att. (1) - PWS (2025.06.06) Clean.pdf PDF
Att. (1) - PWS (2025.06.06) Tracked Changes.pdf PDF
Att. (2) - Annual Unit Pricing (2025.06.06).pdf PDF
N0001925R0003-0005_Conformed.pdf PDF
N0001925R0003_0005.docx DOCX document
Govt Responses to Industry Questions 8.pdf PDF
Att. L-2 Vol 1 CPA Tables FINAL 5 (2025.05.21).xlsx XLSX spreadsheet
Att. L-2 Vol 1 CPA Tables FINAL 4 (2025.05.20).xlsx XLSX spreadsheet
Govt Responses to Industry Questions 6.pdf PDF
N0001925R0003-0004.docx DOCX document
Att. L-2 Vol 1 CPA Tables FINAL 3 (2025.05.16).xlsx XLSX spreadsheet
N0001925R0003-0004 Conformed.docx DOCX document
N0001925R0003-0003.docx DOCX document
N0001925R0003-0003 Conformed.docx DOCX document
Att. (4) - Annual Burden Rates FINAL 2 (2025.04.28).pdf PDF
Govt Responses to Industry Questions 4.pdf PDF
Att. (1) - PWS FINAL 2 (2025.05.05) Tracked Changes.pdf PDF
Att. L-2 Vol 1 CPA Tables FINAL 2 (2025.04.28).xlsx XLSX spreadsheet
Att. (1) - PWS FINAL 2 (2025.05.05).pdf PDF
Att. (2) - Annual Unit Pricing FINAL.pdf PDF
Att. (3), App. (C) - Field Team Days On-Site FINAL.pdf PDF
Att. (5), App. (C) - 3C-Check TCs FINAL.pdf PDF
N0001925R0003-0002.docx DOCX document
Att. (5), App. (D) - 4C-Check TCs FINAL.pdf PDF
Exhibit A - CDRLs (2025.01.29) FINAL.pdf PDF
N0001925R0003-0002 Conformed.docx DOCX document
Att. (5) - C-Check Baseline Task Cards FINAL.pdf PDF
Att. (8) - WDs - Virginia Beach, VA (2015-4341 R.29) FINAL.pdf PDF
Att. (1), App. I - Performance Metrics FINAL.pdf PDF
Att. (1), App. C - DSKs FINAL.pdf PDF
Att. (1), App. B - HVAs FINAL.pdf PDF
Att. (2), App. (C) - Round-Trip Field Team Transportation FINAL.pdf PDF
Att. (1), App. J - Preferred Parts List FINAL.pdf PDF
Att. (5), App. (G) - 7C-Check TCs FINAL.pdf PDF
Att. (1), App. F - Gov't Repairables FINAL.pdf PDF
Att. (5), App. (A) - 1C-Check TCs FINAL.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Set # 7 (Formal RFP) 20 May 2025

Government Responses to Industry Questions N0001925R0003 Enclosure (1)

Industry Feedback Worksheet

1 A: Gen. Info N/A Att. L-2

Question #10: can the Government review CLIN 0031 Unit Price calculation. It is applying CPA-6 Burden Rates, when those rates shouldn’t apply to CLIN 0031. Also, it is extending the unit price by the quantity. However, that should be reflected in the Total Price column (cell H37)?

Recommend changing cell E37: =ROUND MAX('CPA-4 Field Transportation'!$B$7:$B$16)

And changing the subsequent unit price in years CY2-CY5

Calculations have been updated and posted with these responses.

The Offeror shall ensure that unit prices entered into Attachments L-2 and L-6 align. Note that resultant values for evaluation purposes (Att.

L-6) vice contract ceiling values (Att. L-2) may differ; the TEP may not match ceiling values entered into Section B of the Contract.

2 A: Gen. Info N/A Att. L-2

Question #11: similar to CLIN 0032, recommend changing cell E38:

=ROUND MAX('CPA-5 Field Daily Travel'!$B$7:$B$16)

Calculations have been updated and posted with these responses.

The Offeror shall ensure that unit prices entered into Attachments L-2 and L-6 align. Note that resultant values for evaluation purposes (Att.

L-6) vice contract ceiling values (Att. L-2) may differ; the TEP may not match ceiling values entered into Section B of the Contract.

3 11.0

Paragraph 11.2 (CLIN 0015) - Is this CLIN priced on a per person basis or for the entire team? This CLIN is priced for the team required for Detachment Support. Per PWS Section 11.0, the Contractor shall provide at least two personnel for each detachment. The Contractor shall determine the number of personnel required and price CLIN 0015 to include all personnel on a per day basis.

The Offeror shall ensure that unit prices entered into Attachments L-2 and L-6 align. Note that resultant values for evaluation purposes (Att.

L-6) vice contract ceiling values (Att. L-2) may differ; the TEP may not match ceiling values entered into Section B of the Contract.

No.

Solicitation

Section

PWS

Section

Att.

App.

CDRL

Question/Comment Government Response