Lead Based Paint Report - AC-905579_HWY-483.pdf

PDF 11 MB Posted

Attached to
Landslide Repairs in Morovis, Puerto Rico
Solicitation number
693C73-24-B-000015
Issued by

About this file

This document is a Lead Based Paint Report related to a federal contract opportunity for Landslide Repairs in Morovis, Puerto Rico.

The federal contract opportunity is for the Landslide Repairs in Morovis, Puerto Rico project, Solicitation Number 693C73-24-B-000015, with an estimated cost range of $10,000,000 to $15,000,000. The project involves repairing landslides and washouts caused by Hurricanes Irma and Maria on PR-155 and PR-159. The work includes embankment reconstruction, shotcrete wall construction, soil nail wall construction, Reinforced Soil Slope (RSS) system construction, gabion wall construction, Mechanically Stabilized Earth (MSE) retaining wall construction, drainage system installation, milling and overlay, pavement reconstruction, pavement markings, removal and replacement of guardrails, signage, maintenance of traffic (MOT), and other miscellaneous work. The project will be split into multiple work schedules/contract options. The solicitation documents will be issued on or about July 23, 2024, and bids will be accepted from certified Small Business Concerns only. Bidders are encouraged to submit bids electronically.

View the file

Other files

File Type Posted
Results of Bid Opening - PR ER DOT PRMNT RPR(17).pdf PDF
Amendment 0004 - PR ER DOT PRMNT RPR(17).pdf PDF
Amendment 0003 - PR ER DOT PRMNT RPR(17).pdf PDF
Amendment 0002 Plans - AC-857579_HWY-258 260 261 262 263 265 - Part 4 of 4.pdf PDF
Amendment 0002 Plans - AC-857579_HWY-258 260 261 262 263 265 - Part 3 of 4.pdf PDF
Amendment 0002 - PR ER DOT PRMNT RPR(17).pdf PDF
Amendment 0002 Plans - AC-857579_HWY-258 260 261 262 263 265 - Part 1 of 4.pdf PDF
Amendment 0002 Plans - AC-857579_HWY-258 260 261 262 263 265 - Part 2 of 4.pdf PDF
Amendment 0001 Plans - AC-905579_HWY-483 - Full-Size Part 1 of 2.pdf PDF
Amendment 0001 Plans - AC-857579_HWY-258 260 261 262 263 265 - Full-Size Part 2 of 3.pdf PDF
Amendment 0001 Plans - AC-916579_HWY-286 287 - Full-Size.pdf PDF
Amendment 0001 Plans - AC-908579_HWY-257 - Full-Size.pdf PDF
Amendment 0001 Plans - AC-857579_HWY-258 260 261 262 263 265 - Full-Size Part 3 of 3.pdf PDF
Amendment 0001 Plans - AC-919579_HWY-259 - Full-Size.pdf PDF
Amendment 0001 - PR ER DOT PRMNT RPR(17).pdf PDF
Amendment 0001 Plans - AC-857579_HWY-258 260 261 262 263 265 - Full-Size Part 1 of 3.pdf PDF
Amendment 0001 Plans - AC-893579_HWY-264 - Full-Size.pdf PDF
Amendment 0001 Plans - AC-905579_HWY-483 - Full-Size Part 2 of 2.pdf PDF
Geotechnical Report - AC-857579_HWY-258 260 261 262 263 265.pdf PDF
Utility Status Report - AC-905579_HWY-483.pdf PDF
Lead Based Paint Report - AC-916579_HWY-286.pdf PDF
Geotechnical Report Addendum - AC-905579_HWY-483.pdf PDF
Utility Status Report - AC-857579_HWY-260 261 265.pdf PDF
Utility Status Report - AC-916579_HWY-287.pdf PDF
Plans - PR ER DOT PRMNT RPR(17) - 893579_HWY-264_plot.pdf PDF
Technical Report - AC-908579_HWY-257.pdf PDF
VETS-4212 Form.pdf PDF
Categorical Exclusion Form (NEPA) - AC-857579_HWY-258 260 261 262 263 265 (Part 1 of 2).pdf PDF
Technical Report - AC-893579_HWY-264.pdf PDF
Geotechnical Report Addendum - Letter AC-857579_HWY-260.pdf PDF
Geotechnical Report Addendum - Letter AC-857579_HWY-262.pdf PDF
Plans - PR ER DOT PRMNT RPR(17) - AC-905579_HWY-483_plot.pdf PDF
Categorical Exclusion Form (NEPA) - AC-916579_HWY-286 287.pdf PDF
Geotechnical Report Addendum - Letter AC-857579_HWY-261.pdf PDF
Categorical Exclusion Form (NEPA) - APPENDIX B_PLANS_SITE-264.pdf PDF
Lead Based Paint Report - AC-916579_HWY-287.pdf PDF
Utility Status Report - AC-908579_HWY-257.pdf PDF
Asbestos and Lead Report - AC-857579_AC-919579 (Part 3 of 3).pdf PDF
Geotechnical Report - AC-919579_HWY-259.pdf PDF
Asbestos Report - AC-908579_HWY-257.pdf PDF
PRHTAs Material Testing Schedule.PDF PDF
Utility Status Report - AC-857579_HWY-260.pdf PDF
Categorical Exclusion Form (NEPA) - AC-919579_HWY-259 (Part 2 of 2).pdf PDF
Plans - PR ER DOT PRMNT RPR(17) - 916579_HWY-286 287_plot.pdf PDF
Technical Report - AC-919579_HWY-259.pdf PDF
Carlos E. Ocasio_LBP_Exp-08.26.24.pdf PDF
Utility Status Report - AC-919579_HWY-259_PRASA.pdf PDF
Geotechnical Report Addendum - Letter 1_AC-893579_HWY-264.pdf PDF
PRHTAs Standard Drawings.pdf PDF
Technical Report - AC-916579_HWY-287.pdf PDF
Show 40 more

Latest 50 of 101 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lead Based Paint Inspection Report

