DRAFT Task Order QASP
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
UNCLASSIFIED
Task Order 1 Quality Assurance Surveillance Plan (QASP)
For
Marine Corps Tactics and Operations Group (MCTOG) Support Services
Version 0.1
02 Nov 2016
Prepared by
Program Manager, Training Systems
DISTRIBUTION STATEMENT A. Approved for public release. Distribution is unlimited.
UNCLASSIFIED
UNCLASSIFIED
Table of Contents
1 Vision
2 Mission
3 Purpose
4 Scope
5 Authority
6 Roles and Responsibilities
6.1 Program/Project Manager (PM)
6.2 Contracting Officer (KO)
6.3 Contracting Officer’s Representative (COR)
6.4 Alternate Contracting Officer’s Representative (ACOR)
6.5 Other Key Government Personnel
6.6 Contractor Representatives
7 Performance Requirements and Method of Surveillance
7.1 MCTOG Support Services Requirements Worksheet
7.2 Contract Surveillance
7.3 Performance Reporting
7.3.1 Contractor Performance Assessment Reporting System (CPARS)
7.3.2 Customer Complaint Record (CCR)
Appendix A‐ Customer Complaint Record (CCR)
UNCLASSIFIED
UNCLASSIFIED
| Quality | Assurance | Surveillance | Plan | (QASP) | ||
| Marine | Corps | Tactics | and | Operations | Group | (MCTOG) |
1 Vision
| The | Marine | Corps | Tactics | and | Operations | Group | (MCTOG) | Support | Services | Contractor |
| shall | provide | effective | functional, | technical, | instructional, | and | limited | maintenance | support | |
| for | operational | training, | doctrine | development | and | military | education | and | training. |
2 Mission
| MCTOG's | mission | is | to | provide | standardized | advanced | training | and | certification | to | Ground | ||
| Combat | Element | (GCE) | Operations | Officers, | Operations | Chiefs, | and | select | other | GCE | |||
| training | specialists. | The | training | encompasses | GCE | operations, | combined | arms | planning | ||||
| and | integration, | and | unit | readiness | planning | at | the | company, | battalion, | and | regiment | levels | |
| to | support | GCE | Training | and | Readiness | (T&R) | events. | MCTOG | provides | advanced | |||
| collective | training | to | company | through | regiment | staffs | by | executing | the | Battle | Staff | ||
| Training | Program | (BSTP). | MCTOG | serves | as | the | proponent | lead | to | develop | specified | GCE | |
| publications, | ensures | GCE | doctrine | is | nested | and | consistent | both | horizontally | and | vertically | ||
| within | the | Marine | Air | Ground | Task | Force | (MAGTF), | and | ensures | GCE | doctrine | and | |
| individual | and | collective | T&R | events | are | mutually | supporting | to | enhance | the | combat | ||
| readiness | of | GCE | units. | MCTOG | is | the | institutional | caretaker | of | the | OTTP. |
3 Purpose
| This | QASP | is | a | Government‐developed | document | that | is | used | to | determine | if | the |
| Contractor's | performance | meets | the | performance | standards | that | are | contained | in | the | ||
| MCTOG | Support | Services | Performance | Work | Statement | (PWS). | The | QASP | establishes | |||
| procedures | on | how | this | assessment/inspection | process | will | be | conducted. | It | provides | the | |
| detailed | process | for | continuous | contract | monitoring | and | surveillance: |
| What | will | be | monitored? | ||||
| How | will | monitoring | take | place? | |||
| Who | will | conduct | the | monitoring? | |||
| How | will | monitoring | efforts | and | results | be | documented? |
4 Scope
| The | Contractor | is | responsible | for | implementing | and | delivering | performance | that | meets | ||
| contract | requirements. | The | QASP | provides | the | structure | for | Government | monitoring | and | ||
| surveillance | of | the | Contractor's | performance | to | ensure | that | it | meets | contract | requirements. | |
| It | is | the | Government's | responsibility | to | be | objective, | fair, | and | consistent | in | evaluating |
| Contractor | performance. |
| This | QASP | is | a | living | document. | Flexibility | in | the | QASP | is | required | to | allow | for | an | increase | |
| or | decrease | in | the | level | of | surveillance | that | is | necessary | based | on | Contractor | performance. | ||||
| In | addition, | the | QASP | should | recognize | that | unforeseen | or | uncontrollable | circumstances |
UNCLASSIFIED
UNCLASSIFIED
| might | occur | that | are | outside | the | control | of | the | Contractor. | The | QASP | is | intended | to | |
| promote | the | early | identification | and | resolution | of | performance | issues | to | minimize | negative | ||||
| impact | to | the | MCTOG | mission. |
