L-9.1_Vol_3_CSDR_Sub_Rpt_Example.xlsx
XLSX spreadsheet 43 KB Posted
- Solicitation number
- N00019-12-R-0001
About this file
Amendment 0005 Attachment L-9.1 (example for inclusion as part of Section L Attachment L-9)
View the file
Other files
Show 40 more
Latest 50 of 192 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Subsidary Report Example
| Subsidiary Reports including summary elements (G&A, FCCM, Profit etc) will be provided for each of the following elements: | |
| 3.0 | Maintenance |
| 3.1 | Overhaul of end items |
| 3.1.1 | Scheduled Overhaul |
| 3.1.1.1 | Vehicle/Platform Overhaul |
| 3.1.1.1.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost | |
| 3.1.1.2 | Propulsion Overhaul |
| 3.1.1.2.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost | |
| 3.1.1.3 | Other Overhaul |
| 3.1.1.3.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost | |
| 3.1.2 | Unscheduled Overhaul |
| 3.1.2.1 | Vehicle/Platform Overhaul |
| 3.1.2.1.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost | |
| 3.1.2.2 | Propulsion Overhaul |
| 3.1.2.2.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost | |
| 6.1 | Operational/Site Activation |
| 6.1.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost | |
| 6.2 | Industrial Facilities |
| 6.2.2 | Material |
| Reporting Contractor G&A | |
| Reporting Contractor Undistributed Budget | |
| Reporting Contractor Management Reserve | |
| Reporting Contractor FCCM | |
| Total Cost |