EMERGENCY RELIEF PROGRAM

LANDSLIDES & ROAD DAMAGES-EVALUATION REPAIRS

Group A PR-162-Aibonito (Kms 4.5, 4.70, 6.20)

PR-155-Morovis (km 35.0) PR-514-Villalba (Km 2.60) PR-514-Villalba (Km 3.20)

Project AC-818544 and AC-812544 ER-HWY-293-2 (PR-162 km 4.5) ER-HWY-293-3 (PR-162 km 4.7) ER-HWY-293-5 (PR-162 km 6.2) ER-HWY-483 (PR-155 km 35)

ER-HWY-372-1 (PR-514 km 2.6) ER-HWY-372-2 (PR-514 km 3.20)

Prepared for:

Puerto Rico Highway and Transportation Authority

Centro Gubernamental Roberto Sánchez Villella PO Box 42007, San Juan, P.R. 00940-2007

Inspectors: Angel A. Burgos

Asb. PREQB I.D. # ASB-0319-0191-SI | LBP PREQB I.D. # 3253-1218-LI-003

NORTOL’S PREQB Lead Firm #: 5550-0219-LF-007 NORTOL’S USEPA Lead Firm #: NAF-F121771-2 XRF-direct reading Instrument: Pb200i Alpha (serial # 1142)

Survey Dates: October 25, 30 and November 1st, 2019 & October 17, 2020

Lead-Based Paint Survey Emergency Relief Program Landslide and Road Damages-Evaluation Repairs

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Table of Contents

Executive Summary ……………………………………… 3 Introduction ………………………………………………… 4 Regulatory Review ………………………………………… 5 Survey Design & Methodology ………………………… 6 Lead Based Paint Results ………………………………… 6 Conclusion and Limitations ……………………………… 7

Attachment 1 – Location Maps Attachment 2 – Representative Pictures

Attachment 3 – LBP XRF Readings Attachment 4 – PGC-010 LBP Certification (no presence, as applicable)

Attachment 5 – Inspector, Company and XRF-instrument Certificates

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

EXECUTIVE SUMMARY

The Puerto Rico Highway & Transportation Authority (PRHTA), as part of their project AC- 818544 / AC-812544 “Emergency relief program: landslides & road damages-evaluation repairs”, requested a Lead Based Paint (LBP) survey. The project is located at following PR road’s segments as indicated in Attachment 1.0 (Location Maps):

The assessment was conducted by Nortol Environmental & Occupational Safety, Inc., under agreement with Integra Design Group (IDG) as PRHTA representative. The field work was executed within October 25 and November 1st, 2019 & October 17, 2020 in coordination with Ms. Luz M. Rodríguez from IDG.

The XRF-readings shown that metal safety guardrails from segments at PR-162 (km 6.20) Aibonito and PR-155 (km 35) Morovis are positive to Lead-based Paint. The established threshold for the classification of painted components as lead bearing per federal and local regulations is 1.0 mg/cm². Other guardrails and components are negative to LBP or are unpainted. Representative pictures are included as Attachment 2.0

Table 1.0 ER-HWY-# Road ID Kilometer City ER-HWY-293-2 PR-162 Kms 4.5 Aibonito ER-HWY-293-3 PR-162 Kms 4.70 Aibonito ER-HWY-293-5 PR-162 Kms 6.20 Aibonito ER-HWY-483 PR-155 Km 35.0 Morovis

ER-HWY-372-1 PR-514 Km 2.60 Villalba ER-HWY-372-2 PR-514 Km 3.20 Villalba

Segments with guardrails positive to lead-based paint.

See Attachment 1.0-Location Maps.

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

I. INTRODUCTION

A. Lead-based Paint background

Lead is one of the most common over exposure found in industry. It is also a major potential public health risk. Lead poisoning is a leading environmentally induced illness in children. At greatest risk are children under the age of six because they are undergoing rapid neurological and physical development. In general population, lead may be present at hazardous concentrations in food, water, and air. Sources include lead-based paint, urban soil, and dust, and drinking water.

Lead is commonly added to industrial paints because of its characteristic to resist corrosion.

Industries with particularly high potential exposures include construction work involving welding, cutting, brazing, blasting, etc., on lead paint surfaces; most smelter operations either as a trace contaminant or as a major product; secondary lead smelters where lead is recovered from batteries; radiator repair shops; and firing ranges. Oral ingestion may represent a major route of exposure in contaminated workplaces. Once in the blood, lead is distributed primarily among three routes - blood, soft tissue (kidney, bone marrow, liver, and brain) and mineralizing tissue (bones and teeth).

B. Survey Purpose and Scope

The purpose of this survey was to locate and identify if Lead-based Painted components are present in the PRHTA project AC-818544 / AC-812544 “Landslide and Road Evaluation and Repairs Recommendations”. The scope of work for this project consisted of the following tasks:

Review the information for proposal as provided by the client;

Coordinate field work with the client’s representative;

Achieve inventory of painted surfaces (guardrails, pavement parking and concrete barriers as apply);

Select locations to be tested;

Perform XRF testing;

Review and evaluate the data;

Report findings.

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

II. REGULATORY REVIEW

Hazard of lead in paint has been defined by the Department of Housing and Urban Development as 1.0 mg/cm2 as measured by an XRF instrument, or Atomic Absorption Spectroscopy (AAS);

or 0.5% by weight (or 5,000 ppm) as measured by AAS, or Inductive Coupled Plasma (ICP).

The same level was adopted by EPA regulations published in 1992, under Title X and by local regulation.

Although Occupational Safety and Health Administration (OSHA) regulations for occupational lead exposure have been in effect since 1971 for the construction and general industries, the agency recognized the need to provide better protection and revised the regulations for general industry in 1978. The 1978 lead standard, however, excluded the construction industry from coverage because of insufficient information regarding lead use in construction.

In 1990, the National Institute for Occupational Safety and Health (NIOSH) set a national goal to eliminate worker exposures resulting in blood lead concentrations greater than 25 micrograms per deciliter (25 µg/dl) of whole blood. Consequently, OSHA began developing a proposal for a comprehensive standard regulating occupational exposure to lead in construction. In October 1992, the Congress passed Section 1031 of Title X of the Housing and Community Development Act of 1992 (P. L. 102-550) requiring OSHA to issue an interim final lead standard for the construction industry, effective until OSHA issues a final standard.

