This is a Measurement and Payment exhibit for ITB CIP/250996, the Parking Lot Improvement Program administered by the City of Ocala, Florida. The document outlines the measurement standards and payment methodologies for various infrastructure improvement line items including pavement work, conduit installation, directional boring, traffic separators, decorative concrete finishing, and joint sealing. Specific bid items detailed include PVC conduit in sizes ranging from 1" to 6", directional bore work for PVC and HDPE pipes ranging from 1" to 18" in diameter, traffic separators in multiple types and widths, decorative stamp installations, and hot pour crack sealing for asphalt. The City of Ocala seeks an experienced contractor to complete projects on an as-requested basis that encompass repaving, asphalt overlays, roadway reconstruction, parking lot and trail construction, concrete sidewalks and curbing, stormwater system repairs and installations, and related infrastructure rehabilitation work.
Payment for each line item is established at unit prices set forth in the Bid Schedule and constitutes full compensation for all materials, labor, equipment, and incidentals necessary to complete the work as specified in the contract documents and City of Ocala Standard Specifications for Construction of Streets, Stormwater, Traffic, Water and Sewer Infrastructure. For conduit installation, payment includes trench excavation, sweeps, stub-ups, pull strings, warning tape, and backfill compaction. For directional boring, payment encompasses utility locating, dewatering, shoring, bracing, drill fluid disposal, welding, tracer wire, and testing. For traffic separators, payment includes forming, joint construction, steel reinforcement, and finishing. Bidders must possess three years of roadway resurfacing experience and maintain FDOT Pre-Qualification with reviewed financial statements in applicable work classes.
View the file
Other files for this state and local contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
G-99-2 Remove & Reinstall Speed Hump EA
Payment for this item shall be made at the unit price set forth in the Bid Schedule and shall constitute full compensation for Work specified in the Contract Documents. Payment shall include, but is not limited to, all material cost, labor, and all incidentals and appurtenances required to complete the installation as shown and specified.
G-100-1 1" SCDH 40 PVC, Conduit, Furnish & Install LF G-100-2 2" SCDH 40 PVC, Conduit, Furnish & Install LF G-100-3 3" SCDH 40 PVC, Conduit, Furnish & Install LF G-100-4 4" SCDH 40 PVC, Conduit, Furnish & Install LF G-100-5 6" SCDH 40 PVC, Conduit, Furnish & Install LF
Payment for conduit items includes full compensation for equipment, labor and material necessary to execute the work as required by the plans and applicable City Standards. Payment includes trench excavation, installation of conduit, installation of necessary sweeps and 4' stub ups, pull strings, placement of warning tape, backfilling and compacting of trench and other work necessary for complete installation
G-101-1 DIRECTIONAL BORE 1" PVC PIPE LF
G-101-2 DIRECTIONAL BORE 2" PVC PIPE LF
G-101-3 DIRECTIONAL BORE 2" PVC PIPE LF
G-101-4 DIRECTIONAL BORE 4" PVC PIPE LF
G-101-5 DIRECTIONAL BORE 6" PVC PIPE LF
G-101-6 DIRECTIONAL BORE 2" HDPE PIPE LF
G-101-7 DIRECTIONAL BORE 4" HDPE PIPE LF
G-101-8 DIRECTIONAL BORE 6" HDPE PIPE LF
G-101-9 DIRECTIONAL BORE 8" HDPE PIPE LF
G-101-10 DIRECTIONAL BORE 10 " HDPE PIPE LF
G-101-11 DIRECTIONAL BORE 12" HDPE PIPE LF
G-101-12 DIRECTIONAL BORE 14" HDPE PIPE LF
G-101-13 DIRECTIONAL BORE 16" HDPE PIPE LF
G-101-14 DIRECTIONAL BORE 18" HDPE PIPE LF
Payment for this item shall be made at the unit price set forth in the Bid Schedule and shall constitute full compensation for Work specified in the Contract Documents. Payment shall include, but is not limited to, all costs for excavation, locating existing utilities, backfilling, dewatering, shoring and bracing, directional bore, proper disposal of drill fluids, butt welding of joints and mechanical joint fittings, pipe installation, tracer wire, testing, and all incidentals and appurtenances required to complete the installation as shown and specified.
G-102-1 TRAFFIC SEPARATOR CONCRETE-TYPE I, 4' WIDE LF
G-102-2 TRAFFIC SEPARATOR CONCRETE-TYPE I, 6' WIDE LF
G-102-3 TRAFFIC SEPARATOR CONCRETE- TYPE I, 8.5' WIDE LF
G-102-4 TRAFFIC SEPARATOR - CONCRETE, TYPE II, 4' WIDE LF
G-102-5 TRAFFIC SEPARATOR - CONCRETE, TYPE II, 6' WIDE LF
G-102-6 TRAFFIC SEPARATOR CONCRETE- TYPE II, 8.5' WIDE LF
Exhibit D - Measurement and Payment CONTRACT# CIP/250996
D-1
G-102-7 TRAFFIC SEPARATOR CONCRETE- TYPE IV, 4' WIDE LF
G-102-8 TRAFFIC SEPARATOR CONCRETE- TYPE IV, 6' WIDE LF
G-102-9 TRAFFIC SEPARATOR CONCRETE- TYPE IV, 8.5' WIDE LF
G-102-10 TRAFFIC SEPARATOR CONCRETE, TYPE V, 4' WIDE LF
G-102-11 TRAFFIC SEPARATOR CONCRETE- TYPE V, 6' WIDE LF
Payment for this item shall be made at the unit price set forth in the Bid Schedule and shall constitute full compensation for Work specified in the Contract Documents. Payment shall include, but is not limited to, all material cost, forming, contraction joint forming, expansion joint construction, steel reinforcement, finishing and backfilling and compaction, and all incidentals and appurtenances required to complete the installation of the traffic separator as shown and specified in plans and in accordance with Standard Plans 520-020
G-103 Decorative Stamp installed in concrete finish (City provides stamp) EA
Payment for this item shall be made at the unit price set forth in the Bid Schedule and shall constitute full compensation for all cost associated with installing a decorative stamp at each location as specified in the Contract Documents. (Each location may have up to two (2) stamps in a five feet by five feet (5’ x 5’) area.
G-104-1 JOINT SEALER FOR PAVEMENT AND STRUCTURES: HOT POUR CRACK SEALING GA
G-104-2 JOINT SEALER FOR PAVEMENT AND STRUCTURES: HOT POUR CRACK SEALING GA
Payment for this bid item shall be made at the unit price set forth in the Bid Schedule and shall constitute full compensation for Work specified in the Contract Documents. Payment shall include, but is not limited to, all costs to crack fill, and all incidentals and appurtenances required to complete the sealing of the Asphalt as shown and specified in FDOT Standard Specifications for Road and Bridge Construction.
*All other line items measurements and payments descriptions can be found in the City of Ocala Standard Specifications for Construction of Streets, Stormwater, Traffic, Water and Sewer Infrastructure.