SECTION J
DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
TABLE OF CONTENTS
ATTACHMENT
NUMBER ATTACHMENT TITLE
J-1503060-01 DEFINITIONS AND ACRONYMS
J-1503060-02 PAVEMENT CLEARANCE SITE MAP
J-1503060-03 PAVEMENT CLEARANCE LOCATIONS AND FREQUENCIES
J-1503060-04 SNOW AND ICE CLEARING LOCATIONS
ATTACHMENT J-1503060-01
DEFINITIONS AND ACRONYMS
DEFINITION/ACRONYM DESCRIPTION
Bare Pavement Free of frozen precipitation down to the surface of the pavement. Bare pavement does not mean completely dry and may still have frozen and/or liquid precipitation in the holes, pores, divots, seams and cracks.
Clear Free of debris, as defined below.
Debris Includes, but is not limited to, paper, cans, bottles, limbs and branches, pine straw and pinecones, leaves, sand, soil, aggregates, grass, metals, and other similar items.
End of Cleanup Defined as when the Contractor has met all performance objectives.
End of Precipitation The end of the hour during which the Contractor and the KO or designated representative mutually agree the precipitation has ended EPA Environmental Protection Agency Finished Street, Road, or Parking Lot
A paved or improved area in which the following conditions are met:
Clear, Dry Area – The entire area of responsibility is as close as possible to clear and dry. Not more than one inch of snow shall remain on the area, including hard packed snow.
Full Width – Snow is from the full width of the paved and improved area of the streets, roads, or parking lots. The snow is removed to at least the outer edge of the entire area of responsibility, so that the outer edge is exposed, unless otherwise specified.
Obstructions – Where obstructions such as utility poles, sign posts, fire hydrants, and trees exist between or in the midst of the streets, roads or parking area: snow shall be cleared around these objects down to the required finished depth (by hand if necessary) so that streets, roads, or parking areas are blocked with snow.
Initiation of Work The Contractor shall initiate work as required to maintain streets, roads, and parking lots within the performance standard for snow removal and sanding.
New Storm Any precipitation occurring after the “End of Precipitation” defined above.
Passage The movement of persons or vehicles across paved surfaces.
Ice (Taken from FAA AC 150/5200-30C)
The solid form of water consisting of a characteristic hexagonal symmetry of water molecules. The density of pure is 57 lb/ cu. ft. (913 kg/ cu. m.), which is 9 percent less dense than water. Compacted snow becomes ice when the air passages become discontinuous at a density of about 50 lb/ cu. ft. (800 kg/ cu. m.).
Snow (on the ground).
(Taken from FAA AC 150/5200-30C)
A porous, permeable aggregate of ice grains, which can be predominately single crystals or close groupings of several crystals.
Snow Event Any occurrence of frozen precipitation that results in visible accumulation of snow or ice on paved surfaces.
ATTACHMENT J-1503060-02
PAVEMENT CLEARANCE SITE MAP
ATTACHMENT J-1503060-03
PAVEMENT SWEEPING LOCATIONS
Location Surface Type Approx.
Size (LF) Remarks
Road A Bituminous 2165 Includes pavement to RDH front entrance Road B Bituminous 320 Road C Bituminous 442 Road D Bituminous 614 Road E Bituminous 255 Road F Bituminous 816 Road G Bituminous 648 Road H Bituminous 816 Road I Bituminous 4097 Snow removal and de-icing activity around areas where ATFP in-ground barriers are located must be performed manually (hand shovel) to avoid damage to barrier equipment.
Road J Bituminous 1007 Exit Route Road M Bituminous 826 Includes entry loop into SCF building around flag poles Road N Bituminous 1600 Road P Bituminous 372 Polish 2nd Check Point through US Main Gate Entrance
Bituminous 870 Access Road – Snow removal and de-icing activity around areas where ATFP in-ground barriers are located must be performed manually (hand shovel) to avoid damage to barrier equipment.
Polish 2nd Check Point through Vehicle Inspection Facility
Bituminous 825 Access Road – Snow removal and de-icing activity around areas where ATFP in-ground barriers are located must be performed manually (hand shovel) to avoid damage to barrier equipment.
SCF North Side roadway
Bituminous 232
Perimeter Road Bituminous 15,700
ATTACHMENT J-1503060-04
SNOW AND ICE CLEARING LOCATIONS
Location Surface Type Approx. Size
(LF)
Priority Remarks
Road A Bituminous 2165 1 Includes road pavement to RDH front entrance
Road B Bituminous 320 1 Road C Bituminous 442 1 Road D Bituminous 614 1 Road E Bituminous 255 1 Road F Bituminous 816 1 Road G Bituminous 648 1 Road H Bituminous 816 1 Road I Bituminous 4097 1 Road J Bituminous 1007 1 Exit Route Road M Bituminous 826 1 Includes entry loop into SCF building Road N Bituminous 1600 1 Road P Bituminous 372 1 Polish 2nd Check Point through US Main Gate Entrance
Bituminous 870 1 Access Road
Polish 2nd Check Point through Vehicle Inspection Facility
Bituminous 825 1 Access Road
SCF North side roadway 232 2 Perimeter Road 15,700 2 Bldg 4500 (PWF) & Bldg
4800 (SCF)
Bituminous 17,000 SF 1 Parking Lot, paved areas, and walkways
Bldg 4900 (Fire Station) Bituminous 16,000 SF 1 Parking Lot, paved areas, and walkways Bldg 4300 (MPF) Bituminous 10,650 SF 2 Parking Lot, paved areas, and walkways Bldg 4400 (GPW2) 17,400 SF 2 Parking Lot, paved areas, and walkways
Working Area for SA Facilities (yellow markings)
Approx.
Size
SA Area (roads/parking areas only) 920 LF SA Access Road 3,227 LF ACS Laydown area 3 acres Access routes to CHUs and laydown areas 4,213 LF CHUs sidewalk & parking 1½ acre