The interim final rule, published on May 4, 1993, amends the OSHA standards for occupational health and environmental controls in Subpart D of Title 29 Code of Federal Regulations (CFR) 1926 by adding a new section 1926.62, containing employee protection requirements for construction workers exposed to lead.

On July 1998, the PR Departamento de Recursos Naturales y Ambientales-former PR Environmental Quality Board regulations regarding to Lead Based Paint was created to issue activity permits, accredit institutions, and certificate persons involved in Lead Based Paint activities in Puerto Rico. Local regulations require all lead to be managed as a special waste.

On August 2019 this regulation was replaced by the new Reglamento para el Manejo Adecuado de Actividades de Pintura con Base de Plomo. To obtain a demolition permit in Puerto Rico is necessary to includes a certification (OGP-PGC-010 or equivalent) stating that there is no lead-based paint in the project.

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

III. SURVEY DESIGN & METHODOLOGY

Inspection scope and schedule was coordinated with Luz M. Rodríguez from Integra Design Group as PRHTA representative to be conducted within specific days/hours.

The applicable guardrails, pavement marks and concrete barriers in the project scope areas were inspected for LBP. The survey was performed following applicable current regulations leading accredited inspections in Puerto Rico. The technique used for the assessment of the painted components was the XRF instrument model VIKEN (former HEURESIS) with serial number 2279. Portable XRF instruments expose a component to X-ray or gamma radiation, which causes lead to emit X rays with a characteristic frequency or energy. The intensity of this radiation is measured by the instrument. The XRF instrument was set at Standard Paint Mode showing reading “Positive” or “Negative” with a 95% confident reading. The result is reported in mg/cm2.

IV. Lead Based Paint Survey Results

By definitions set forth in 24 CFR Part § 35.86: “Lead-Based Paint (LBP) means paint or other surface coatings that contain lead equal to or in excess of 1.0 milligram per square centimeter or 0.5 percent by weight.”

At the PRHTA project AC-818544 / AC-812544 “Landslide and Road Evaluation and Repairs Recommendations”, Group A (PR-162-Aibonito Kms 4.5, 4.70, 6.20; PR-155-Morovis km 35.0;

PR-514-Villalba Km 2.60, the metal safety guardrails from the segments described in Table 2.0 were found to contain lead-based paints at or above current PR regulatory limit of 1.0 mg/cm2.

The XRF-instrument’s readings were between 1.2 and 9.4 mg/cm2. Some of metal barriers have only the remnants of yellow paint. The XRF readings are tabulated in the Attachment 3.0.

Other guardrails or components are negative to LBP or are unpainted. See Attachment 4.0 for the PGC-010 (no LBP presence applicable certifications).

Table 2.0 Segments Positive to Lead-based Paints

ER-HWY-# Road ID Kilometer Location Component Approximated amount

ER-HWY-293-5 PR-162 Kms 6.20 Aibonito Metal Guardrail Small concrete columns

30 ln ft 20 units

ER-HWY-483 PR-155 Km 35.0 Morovis Metal guardrail 180 ln ft

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

V. Conclusion and Limitations

The following options are promulgating by the PR Departamento de Recursos Naturales y Ambientales - former PR Environmental Quality Board regulations and/or the US Environmental Protection Agency (EPA):

- A Lead-Based Paint mitigation project shall be conducted prior to any demolition when lead is present in painted components. The LBP abatement project shall be in accordance with new PR DRNA (former Environmental Quality Board) applicable regulations. This requirement is particularly applicable to concrete components.

- Federal and local regulation provides that steel (or metal) structures with Lead-based Paint be considered as recycling material. Scrap metal is a relatively easy waste to recycle. Many operators have found that scrap metal recycling companies will collect and remove materials such as tanks, drums, and other types of scrap metal from the lease.

Additional consideration should be given to the associated regulatory requirements.

Scrap metal that is recycled is not subject to hazardous waste regulations; but it can be considered hazardous waste if disposed.

The results, findings, and conclusions expressed in this report are based only on conditions that were noted during the Nortol’s assessment of the PRHTA project AC-818544 / AC-812544 “Landslide and Road Evaluation and Repairs Recommendations”, Group A (PR-162-Aibonito Kms 4.5, 4.70, 6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60 within October 25 and November 1st, 2019. Any conditions or materials that could not be visually identified on the surface were not inspected and may differ from those conditions or materials noted. It was not within the scope of the inspection to remove surface materials to investigate portions of the structure or materials that lay beneath the surface. Nortol’s selection of reading locations and frequency of readings was based on Nortol’s observations and the assumption that like components in the same area are homogeneous in paint content.

The report is designed to aid the building owner, architect, construction manager, general contractors, and potential lead abatement contractors in locating lead-based paint. The abatement bidders are responsible for visiting the project to confirm the estimated amounts.

See Attachment 5.0 for company, personnel, and instrument’s certifications.

I certify that the subject project was done in accordance w ith current applicable regulations and that the information included in this report is true.

Angel A. Burgos, PR accredited lead-based paint inspector

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

ATTACHMENT 1

LOCATION (AERIAL PICTURES)

(refer to PR-162 km 6.2 and PR-155 km 35 with guardrails positive to LBP)

PR-162 KM. 6.2, AIBONITO P.R. METAL

GUARDRAIL & CONCRETE BASE/ COLUMNS ARE

POSITIVE TO LEAD-BASED PAINT IN THE

SHOWED AREAS

PR-155 KM. 35.0 MOROVIS, P.R.

GUARDRAILS ARE POSITIVE TO LEAD-BASED

PAINT IN THE SHOWED AREAS

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

ATTACHMENT 2

REPRESENTATIVE PICTURES

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Pictures

Lead-based paint positive PR-162 Km 6.2 Aibonito: Yellow and blue metal guardrails.

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Pictures

General Views: PR-162 Km 4.5 Aibonito

Components negative to Lead-based Paint

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Pictures

General V iew s: PR-162 Km 4.7 Aibonito

Components negative to Lead-based Paint Page 3 of 3

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Lead-based paint positive PR-155 Km 35 Morovis: Yellow metal guardrails.

Pictures

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Pictures

General Views: PR-514 Km 2.6 Villalba

Components negative to Lead-based Paint

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

Pictures

General Views: PR-514 Km 3.2 Villalba

Guardrails are unpainted.

XRF readings were not necessary.

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

ATTACHMENT 3

XRF READINGS

Lead Based Paint - XRF Readings Project: ER-HWY-293-3 (Km 6.2) Date: 25-Oct-19 Location: PR 162 Aibonito Inspector: AB Client: Integra Desing Group PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments

- CALIBRATION - - - - - - 0.00

- CALIBRATION - - - - - - 0.30

- CALIBRATION - - - - - - 1.00

1 EXTERIOR 1 - Km 6.2 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

2 EXTERIOR 1 - Km 6.2 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

3 EXTERIOR 1 - Km 6.2 BARRIERS CONCRETE UNPAINTED <1.0 NEGATIVE

4 EXTERIOR 1 - Km 6.2 BARRIERS CONCRETE UNPAINTED <1.0 NEGATIVE

5 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL YELLOW 1.7 POSITIVE 6 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL YELLOW 1.6 POSITIVE 7 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL YELLOW 1.5 POSITIVE 8 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL YELLOW 1.4 POSITIVE 9 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL BLUE 3.0 POSITIVE

10 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL BLUE 2.7 POSITIVE 11 EXTERIOR 1 - Km 6.2 GUARDRAILS METAL BLUE 2.4 POSITIVE 12 EXTERIOR 1 - Km 6.2 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

13 EXTERIOR 1 - Km 6.2 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

14 EXTERIOR 1 - Km 6.2 FLOOR MARK ASPHALT YELLOW <1.0 NEGATIVE

15 EXTERIOR 1 - Km 6.2 FLOOR MARK ASPHALT YELLOW <1.0 NEGATIVE

16 EXTERIOR 1 - Km 6.2 FLOOR MARK ASPHALT YELLOW <1.0 NEGATIVE

17 EXTERIOR 1 - Km 6.2 FLOOR MARK ASPHALT YELLOW <1.0 NEGATIVE

18 EXTERIOR 1 - Km 6.2 WALL CONCRETE UNPAINTED <1.0 NEGATIVE

19 EXTERIOR 1 - Km 6.2 WALL CONCRETE UNPAINTED <1.0 NEGATIVE

NORTOL Environmental and Occupational Safety, Inc. Regulatory Level: 1.0 mg/cm2 Page 1 of 2

Project: ER-HWY-293-3 (Km 6.2) Date: 25-Oct-19 Location: PR 162 Aibonito Inspector: AB Client: Integra Desing Group PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments 20 EXTERIOR 1 - Km 6.2 WALL CONCRETE YELLOW <1.0 NEGATIVE

21 EXTERIOR 1 - Km 6.2 WALL CONCRETE YELLOW <1.0 NEGATIVE

22 EXTERIOR 1 - Km 6.2 WALL CONCRETE YELLOW <1.0 NEGATIVE

23 EXTERIOR 1 - Km 6.2 WALL CONCRETE YELLOW <1.0 NEGATIVE

24 EXTERIOR 1 - Km 6.2 WALL CONCRETE YELLOW <1.0 NEGATIVE

25 EXTERIOR 1 - Km 6.2 WALL CONCRETE BLUE <1.0 NEGATIVE

26 EXTERIOR 1 - Km 6.2 WALL CONCRETE BLUE <1.0 NEGATIVE

27 EXTERIOR 1 - Km 6.2 WALL CONCRETE BLUE <1.0 NEGATIVE

28 EXTERIOR 1 - Km 6.2 BARRIERS COLUMN CONCRETE YELLOW 9.4 20 UNITS 29 EXTERIOR 1 - Km 6.2 BARRIERS COLUMN CONCRETE YELLOW 6.1 POSITIVE 30 EXTERIOR 1 - Km 6.2 BARRIERS COLUMN CONCRETE YELLOW 1.1 POSITIVE 31 EXTERIOR 1 - Km 6.2 BARRIERS COLUMN CONCRETE YELLOW <1.0

32 EXTERIOR 1 - Km 6.2 BARRIERS COLUMN CONCRETE YELLOW 2.1 POSITIVE

- CALIBRATION - - - - - - 1.20

- CALIBRATION - - - - - - 1.00

- CALIBRATION - - - - - - 0.80

NORTOL Environmental and Occupational Safety, Inc. Regulatory Level: 1.0 mg/cm2 Page 2 of 2

Project: ER-HWY-293-2 (Km 4.5) Date: 25-Oct-19 Location: PR 162 Aibonito Inspector: AB Client: Integra Desing Group PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments

- CALIBRATION - - - - - - 0.00

- CALIBRATION - - - - - - 0.30

- CALIBRATION - - - - - - 1.00

1 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

2 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

3 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

4 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

5 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

6 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

7 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

8 EXTERIOR 1 - Km 4.5 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

9 EXTERIOR 1 - Km 4.5 GUARDRAILS METAL YELLOW <1.0 NEGATIVE

10 EXTERIOR 1 - Km 4.5 GUARDRAILS METAL BLUE <1.0 NEGATIVE

11 EXTERIOR 1 - Km 4.5 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

12 EXTERIOR 1 Km 4.5 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

- CALIBRATION - - - - - - 1.20

- CALIBRATION - - - - - - 1.00

NORTOL Environmental and Occupational Safety, Inc. Regulatory Level: 1.0 mg/cm2 Page 1 of 1

Project: ER-HWY-293-3 (Km 4.7) Date: 25-Oct-19 Location: PR 162 Aibonito Inspector: NT/AB Client: Integra Desing Group PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments

- CALIBRATION - - - - - - 0.00

- CALIBRATION - - - - - - 0.30

- CALIBRATION - - - - - - 1.00

1 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

2 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

3 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

4 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

5 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

6 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

7 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE WHITE <1.0 NEGATIVE

8 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

9 EXTERIOR 1 - Km 4.7 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

10 EXTERIOR 1 - Km 4.7 GUARDRAILS METAL YELLOW <1.0 NEGATIVE

11 EXTERIOR 1 - Km 4.7 GUARDRAILS METAL YELLOW <1.0 NEGATIVE

12 EXTERIOR 1 - Km 4.7 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

13 EXTERIOR 1 - Km 4.7 FLOOR MARK ASPHALT WHITE <1.1 NEGATIVE

- CALIBRATION - - - - - - 1.20

- CALIBRATION - - - - - - 1.00

Project: ER-HWY-483 (Km 35.0) Date: 1-Nov-19 Location: PR-155 Morovis Inspector: AB Client: Integra Design Group, PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments

- CALIBRATION - - - - - - 1.10

- CALIBRATION - - - - - - 1.00

- CALIBRATION - - - - - - 0.7

1 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 2.1 POSITIVE

2 EXTERIOR 1 - Km 35.0 COLUMNS CONCRETE UNPAINTED <1.0 NEGATIVE

3 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 3.1 POSITIVE

4 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 2.8 POSITIVE

5 EXTERIOR 1 - Km 35.0 COLUMNS CONCRETE UNPAINTED <1.0 NEGATIVE 6 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 2.0 POSITIVE 7 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 2.2 POSITIVE 8 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 3.0 POSITIVE

9 EXTERIOR 1 - Km 35.0 COLUMNS METAL UNPAINTED <1.0 NEGATIVE

10 EXTERIOR 1 - Km 35.0 BARRIERS CONCRETE YELLOW <1.0 NEGATIVE

11 EXTERIOR 1 - Km 35.0 BARRIERS CONCRETE UNPAINTED <1.0 NEGATIVE

12 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 2.50 POSITIVE

13 EXTERIOR 1 - Km 35.0 GUARDRAILS METAL YELLOW 3.20 POSITIVE

14 EXTERIOR 1 - Km 35.0 COLUMNS CONCRETE UNPAINTED <1.0 NEGATIVE

15 EXTERIOR 1 - Km 35.0 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

16 EXTERIOR 1 - Km 35.0 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

- CALIBRATION - - - - - - 1.00

- CALIBRATION - - - - - - 0.80

- CALIBRATION - - - - - - 1.00

Project: ER-HWY-372-1 (Km 2.6) Date: 25-Oct-19 Location: PR 514 Villalba Inspector: AB Client: Integra Desing Group PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments

- CALIBRATION - - - - - - 0.80

- CALIBRATION - - - - - - 0.80

- CALIBRATION - - - - - - 1.00

1 EXTERIOR 1 - Km 2.6 WALL CONCRETE UNPAINTED <1.0 NEGATIVE

2 EXTERIOR 1 - Km 2.6 GUARDRAILS METAL UNPAINTED <1.0 NEGATIVE

3 EXTERIOR 1 - Km 2.6 GUARDRAILS METAL UNPAINTED <1.0 NEGATIVE

4 EXTERIOR 1 - Km 2.6 GUARDRAILS METAL YELLOW <1.0 NEGATIVE

5 EXTERIOR 1 - Km 2.6 GUARDRAILS METAL YELLOW <1.0 NEGATIVE

5 EXTERIOR 1 - Km 2.6 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

6 EXTERIOR 1 - Km 2.6 FLOOR MARK ASPHALT WHITE <1.0 NEGATIVE

- CALIBRATION - - - - - - 1.00

- CALIBRATION - - - - - - 1.10

- CALIBRATION - - - - - - 0.30

Project: ER-HWY-372-2 (Km 3.2) Date: 17-Oct-19 Location: PR 514 Villalba Inspector: AB Client: Integra Design Group PSC XRF instrument: Pb200i Alpha (serials #1142 & #2279)

I.D. # Location Floor Side Room Structure Substrate Color XRF (mg/cm2 ) Comments 1 EXTERIOR 1 - Km 3.2 GUARDRAILS METAL UNPAINTED N/A NEGATIVE

2 EXTERIOR 1 - Km 3.2 GUARDRAILS METAL UNPAINTED N/A NEGATIVE

3 EXTERIOR 1 - Km 3.2 GUARDRAIL BASES METAL UNPAINTED N/A NEGATIVE

4 EXTERIOR 1 - Km 3.2 GUARDRAIL BASES METAL UNPAINTED N/A NEGATIVE

5 EXTERIOR 1 - Km 3.2 GUARDRAILS METAL UNPAINTED N/A NEGATIVE

N/A = NOT APPLICABLE. NO TRACE OF PAINTS WAS OBSERVED

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A) Project AC-818544/AC-812544

ATTACHMENT 4

PGC-010 CERTIFICATIONS

No presence of LBP, as applicable for:

PR-162-Aibonito 4.5 PR-162-Aibonito 4.7 PR-514-Villalba 2.60 PR-514-Villalba 3.20

Dirección Física: Ave. Ponce de León 1308, Carr. Estatal 8838, Sector el Cinco, Río Piedras, PR 00926 Dirección Postal: Apartado 11488, Santurce, PR 00910-1488 Tel. (787) 767-8181 • Fax (787) 767-1962

Forma PGC-010

GOBIERNO DE PUERTO RICO

OFICINA DEL GOBERNADOR

JUNTA DE CALIDAD AMBIENTAL

Área de Calidad de Agua

CERTIFICACION DE NO PRESENCIA DE PINTURA CON BASE DE PLOMO

EN ESTRUCTURAS A DEMOLERSE

(Deberá completarse en letra de molde o impresa)

PGC-_____________________

PARA USO OFICIAL

Yo, Angel A. Burgos Torres, mayor de edad, casado, y vecino de Gurabo, Puerto Rico (Inspector o Evaluador de Riesgos) (Estado Civil) (Municipio)

Dirección Postal: P.O. Box 366457, San Juan PR 00936-6457 (Pueblo) (Zip Code)

Teléfonos: Residencial (787) 761-5527 Oficina (787) 420-0220420-0220 Fax (787) 293-5774

Certifico que:

1. Estoy certificado por la Junta de Calidad Ambiental como ( Inspector / Evaluador de Riesgos) con Número de Certificación 1200-0419-LI-017, la cual se encuentra vigente.

2. La estructura "PR-162 Km 4.5” localizada en Aibonito, P.R., la cual será objeto de una demolición se encuentra libre de pintura con base de plomo.

3. La información antes indicada es cierta y correcta.

4. Afirmo y reconozco las consecuencias de incluir y someter información falsa en este documento.

5. Para que así conste, firmo la presente certificación en San Juan de Puerto Rico, (Municipio) hoy día 18 de diciembre de 2019.

Firma del Inspector o Evaluador de Riesgos (en original)

Nota : Deberá someter evidencia de la tarjeta o certificado provista por la JCA.

PR Environmental Quality Board Lead-based Paint Inspector and Company Accreditations

Dirección Física: Ave. Ponce de León 1308, Carr. Estatal 8838, Sector el Cinco, Río Piedras, PR 00926

Tel. (787) 767-8181 • Fax (787) 767-1962

Forma PGC-010

GOBIERNO DE PUERTO RICO

OFICINA DEL GOBERNADOR

(Deberá completarse en letra de molde o impresa)

PGC-_____________________

PARA USO OFICIAL

Yo, Angel A. Burgos Torres, mayor de edad, casado, y vecino de Gurabo, Puerto Rico (Inspector o Evaluador de Riesgos) (Estado Civil) (Municipio)

Dirección Postal: P.O. Box 366457, San Juan PR 00936-6457 (Pueblo) (Zip Code)

Teléfonos: Residencial (787) 761-5527 Oficina (787) 420-0220420-0220 Fax (787) 293-5774

Certifico que:

1. Estoy certificado por la Junta de Calidad Ambiental como ( Inspector / Evaluador de Riesgos) con Número de Certificación 1200-0419-LI-017, la cual se encuentra vigente.

2. La estructura "PR-162 Km 4.7” localizada en Aibonito, P.R., la cual será objeto de una demolición se encuentra libre de pintura con base de plomo.

3. La información antes indicada es cierta y correcta.

4. Afirmo y reconozco las consecuencias de incluir y someter información falsa en este documento.

5. Para que así conste, firmo la presente certificación en San Juan de Puerto Rico, (Municipio) hoy día 18 de diciembre de 2019.

Dirección Física: Ave. Ponce de León 1308, Carr. Estatal 8838, Sector el Cinco, Río Piedras, PR 00926

Tel. (787) 767-8181 • Fax (787) 767-1962

Forma PGC-010

GOBIERNO DE PUERTO RICO

OFICINA DEL GOBERNADOR

(Deberá completarse en letra de molde o impresa)

PGC-_____________________

PARA USO OFICIAL

Yo, Angel A. Burgos Torres, mayor de edad, casado, y vecino de Gurabo, Puerto Rico (Inspector o Evaluador de Riesgos) (Estado Civil) (Municipio)

Dirección Postal: P.O. Box 366457, San Juan PR 00936-6457 (Pueblo) (Zip Code)

Teléfonos: Residencial (787) 761-5527 Oficina (787) 420-0220420-0220 Fax (787) 293-5774

Certifico que:

1. Estoy certificado por la Junta de Calidad Ambiental como ( Inspector / Evaluador de Riesgos) con Número de Certificación 1200-0419-LI-017, la cual se encuentra vigente.

2. La estructura "PR-514 Km 2.6” localizada en Villalba, P.R., la cual será objeto de una demolición se encuentra libre de pintura con base de plomo.

3. La información antes indicada es cierta y correcta.

4. Afirmo y reconozco las consecuencias de incluir y someter información falsa en este documento.

5. Para que así conste, firmo la presente certificación en San Juan de Puerto Rico, (Municipio) hoy día 18 de diciembre de 2019.

Dirección Física: Ave. Ponce de León 1308, Carr. Estatal 8838, Sector el Cinco, Río Piedras, PR 00926

Tel. (787) 767-8181 • Fax (787) 767-1962

Forma PGC-010

GOBIERNO DE PUERTO RICO

OFICINA DEL GOBERNADOR

(Deberá completarse en letra de molde o impresa)

PGC-_____________________

PARA USO OFICIAL

Yo, Angel A. Burgos Torres, mayor de edad, casado, y vecino de Gurabo, Puerto Rico (Inspector o Evaluador de Riesgos) (Estado Civil) (Municipio)

Dirección Postal: P.O. Box 366457, San Juan PR 00936-6457 (Pueblo) (Zip Code)

Teléfonos: Residencial (787) 761-5527 Oficina (787) 420-0220420-0220 Fax (787) 293-5774

Certifico que:

1. Estoy certificado por la Junta de Calidad Ambiental como ( Inspector / Evaluador de Riesgos) con Número de Certificación 1200-0419-LI-017, la cual se encuentra vigente.

2. La estructura "PR-514 Km 3.20” localizada en Villalba, P.R., la cual será objeto de una demolición se encuentra libre de pintura con base de plomo.

3. La información antes indicada es cierta y correcta.

4. Afirmo y reconozco las consecuencias de incluir y someter información falsa en este documento.

5. Para que así conste, firmo la presente certificación en San Juan de Puerto Rico, (Municipio) hoy día 30 de octubre de 2020.

Puerto Rico

PR-162-Aibonito Kms 4.5_4.70_6.20; PR-155-Morovis km 35.0; PR-514-Villalba Km 2.60; PR-514-Villalba Km 3.20 (Group A)

ATTACHMENT 5

LBP INSPECTOR’S, COMPANY AND

XRF PCS QUALIFICATIONS

HEURESIS PCS December 2015

Performance Characteristic Sheet EFFECTIVE DATE: December 1, 2015

MANUFACTURER AND MODEL:

Make: Heuresis Models: Model Pb200i

Source: 57Co, 5 mCi (nominal – new source)

FIELD OPERATION GUIDANCE

OPERATING PARAMETERS:

Action Level mode

XRF CALIBRATION CHECK LIMITS:

0.8 to 1.2 mg/cm2 (inclusive)

SUBSTRATE CORRECTION:

Not applicable

INCONCLUSIVE RANGE OR THRESHOLD:

ACTION LEVEL MODE

READING DESCRIPTION

SUBSTRATE THRESHOLD (mg/cm2)

Results not corrected for substrate bias on any substrate

Brick 1.0 Concrete 1.0 Drywall 1.0 Metal 1.0

Plaster 1.0 Wood 1.0

BACKGROUND INFORMATION

EVALUATION DATA SOURCE AND DATE:

This sheet is supplemental information to be used in conjunction with Chapter 7 of the HUD Guidelines for the Evaluation and Control of Lead-Based Paint Hazards in Housing ("HUD Guidelines"). Performance parameters shown on this sheet are calculated using test results on building components in the HUD archive. Testing was conducted on 146 test samples in November 2015, with two separate instruments running software version 2.1-2 in Action Level test mode. The actual source strength of each instrument on the day of testing was approximately

2.0 mCi; source ages were approximately one year.

OPERATING PARAMETERS

Performance parameters shown in this sheet are applicable only when properly operating the instrument using the manufacturer's instructions and procedures described in Chapter 7 of the HUD Guidelines.

XRF CALIBRATION CHECK:

The calibration of the XRF instrument should be checked using the paint film nearest 1.0 mg/cm2 in the NIST Standard Reference Material (SRM) used (e.g., for NIST SRM 2579, use the 1.02 mg/cm2 film).

If the average (rounded to 1 decimal place) of three readings is outside the acceptable calibration check range, follow the manufacturer's instructions to bring the instrument into control before XRF testing proceeds.

SUBSTRATE CORRECTION VALUE COMPUTATION:

Chapter 7 of the HUD Guidelines provides guidance on correcting XRF results for substrate bias. Supplemental guidance for using the paint film nearest 1.0 mg/cm2 for substrate correction is provided:

XRF results are corrected for substrate bias by subtracting from each XRF result a correction value determined separately in each house for single-family housing or in each development for multifamily housing, for each substrate. The correction value is an average of XRF readings taken over the NIST SRM paint film nearest to 1.0 mg/cm2 at test locations that have been scraped bare of their paint covering. Compute the correction values as follows:

Using the same XRF instrument, take three readings on a bare substrate area covered with the NIST SRM paint film nearest 1 mg/cm2. Repeat this procedure by taking three more readings on a second bare substrate area of the same substrate covered with the NIST SRM.

Compute the correction value for each substrate type where XRF readings indicate substrate correction is needed by computing the average of all six readings as shown below.

For each substrate type (the 1.02 mg/cm2 NIST SRM is shown in this example; use the actual lead loading of the NIST SRM used for substrate correction):

Correction value = (1st + 2nd + 3rd + 4th + 5th + 6th Reading)/6 - 1.02 mg/cm2

Repeat this procedure for each substrate requiring substrate correction in the house or housing development.

EVALUATING THE QUALITY OF XRF TESTING:

Randomly select ten testing combinations for retesting from each house or from two randomly selected units in multifamily housing.

Conduct XRF re-testing at the ten testing combinations selected for retesting.

Determine if the XRF testing in the units or house passed or failed the test by applying the steps below. Compute the Retest Tolerance Limit by the following steps:

Determine XRF results for the original and retest XRF readings. Do not correct the original or retest results for substrate bias. In single-family and multi-family housing, a result is defined as a single reading. Therefore, there will be ten original and ten retest XRF results for each house or for the two selected units.

Calculate the average of the original XRF result and the retest XRF result for each testing combination.

Square the average for each testing combination.

Add the ten squared averages together. Call this quantity C.

Multiply the number C by 0.0072. Call this quantity D.

Add the number 0.032 to D. Call this quantity E.

Take the square root of E. Call this quantity F.

Multiply F by 1.645. The result is the Retest Tolerance Limit.

Compute the average of all ten original XRF readings.

Compute the average of all ten re-test XRF readings.

Find the absolute difference of the two averages.

If the difference is less than the Retest Tolerance Limit, the inspection has passed the retest. If the difference of the overall averages equals or exceeds the Retest Tolerance Limit, this procedure should be repeated with ten new testing combinations. If the difference of the overall averages is equal to or greater than the Retest Tolerance Limit a second time, then the inspection should be considered deficient.

Use of this procedure is estimated to produce a spurious result approximately 1% of the time. That is, results of this procedure will call for further examination when no examination is warranted in approximately 1 out of 100 dwelling units tested.

TESTING TIMES:

In the Action Level paint test mode, the instrument takes the longest time to complete readings close to the Federal standard of 1.0 mg/cm2. The table below shows the mean and standard deviation of actual reading times by reading level for paint samples during the November 2015 archive testing. The tested instruments reported readings to one decimal place. No significant differences in reading times by substrate were observed. These times apply only to instruments with the same source strength as those tested (2.0 mCi). Instruments with stronger sources will have shorter reading times and those with weaker sources, longer reading times, than those in the table.

Mean and Standard Deviation of Reading Times in Action Level Mode by Reading Level

Reading (mg/cm2) Mean Reading Time (seconds) Standard Deviation (seconds)

< 0.7 3.48 0.47

0.7 7.29 1.92

0.8 13.95 1.78

0.9 – 1.2 15.25 0.66

1.3 – 1.4 6.08 2.50

> 1.5 3.32 0.05

CLASSIFICATION OF RESULTS:

XRF results are classified as positive if they are greater than or equal to the stated threshold for the instrument (1.0 mg/cm2), and negative if they are less than the threshold.

DOCUMENTATION:

A report titled Methodology for XRF Performance Characteristic Sheets (EPA 747-R-95-008) provides an explanation of the statistical methodology used to construct the data in the sheets, and provides empirical results from using the recommended inconclusive ranges or thresholds for specific XRF instruments. The report may be downloaded at http://www2.epa.gov/lead/methodology-xrf-performance-characteristic-sheets-epa-747-r-95- 008-september-1997.

This XRF Performance Characteristic Sheet (PCS) was developed by QuanTech, Inc., under a contract with the XRF manufacturer.

Puerto Rico

Certificate of Training Has completed the Heuresis Corp. training materials presented on the topic of

Instrument Operator Training, Pb200i, with regards to the materials licensed by the Commonwealth of Massachusetts and the Nuclear Regulatory Commission.

Instrument Operator Training

Heuresis Corporation, Pb200i

I confirm that the above named individual has received the training listed on this certificate.

Adam Robison March 2nd, 2021 Name Date

Senior Director of Sales Title

I certify that I have received the stated training and understand the content presented. I understand that I can follow up this training with questions from Heuresis Corporation.

Angel Burgos March 2nd, 2021 Name Date

Lead Based Paint
Anejo 1 no cambios.pdf
Lead Based Paint
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
ER-HWY-293-3 (Km 6.2) Oct-25-2019.pdf
1DIC
ER-HWY-293-2 (Km 4.5) Oct-25-2019.pdf
1DIC
ER-HWY-293-3 (Km 4.7) Oct-25-2019.pdf
1DIC
ER-HWY-483 (Km 35) Nov-1-19.pdf
1DIC
ER-HWY-334 (Km 194.4) Oct-30-19.pdf
1DIC
ER-HWY-372-1 (Km 2.6) Oct-25-2019.pdf
1DIC
PGC010-PR162 Km4punto5 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR162 Km4punto7 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR514 Km2punto6 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Test Group A PR162Aibonito_PR514Villalba_Pr155Morovis-RevDic2020.pdf
Lead Based Paint
PGC010-PR514 Km3punto20 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Anejo 3 eliminar comentario XRF y anadir Faltante.pdf
Lead Based Paint
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
ER-HWY-293-3 (Km 6.2) Oct-25-2019.pdf
1DIC
ER-HWY-293-2 (Km 4.5) Oct-25-2019.pdf
1DIC
ER-HWY-293-3 (Km 4.7) Oct-25-2019.pdf
1DIC
ER-HWY-483 (Km 35) Nov-1-19.pdf
1DIC
ER-HWY-334 (Km 194.4) Oct-30-19.pdf
1DIC
ER-HWY-372-1 (Km 2.6) Oct-25-2019.pdf
1DIC
PGC010-PR162 Km4punto5 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR162 Km4punto7 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR514 Km2punto6 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Test Group A PR162Aibonito_PR514Villalba_Pr155Morovis-RevDic2020.pdf
Lead Based Paint
PGC010-PR514 Km3punto20 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
ER-HWY-372-1 (Km 3.2) Oct-25-2019.pdf
1DIC
Anejo 4 poner checkmark.pdf
Lead Based Paint
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
ER-HWY-293-3 (Km 6.2) Oct-25-2019.pdf
1DIC
ER-HWY-293-2 (Km 4.5) Oct-25-2019.pdf
1DIC
ER-HWY-293-3 (Km 4.7) Oct-25-2019.pdf
1DIC
ER-HWY-483 (Km 35) Nov-1-19.pdf
1DIC
ER-HWY-334 (Km 194.4) Oct-30-19.pdf
1DIC
ER-HWY-372-1 (Km 2.6) Oct-25-2019.pdf
1DIC
PGC010-PR162 Km4punto5 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR162 Km4punto7 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR514 Km2punto6 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Test Group A PR162Aibonito_PR514Villalba_Pr155Morovis-RevDic2020.pdf
Lead Based Paint
PGC010-PR514 Km3punto20 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Anejo 4 poner checkmark.pdf
Lead Based Paint
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
ER-HWY-293-3 (Km 6.2) Oct-25-2019.pdf
1DIC
ER-HWY-293-2 (Km 4.5) Oct-25-2019.pdf
1DIC
ER-HWY-293-3 (Km 4.7) Oct-25-2019.pdf
1DIC
ER-HWY-483 (Km 35) Nov-1-19.pdf
1DIC
ER-HWY-334 (Km 194.4) Oct-30-19.pdf
1DIC
ER-HWY-372-1 (Km 2.6) Oct-25-2019.pdf
1DIC
PGC010-PR162 Km4punto5 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR162 Km4punto7 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR514 Km2punto6 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Test Group A PR162Aibonito_PR514Villalba_Pr155Morovis-RevDic2020.pdf
Lead Based Paint
PGC010-PR514 Km3punto20 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Anejo 5 anadir certificado Heuresis AB.pdf
Lead Based Paint
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
Aerial photo ER-HWY-402 (Km 14-8-14-9) Nov-1-2019.pdf
Sheet1
ER-HWY-293-3 (Km 6.2) Oct-25-2019.pdf
1DIC
ER-HWY-293-2 (Km 4.5) Oct-25-2019.pdf
1DIC
ER-HWY-293-3 (Km 4.7) Oct-25-2019.pdf
1DIC
ER-HWY-483 (Km 35) Nov-1-19.pdf
1DIC
ER-HWY-334 (Km 194.4) Oct-30-19.pdf
1DIC
ER-HWY-372-1 (Km 2.6) Oct-25-2019.pdf
1DIC
PGC010-PR162 Km4punto5 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR162 Km4punto7 Aibonito.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-PR514 Km2punto6 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
Test Group A PR162Aibonito_PR514Villalba_Pr155Morovis-RevDic2020.pdf
Lead Based Paint
PGC010-PR514 Km3punto20 Villaba.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
NTL-Nortol-LBPInspyEmpresa-2019 a 2020.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground
PGC010-Intercontinental-Feb2019.pdf
LBP Luna 151 Diagram-February2018.pdf
Ground

File details come from the government source that posted it. Updated .