5 Authority
| Authority | for | issuance | of | this | QASP | is | provided | under | Part | 46 | of | the | Federal | Acquisition | |
| Regulation | (FAR), | Inspection | of | Services | clauses, | which | provides | for | inspection, | acceptance, | |||||
| and | documentation | of | the | services | required | to | be | delivered | or | performed | in | the | contract | or | |
| order. | This | acceptance | is | to | be | executed | by | the | Contracting | Officer | (KO), | or | other | duly | |
| authorized | representative, | such | as | the | Contracting | Officer’s | Representative | (COR). |
| 6 Roles | and | Responsibilities | ||||||
| The | following | personnel | shall | oversee | and | coordinate | surveillance | activities: |
6.1 Program/Project Manager (PM)
| The | PM | provides | primary | program | oversight, | nominates | the | COR, | ensures | the | COR | is | ||
| trained | before | performing | any | COR | duties | and | supports | the | COR's | performance | assessment | |||
| activities. | While | the | PM | may | serve | as | a | direct | conduit | to | provide | Government | guidance | and |
| feedback | to | the | Contractor | on | technical | matters, | they | are | not | empowered | to | make | any | |
| contractual | commitments | or | any | contract | changes | on | the | government's | behalf. |
| Assigned | PM: | To | be | completed | after | contract | award | |
| Organization | or | Agency: | Program | Manager, | Training | Systems | (PM | TRASYS) |
| Telephone: | To | be | completed | after | contract | award | ||
| Email: | To | be | completed | after | contract | award |
6.2 Contracting Officer (KO)
| The | KO | will | ensure | performance | of | all | necessary | actions | for | effective | contracting, | ensure | |
| compliance | with | the | contract | terms, | and | will | safeguard | the | interests | of | the | Government | in |
| the | contractual | relationship. | The | KO | will | also | ensure | that | the | Contractor | receives | ||
| impartial, | fair, | and | equitable | treatment | under | this | contract. |
| Assigned | KO: | To | be | completed | after | contract | award | |
| Organization | or | Agency: | Program | Manager, | Training | Systems | (PM | TRASYS) |
| Telephone: | To | be | completed | after | contract | award | ||
| Email: | To | be | completed | after | contract | award |
6.3 Contracting Officer’s Representative (COR)
| The | COR | is | responsible | for | providing | continuous | technical | oversight | of | the | contractor's | |||
| performance. | The | QASP | is | the | primary | tool | for | documenting | contractor | performance. | The | |||
| COR | uses | the | QASP | to | conduct | the | oversight/surveillance | process. | The | purpose | is | to | ensure | |
| that | the | contractor | meets | the | performance | standards | contained | in | the | contract. | The | COR | is | |
| responsible | for | reporting | early | identification | of | performance | problems | to | the | KO. | While | the | ||
| COR | may | serve | as | a | direct | conduit | to | provide | Government | guidance | and | feedback | to | the |
UNCLASSIFIED
UNCLASSIFIED
| Contractor | on | technical | matters, | the | COR | is | not | empowered | to | make | any | contractual |
| commitments | or | any | contract | changes | on | the | Government's | behalf. |
| Assigned | COR: | To | be | completed | after | contract | award | |
| Organization | or | Agency: | Program | Manager, | Training | Systems | (PM | TRASYS) |
| Telephone: | To | be | completed | after | contract | award | ||
| Email: | To | be | completed | after | contract | award |
6.4 Alternate Contracting Officer’s Representative (ACOR)
| Given | the | fact | that | the | MCTOG | Support | Services | contract | is | geographically | dispersed | and | ||
| will | likely | include | multiple | task | orders | throughout | the | contract | ordering | period, | the | |||
| Contracting | Officer | has | determined | that | an | Alternate | Contracting | Officer’s | Representative | |||||
| (ACOR) | is | required | to | reduce | contract | performance | risk. | The | ACOR | has | authority | and | ||
| responsibility | to | act | as | COR | ONLY | in | the | absence | of | the | primary | COR | by | providing |
| assistance | to | the | COR | with | surveillance | duties. |
| Assigned | ACOR: | To | be | completed | after | contract | award | ||
| Organization | or | Agency: | Marine | Corps | Operations | and | Tactics | Group | (MCTOG) |
| Telephone: | To | be | completed | after | contract | award | |||
| Email: | To | be | completed | after | contract | award |
6.5 Other Key Government Personnel
| Other | key | government | personnel | who | may | serve | as | a | performance | monitor, | inspector, |
| technical | expert, | or | otherwise | provide | information | that | helps | the | COR/ACOR | monitor | |
| Contractor | performance | are | identified | in | Appendix | A | of | the | PWS. |
6.6 Contractor Representatives
| Upon | contract | award, | the | Contractor | shall | provide | the | title(s), | name(s), | telephone, | and |
| contact | information | for | contractor | personnel | assigned | the | responsibility | for | quality | ||
| assurance | during | the | contract | period | of | performance. |
| 7 Performance | Requirements | and | Method | of | Surveillance | |||||
| This | section | describes | the | special | requirements | and | provides | details | of | various |
| considerations | for | this | effort. |
7.1 MCTOG Support Services Requirements Worksheet
| The | MCTOG | Service | Support | Requirements | Worksheet, | included | as | Appendix | A | of | the | |||||
| MCTOG | Support | Services | Task | Order | 1 | PWS | lists | the | performance | objectives | and | standards | ||||
| that | must | be | met | by | the | Contractor. | This | matrix | details | the | method | of | surveillance | that | the | |
| COR | will | use | to | validate | and | inspect | these | performance | elements. | Performance | objectives | |||||
| define | what | results | are | required. | Performance | standards | define | what | level | of | performance | |||||
| is | required | to | meet | the | performance | objective | or | task. | The | inspection | requirements | define | ||||
| what, | how, | when, | and | by | whom | inspections | will | be | conducted | to | measure | Contractor |
performance.
UNCLASSIFIED
UNCLASSIFIED
7.2 Contract Surveillance
| The | goal | of | the | QASP | is | to | ensure | that | Contractor | performance | is | effectively | monitored | and |
| documented. | The | COR's | professional, | non‐adversarial | relationships | with | the | KO | and | the | ||||
| Contractor | will | enable | positive, | open, | and | timely | communications. | The | foundation | of | this | |||
| relationship | is | built | upon | objective, | fair, | and | consistent | COR | evaluations | of | Contractor | |||
| performance | against | contract | requirements. | The | COR | uses | the | methods | contained | in | this | |||
| QASP | to | ensure | that | Contractor | performance | meets | all | contract | requirements. | The | COR | is | ||
| responsible | for | a | wide | range | of | surveillance | requirements | that | effectively | measure | and | |||
| evaluate | the | Contractor's | performance. |
7.3 Performance Reporting
7.3.1 Contractor Performance Assessment Reporting System (CPARS)
| The | Federal | Acquisition | Regulation | (FAR) | requires | that | contractor | performance | ||||||
| information | be | collected | (FAR | Part | 42.15) | and | used | in | source | selection | evaluations | (FAR | ||
| Part | 15). | The | contractor | performance | evaluation | contained | in | the | CPARS | is | a | method | of | |
| recording | contractor | performance | and | is | not | the | primary | method | for | reporting | ||||
| performance | information | to | the | contractor. | Contractor | performance | reporting | is | expected | |||||
| to | occur | at | the | task | order | level. | Ratings | will | be | applied | as | follows: |
Performance Rating
Definition
Exceptional
Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor was effective.
Satisfactory Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Table 1. Evaluation Ratings Definitions
UNCLASSIFIED
UNCLASSIFIED
7.3.2 Customer Complaint Record (CCR)
A Customer Complaint Record is included as Appendix A to this QASP. The CCR is a tool to assess contractor performance of the requirements contained in the PWS. The customer will submit CCRs for contractor performance suspected of not satisfying the contract’s performance requirements. Upon receipt of the CCR, the COR will assess the nature of the complaint relative to all available information, including the performance requirements of the MCTOG Support Services Task Order 1 PWS. The COR will make a recommendation to the Contracting Officer concerning the disposition of the complaint (i.e. valid complaint or not valid complaint). The Contracting Officer’s disposition of the complaint is final.
UNCLASSIFIED
UNCLASSIFIED
Appendix A- Customer Complaint Record (CCR)
CUSTOMER COMPLAINT RECORD
DATE/TIME OF COMPLAINT
SOURCE OF COMPLAINT
ORGANIZATION
BUILDING NUMBER
INDIVIDUAL
PHONE NUMBER
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY