7-30-2026 - RFIs - SOLICITATION 36C77626R0065 - Castle Point.xlsx
XLSX spreadsheet 102 KB Posted
- Solicitation number
- IFB-36C77626B0025
About this file
This file is a Request for Information (RFI) tracker documenting 134 pre-bid questions and government responses related to SDVOSB Solicitation 36C77626R0065 for EHRM Infrastructure Upgrades at Castle Point VA Medical Center in Wappinger Falls, New York. The project involves comprehensive renovation and infrastructure upgrades across multiple buildings on a 730-day performance period.
The RFIs address critical clarifications across multiple disciplines: civil work including site utilities, earthwork, drainage, and stormwater systems; structural work including foundation design, dewatering requirements, earth retention systems, and prefabricated ramp specifications; architectural finishes, glazing systems, and fire protection installations; mechanical systems including VRF HVAC, fuel oil piping containment, generator specifications, and chilled water/steam tie-ins; electrical work including generator power ratings, underground ductbanks, and concrete encasement requirements; and telecommunications infrastructure encompassing fiber optic backbone cables (96-strand OS2 umbilical, 12-strand OS2/24-strand OM4 cables), category 6A cabling for workstation outlets, access control systems, video surveillance with no additional licensing required, and fire alarm panel integration. Key contractual clarifications include confirmation that the project is a 100% SDVOSB set-aside requiring VA PIV badging for all personnel, that this is a Firm Fixed Price contract with no economic price adjustment clauses, that design team members are precluded from serving as prime contractors or subcontractors, that stored materials payment is at the Contracting Officer's discretion, and that Notice to Proceed is anticipated within 90 days of award. Environmental scope includes asbestos and presumed asbestos-containing materials abatement with limited scope in Building 88 due to design changes from full renovation to wall-mounted telecommunications enclosure. The file reflects extensive coordination among the A/E team, VA departments, and prospective contractors regarding sequencing constraints in patient-care areas, off-hours work requirements for recabling activities, and VA responsibility for active network equipment programming and cutover.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table
| VA CASTLE POINT EHRM IU - PRE-BID RFIs TRACKER | |
| Numbered Item & Submittal | VA / Client Comments - Compiled from multiple review documents by phase |
| Item # | CPS Phase | Discipline | Reference | Description | Contractor Question | VA Dept. | Government Response | Gov. Reviewer | A/E Responses | A/E Reviewer | Chris Hanson review | Review Date | |
| 001 | Pre-Bid | Will the government pay for materials stored per VAAR 852.232-70 and FAR 52.232-5? We have experienced PCAC Contracting Officers refusal to pay for materials stored on site during these periods of material shortages and the need to expedite procurement of materials when available to meet schedule obligations and prevent project delays. This is an important factor in preparing Price proposals. | In accordance with contract terms and conditions, Contractors should not submit an offer assuming the Government will approve monthly progress payments for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves. | PCAC | |||||||||
| 002 | Pre-Bid | Please confirm that any designers or consultants who provided professional services for the construction documents, including reports, are precluded from pursuing this project as a Prime contractor, Mentor-Protégé partner, or subcontractor. | Any member of the design team of this project is not permitted to be part of the construction team. | PCAC | |||||||||
| 003 | Pre-Bid | Please confirm that this project is a competitive SDVOSB set-aside and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protégé partnership under the SBA/VA Mentor-Protégé program in which the partnership has been approved prior to the due date. | This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors. | PCAC | |||||||||
| 004 | Pre-Bid | Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a bid guarantee or a payment & performance bond for a SDVOSB. | This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors. | PCAC | |||||||||
| 005 | Pre-Bid | When visiting the link, I noticed the project was “set aside for Service-Disabled Veteran Owned Small Business” – does this mean that General Contractors cannot bid the project unless they meet that requirement? | Yes, this project is a 100% set-aside for SDVOSBs. The prime contractor submitting the offer must be certified as such in the SBA VetCert database. | PCAC | |||||||||
| 006 | Pre-Bid | Is this project tax-exempt, if so, will a certificate be provided? | No. See Special Note regarding FAR 52.229-3 Federal, State, and Local Taxes in the solicitation. It is solely the responsibility of the offeror to include all state and local sales or use taxes for construction materials, and all other applicable taxes, in their bid or proposal price. | PCAC | |||||||||
| 007 | Pre-Bid | Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes. | Regardless of affiliation, everyone working within VA facilities or requiring access to VA information systems requires a VA PIV Card. PIV badging requirements can be found at https://www.osp.va.gov/How_To_Get_A_VA_ID_Badge.asp Immediately after the bonds are provided to the Government, the contractor shall immediately start working with the identified COR at the site to commence the VA PIV process for all known contractor personnel that will be working the project. All contractors must have a PIV Card in order to work on site. | PCAC | |||||||||
| 008 | Pre-Bid | How soon after award is NTP expected to be issued? | The Government anticipates issuance within 90 calendar days after award. | PCAC | |||||||||
| 009 | Pre-Bid | Will the VA allow deviations to Buy American Act if the noted products are not available? | The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. Any items not compliant must be specifically listed in the offer. | PCAC | |||||||||
| 010 | Pre-Bid | Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin. | This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added. | PCAC | |||||||||
| 011 | Pre-Bid | Civil | CJ100 | DWGs | Sheet CJ100 - CIVIL NOTES - Civil General Note 6 states that if surplus soil needs to be removed from site, the soil shall be handled per Specification 31 20 11. The issued specification table of contents appears to include Section 31 20 00 Earthwork, but not Section 31 20 11. Please clarify. | This is a numbering error; 31 20 11 is Earthwork (Short Form) but 31 20 00 Earthwork is utilized for the spec section. | JG | 6/11/26 | |||||
| 012 | Pre-Bid | Enviro | 02 82 11 | Specs | Section 02 82 11 includes requirements for the Contractor’s Professional Industrial Hygienist / Certified Industrial Hygienist and IH Technician, including air monitoring, inspections, daily logs, and completion documentation. Please confirm whether these CPIH/CIH/IH Technician services are required to be provided by the Contractor/abatement subcontractor in addition to the asbestos contractor’s NYS DOL competent person/supervisor, or whether the competent person/supervisor may perform these functions where allowed by NYS DOL requirements. | Section 02 82 11 reflects the VA TIL specification requirements; any deviations from requirements outlined in these specifications requires review and approval by the VA CO. | JG | 6/11/26 | |||||
| 013 | Pre-Bid | Enviro | HA100 | DWGs | HA100 Note 2 states that the Contractor shall remove all ACM for all specified areas whether or not shown or accurately indicated, and that the specifications do not limit the Contractor’s responsibility to seek and remove all ACM. Please confirm that the abatement scope for bidding is limited to ACM/PACM materials identified in the contract documents within the indicated limits of disturbance, and that concealed or additional ACM not identified in the documents will be addressed by modification if encountered. | A/E did not perform any destructive or invasive sampling during the limited Asbestos and Lead survey; should any ACM or Lead Containing Materials be discovered that were not previously identified during design, this will likely constitute unforeseen conditions to addressed via modification. | JG | 6/11/26 | |||||
| 014 | Pre-Bid | Enviro | 088HA101 | ||||||||||
| 02 82 11 | DWGs | ||||||||||||
| Specs | Building 88 hazmat documents Building 88 hazmat documents appear inconsistent. The environmental survey sample-location sheet for Building 88 indicates no ACM identified upon PLM/QTEM analysis, while Sheet 088HA101 requires removal/disposal of ACM/PACM sheetrock, wall joint compound, and 2x2 ceiling tile, and Section 02 82 11 includes estimated Building 88 abatement quantities including floor tile/mastic, ceiling tile, and drywall/joint compound. Please confirm the required asbestos/PACM abatement scope for Building 88, including whether floor tile/mastic is included. inconsistent. The environmental survey sample-location sheet for Building 88 indicates no ACM identified upon PLM/QTEM analysis, while Sheet 088HA101 requires removal/disposal of ACM/PACM sheetrock, wall joint compound, and 2x2 ceiling tile, and Section 02 82 11 includes estimated Building 88 abatement quantities including floor tile/mastic, ceiling tile, and drywall/joint compound. Please confirm the required asbestos/PACM abatement scope for Building 88, including whether floor tile/mastic is included. | Samples were taken in RM 006E, which was the original location for the TR. This was shifted late in the design to RM 002A, and was also modified to a Telecommunications Enclosure, requiring significantly less demolition activities in this space. Because sampling was not conducted in RM002A, the abatement plan is based on assumed quantities. Construction activities are limited to installation of FRT plywood over the wall where the TE is to be installed, as well as installation of a new semi-recessed FEC. | JG | 6/11/26 | |||||||||
| 015 | Pre-Bid | Structural | 115-S-200 | DWGs | 115-S-200 identifies a prefabricated ramp and notes that foundation and pier requirements are to be coordinated with the final selection of the ramp manufacturer. Please provide the Basis-of-Design manufacturer/model for the prefabricated ramp system, or confirm the minimum performance, material, finish, loading, railing/handrail, post-spacing, and delegated-design requirements to be used for bidding. | Ramp shall be a galvanized steel premanufactured ramp with 3'-6" guardrail designed for a concentrated live load of 200lb in any direction or a distributed load for 50plf in any direction. The ramp structure itself shall have capacity to support its self-weight as well as 100 psf live load and a concentrated load of 300lb. | ARL | 7/5/26 | |||||
| 016 | Pre-Bid | Structural | Geotechnical Report | Dewatering | The geotechnical report indicates on page 12 that groundwater/perched water was encountered in the borings and further states that, for bidding purposes, the Contractor should assume groundwater elevation at the ground surface, with dewatering sufficient to maintain groundwater at least 2 feet below the bottom of excavation. The structural drawings/general notes do not appear to identify a specific dewatering system or groundwater elevation basis for the Building 115 Data Center excavation. Please confirm the required dewatering basis of bid for the Building 115 Data Center excavation, including whether bidders are to assume groundwater at existing ground surface for the duration of excavation/foundation work, and whether engineered dewatering, monitoring, discharge treatment/permitting, standby equipment, and 24-hour operation are required to be included. | Groundwater level and dewatering requirements should follow the recommendations in the geotechnical report. | ARL | 7/5/26 | |||||
| 017 | Pre-Bid | Structural | Geotechnical Report | Earth Retention | The geotechnical report states on page 10 that required excavations for the proposed Data Center will likely require an earth retention system and that excavation support systems are to be designed by a New York licensed professional engineer. The contract drawings do not appear to show a specific shoring, sheeting, or earth-retention system for the Building 115 Data Center excavation. Please confirm whether temporary excavation support/shoring/sheeting for the Building 115 Data Center is required to be included as a Contractor-designed means-and-methods item, and whether any restrictions apply due to adjacent existing buildings, tunnel/corridor construction, utilities, pavements, or VA operations. | Sheeting and shoring is a means and methods item, but is likely required due to the grade changes on the site. Existing adjacent footings have been indicated on the structural drawings to the best of EOR's ability. Sheeting/shoring shall be designed so that stability of existing building foundations is not affected. | ARL | 7/5/26 | |||||
| 018 | Pre-Bid | Civil | CU101 | DWGs | CU101, a note pointing to the storm sewer at the top of the sheet states "See CU114 Plan…" Such sheet is not present in the provided documents. Please provide CU114. | Mislabeled, should be CU112. | LS | 7/6/26 | 7/6/26 | ||||
| 019 | Pre-Bid | Electrical | 26 32 13 | Specs | Section 26 32 13 states that the rated power of a generator is stated on the drawings. The new generator being installed in the MCR does not have indication of its rated power on the drawing sheets. Please specify the power rating for the generator. | Generator nameplate ratings are shown on Sheet 115EP601 and 115EP701. | SHM | 7/1/26 | |||||
| 020 | Pre-Bid | VA | Please provide the name brand of the PACS, VSS and IDS Equipment installed on site today. | A/E defers to the VA station for preferred equipment manufacturer information. | JG | 7/14/26 | |||||||
| 021 | Pre-Bid | VA | We understand that there has been a recent project award to convert the entire campus to Software House CCURE 9000 for the PACS system. The LENEL system will be discontinued. Please confirm we can quote Software House CCURE 9000. | A/E defers to the VA station for direction related to the PACS system project updates. | JG | 7/14/26 | |||||||
| 022 | Pre-Bid | Telecom | If current security equipment lines/equipment are damaged/removed during construction, would that be considered part of this project to replace? | Some security equipment is called out to be removed from its current locations and reinstalled at the location shown on the drawings. If damage should occur during this process, it would be the responsibility of the Contractor to replace it at their cost. | KG | 7/6/26 | |||||||
| 023 | Pre-Bid | Telecom | Can you supply information on existing panel capacity for Access, IDS and Video systems? | A/E defers to the VA station for preferred equipment manufacturer information. | JG | 7/14/26 | |||||||
| 024 | Pre-Bid | Telecom | If any security system capacity has been reached or would be reached in some areas, would mitigation be considered part of this project? | A/E defers to the VA station for specific information related to the security system current capacities. | JG | 7/14/26 | |||||||
| 025 | Pre-Bid | Telecom | Based on initial design will changes in pathways be considered if it is found to be more advantageous to the security systems layout and possible be more cost effective? | Yes. If an improved pathway is found the Contractor must bring this to the attention of the VA for consideration and direction. | KG | 7/6/26 | |||||||
| 026 | Pre-Bid | Telecom | Can you provide a network map that indicates where that network is established? | A/E defers to the VA station for specific information related to as-built documents for existing network coverage. | JG | 7/14/26 | |||||||
| 027 | Pre-Bid | Telecom | Is all security equipment on a stand-alone LAN network? If so, can you list the components of that network and available expansion. | The existing security equipment is on OIT's network. | SHM | 7/6/26 | |||||||
| 028 | Pre-Bid | Telecom | Will any new switches need to be provided for this Bid? If so can you list the exact model and manufacture of switch needed. | No. The VA provides and installs any required switches. | KG | 7/6/26 | |||||||
| 029 | Pre-Bid | Telecom | Would a new video server be needed to support the additional cameras for this project? | No. A new NVR will not be required. | KG | 7/6/26 | |||||||
| 030 | Pre-Bid | Telecom | Would any additional video License be needed for the new cameras? | The Contractor needs to bid camera brands that do NOT require additional licensing for the NVR. | KG | 7/6/26 | |||||||
| 031 | Pre-Bid | Telecom | If new licenses are needed, please provide | A/E defers to the VA station for specific information related to current / future license needs. | JG | 7/14/26 | |||||||
| 032 | Pre-Bid | Telecom | Will any new network switches be required for any of the new security products? | A/E defers to the VA station regarding security system needs. | JG | 7/14/26 | |||||||
| 033 | Pre-Bid | Telecom | If they are required, can you supply the exact model number of the switches needed? | A/E defers to the VA station regarding security system needs. | JG | 7/14/26 | |||||||
| 034 | Pre-Bid | Telecom | If they are required, can you supply the exact Location of the new switch/switches? | A/E defers to the VA station regarding security system needs. | JG | 7/14/26 | |||||||
| 035 | Pre-Bid | Telecom | Where do the motions in each room terminate into. No IDS panel is listed on the prints and no Keypads to disarm upon opening the room? | These are intended to be terminated on the access control system and need to report to the Police Station when in alarm mode. | KG | 7/6/26 | |||||||
| 036 | Pre-Bid | Telecom | What IDS panel is needed if not installed? | No IDS panel is required. | KG | 7/6/26 | |||||||
| 037 | Pre-Bid | Telecom | What type of cameras are currently in place? | A/E defers to the VA for equipment manufacturer information. | JG | 7/14/26 | |||||||
| 038 | Pre-Bid | Telecom | What type of camera, make and model, is being requested for the new installation | Specific makes and models are not outlined in the construction documents. The Contractor can bid any brand that meets the requirements of the design specifications including no additional licensing costs. | KG | 7/6/26 | |||||||
| 039 | Pre-Bid | Telecom | Is there a license requirement for the new cameras? | The requirement is that no licensing costs are added to the project. | KG | 7/6/26 | |||||||
| 040 | Pre-Bid | VA | Does the price cost worksheet need to be broken down per building? Or can it just be all together? | A/E defers to VA Contracting for specific pricing breakdown requirements | JG | 7/14/26 | |||||||
| 041 | Pre-Bid | Electrical | |||||||||||
| Telecom | What type of keypad card reader is requested for the new installation? | Basis of design is HID pivCLASS #RK40 or equivalent as shown on Sheet ET503. | SHM | 7/6/26 | |||||||||
| 042 | Pre-Bid | Telecom | General note 8, ETG001 | ||||||||||
| General note 6, ETS001 | DWGs | General note 8 on sheet ETG001 states “PRIOR TO INSTALLING CABLING, ALL EXISTING CABLES SHALL BE SEGREGATED INTO DIFFERENT GROUP TYPES; ONCE SEPARATED, CONTRACTOR SHALL DETERMINE WHICH CABLES SHALL BE REMOVED AND WHICH SHALL REMAIN. DEMOLISH ALL CABLES TO BE REMOVED BACK TO SOURCE IN ITS ENTIRETY, UNLESS OTHERWISE NOTED.” While General note 6 on sheet ETS001 states “A TELECOMMUNICATIONS OUTLET UPGRADE SHALL INCLUDE, BUT IS NOT LIMITED TO REMOVING AND DISPOSING OF EXISTING DEVICES” | |||||||||||
| Please confirm that only outlets receiving new cabling, or outlets specifically called out for demolition, will be removed. Please confirm all existing outlets not shown in scope can remain. | WAOs shown on the drawings are existing. These locations are being upgraded with new category 6A cables. What is demolished is the existing cables, jacks and faceplates. Any conduits and backboxes connected to these existing WAOs are to remaon in place and not be demolished. Existing WAPs and Cameras will have the existing category cable(s) demolished and replaced with new category 6A cables. | KG | 7/6/26 | ||||||||||
| 043 | Pre-Bid | Telecom | Please advise if, when feasible, the contractor can install new network cabling through existing J-hook pathways. | Yes, J hooks are an acceptable method of support for new category 6A cables and fiber optic cables. | KG | 7/6/26 | |||||||
| 044 | Pre-Bid | Telecom | Will HEPA carts and tenting be required for telecommunications work? | Please refer to Specification section 01 00 00 General Requirements. In all patient serving buildings, the ICARA standards must be met. | KG | 7/6/26 | |||||||
| 045 | Pre-Bid | Telecom | Please advise if all Wireless Access Point devices will be GFCI. If contractor is to provide Wireless Access Points, please provide specs on Access Points required. | WAPs will be powered with POE and will not rewquire GFCI. | KG | 7/6/26 | |||||||
| 046 | Pre-Bid | Telecom | Please confirm no new work is required for nurse call systems | The Nurse call system is not in scope for this EHRM project. | KG | 7/6/26 | |||||||
| 047 | Pre-Bid | Telecom | Please confirm all new network TR closets will be utilizing basket tray, and not ladder racking. | Basket tray in TRs is to be for the pathway and support of cabling entering the TR and terminated on the new Racks. Ladder Rack is used to support the fiber optic cables when they route vertically in a TR. | KG | 7/6/26 | |||||||
| 048 | Pre-Bid | Telecom | Please advise if ceilings/walls will be open for cable demo/installation, or will Low Voltage Contractor need to cut holes in existing walls/ceilings as needed for cable installation and demolition | The AE cannot confirm that all ceilings and walls will be fully open. The Contractor should anticipate that there will be areas where penetrations will need to be provided to route cabling. | KG | 7/6/26 | |||||||
| 049 | Pre-Bid | Tech | FOC Utility Plans |
CU Sheets
| C4/TN400 | DWGs | FOC Utility Plans: Please confirm that all ductbanks shown on CU sheets are to be 8 x 4" conduits per detail C4/TN400. | Refer to SITE PLAN 00-TN001 for conduit counts. | IMEG - AS | 7/6/26 | |||||||
| 050 | Pre-Bid | Tech | CU104 | DWGs | Sheet CU104: Please clarify if FOC run from MH-16 to MH-17 & MH-18 are also 8 x 4" conduits. | Correct | IMEG - AS | 7/6/26 | ||||
| 051 | Pre-Bid | Tech | CU106 | DWGs | Sheet CU106: Please clarify if FOC run from HH-21 to HH-19 & HH-20 are also 8 x 4" conduits. | Correct | IMEG - AS | 7/6/26 | ||||
| 052 | Pre-Bid | Civil | CU109 | DWGs | Sheet CU109: There is an unlabeled electrical conduit run shown into Building 008, please provide more information (i.e. source/destination, concrete encased, size and quantity of conduit and wire). | Please see sheet ETS003 for additional information. | SHM | 7/1/26 | ||||
| 053 | Pre-Bid | Tech | C4/TN400 | DWGs | Detail C4/TN400 shows #4 continuous rebar, please confirm that all FOC ductbanks will follow this detail. | Rebar Continuious as indicated top and bottom. | IMEG - AS | 7/6/26 | ||||
| 054 | Pre-Bid | Structural | Building 015 new TR Tower Structural Plans | DWGs | Building 015 new TR tower structural plans call out a 6-1/2" total slab thickness but mention 3-1/2" of concrete on 2" metal deck. Please clarify total thickness and thickness of concrete and metal deck. | Provide 5 1/2" thick concrete slab (3 1/2" LWC on 2" deck). | ARL | 7/5/26 | ||||
| 055 | Pre-Bid | Structural | 015-S-102, 103, 104 | DWGs | Sheet 015-S-102, 103, 104: Please clarify size of cantilever beams. | Cantilever beams are to match the size of the beam of the back span on the other side of the column, typ. | ARL | 7/5/26 | ||||
| 056 | Pre-Bid | Architectural | Building 115 | DWGs | Please clarify that new concrete at building 115 shall not receive any finish (i.e. sealer or resinous coating) unless noted in the room finish schedule. | AE clarifies that concrete sealer to follow spec section 03 30 00 -11 Case-in-Place Concrete | NE | 7/1/26 | 7/1/26 | |||
| 057 | Pre-Bid | Architectural | 115A-100A | DWGs | Sheet 115A-100A: Please clarify if exterior fuel tank enclosure walls should receive air barrier and rigid insulation over the new concrete wall. | AE clarifies that rigid insulation and air barrier can be ommited. | NE | 6/29/26 | 6/29/26 | |||
| 058 | Pre-Bid | Telecom | Please clarify if the additional 10% WAO allowance are to be 2-port outlets. | Yes, 2 port WAO's | KG | 7/6/26 | ||||||
| 059 | Pre-Bid | Telecom | ETS100 | DWGs | Sheet ETS100 keynote legend calls out for existing call boxes to be re-fed with (2) Cat6A cables, however, this keynote does not appear on the plan. Please clarify location and routing of these call boxes. | Keynote applies to entire page. Callbox locations shall be field verified. CAT6A cable routing shall utilize existing pathway from callbox back to nearest new Telecom Room. | SHM | 7/6/26 | ||||
| 060 | Pre-Bid | Civil | CK100 | DWGs | Please identify locations where CK100 Type 3 Utility Trench Patch is applicable. | There are not specific locations for this detail, it is only provided as supplemental information if it ends up being needed during construction. All types of VA utility patching were provided. | LS | 7/6/26 | 7/6/26 | |||
| 061 | Pre-Bid | Civil | CS100 | DWGs | Sheet CS100: Please confirm that the pre-fabricated ramp shown will be provided and installed by others and will not be part of this contract. | Ramp is part of this contract unless the VA decides otherwise. "By others" indicates not designed by civil. | LS | 7/6/26 | 7/6/26 | |||
| 062 | Pre-Bid | Structural | Detail 11/S-300 | DWGs | Detail 11/S-300 shows a detail for the pre-fabricated ramp footings, will this same detail be used for the landings? | Design intent is for the detail to be utilized at all footings for prefabricated ramp and landings. | ARL | 7/5/26 | ||||
| 063 | Pre-Bid | Structural, Architectural | 115A-103, | |||||||||
| Structural Drawings | DWGs | Wall along column line "D" on 115A-103 is called out as type C02a CMU, however on the structural drawings this same wall is shown as cast-in-place concrete. Please confirm this wall should be concrete. | Structural drawings shall govern for construction of this wall. | ARL | 7/5/26 | |||||||
| 064 | Pre-Bid | Mechanical | What is the current BAS manufacturer and service vendor? | The A/E has FIPS Panasonic listed, can the VA confirm this is still the case and provide any additional manufacturers if some buildings are operating on a different system. | AP | 7/13/26 | 7/13/26 | |||||
| 065 | Pre-Bid | Telecom | What Is the current Access Control system manufacturer and service vendor? | A/E defers to the VA for equipment manufacturer information. | JG | 7/14/26 | ||||||
| 066 | Pre-Bid | Telecom | What is the current Surveillance System manufacturer and service vendor? | A/E defers to the VA for equipment manufacturer information. | JG | 7/14/26 | ||||||
| 067 | Pre-Bid | Telecom | What is the current Fire Alarm system manufacturer and service vendor? | Campus installed base is Notifier by Honeywell. Reference Specification 28 31 00 - 2.1.B. | SHM | 7/1/26 | ||||||
| 068 | Pre-Bid | Structural | Geotechnical Report | Based on the geotechnical report, we are assuming all foundations will be backfilled with structural fill, is that correct? | Follow recommendations in geotechnical report for backfill requirements. | ARL | 7/6/26 | |||||
| 069 | Pre-Bid | Structural | Please confirm that the General Contractor is responsible for the delegated design of any required shoring. | Confirmed, sheeting and shoring is a delegated design and is responsibility of the general contractor. | ARL | 7/6/26 | ||||||
| 070 | Pre-Bid | Architectural | 115AE201/202 | DWGs | Sheet 115AE201/202: Does the brick veneer extend below grade at the new data center? | AE clarifies that the brick veneer stops at grade for the data center | NE | 6/29/26 | 6/29/26 | |||
| 071 | Pre-Bid | Civil | Please provide Fire Hydrant BOD manufacturer/model and valve type. | Mueller Super Centurion or Clow Medallion or equal with resiliant wedge gate valves. | LS | 7/6/26 | 7/6/26 | |||||
| 072 | Pre-Bid | Civil | Will a live tap of the water main be allowed for utility work or will we be able to shut down the main for a few days? | This decision is the VA's to make. EOR is okay with either option so long as all standard safety and contamination prevention measures are used. | LS | 7/6/26 | 7/6/26 | |||||
| 073 | Pre-Bid | Civil | What is the manufacturer or type of the water line air release, and is it in a contained pit or box? | APCO or equal. Yes, they should be in a pit/box. | LS | 7/6/26 | 7/6/26 | |||||
| 074 | Pre-Bid | Mechanical | 23 10 00-12 2.5 | Specs | Per spec (231000-12 2.5) the secondary fuel containment pipe is Prefab Containment (Galvanized Sched 40 Steel Conduit with Epoxy Coating/Cathodic Protection). Based on spec this could be a 6” or 8” Containment pipe, please clarify the size of this secondary contaiment conduit. | Section 2.5 of specification 23 10 00 indicates the spacing between the carrier pipe and the fuel line. | AP | 7/2/26 | ||||
| 075 | Pre-Bid | Mechanical | Are there any supports required for the underground containment pipe? | Yes, per specification 23 10 00 Facility Fuel Oil Systems, section 2.5.C. | AP | 7/2/26 | ||||||
| 076 | Pre-Bid | Mechanical | Are there any details/sections for the underground fuel piping? | Follow the requirements listed in specification 23 10 00 Facility Fuel Oil Systems. | AP | 7/2/26 | ||||||
| 077 | Pre-Bid | Mechanical | The Run from Tank to Data Center is approx. 190 feet with a 17 foot vertical drop in elevation, based on this a 6” or 8” Sched 40 Containment system may not be recommended. Are there any alternative systems that will be permitted ? (i.e. factory-engineered flexible double-wall fuel oil piping) | Section 2.5 of specification 23 10 00 indicates the spacing between the carrier pipe and the fuel line. Any alternatives must comply with specification 23 10 00. | AP | 7/2/26 | ||||||
| 078 | Pre-Bid | General | Please clarify that the roles of project superintendent, SSHO, and CQC System manager shall be filled by (3) individual persons with no other duties. | Any deviations from the contract specifications (DIV 01) regarding roles and potential overlap in titles must be submitted to the VA CO for final determination. | JG | 7/14/26 | ||||||
| 079 | Pre-Bid | General | Please confirm that a Special Inspector of Record (SIOR) will be required and hired by the General Contractor. | Contractor shall meet the requirements stated in the Contract Specifications; any deviations must be submitted to the VA CO for formal approval. | JG | 7/14/26 | ||||||
| 080 | Pre-Bid | Telecom | Please clarify how many TRs will be available to work in at a time. | Specification section 01 00 00 GENERAL REQUIREMENTS, stats that a maximum of 3 TR locations can be worked on at a time. This is to be determined by the VA and the GC. | KG | 7/6/26 | ||||||
| 081 | Pre-Bid | Telecom | Please clarify if (3) MaxCell 4-pocket ducts are required in all OSP conduits, including spares. | Maxcell 3 pocket ducts are required in all OSP conduits. | KG | 7/6/26 | ||||||
| 082 | Pre-Bid | Telecom | Will all firestopping have to be done by a UL or FM Global certified contractor? | The firestopping in all Telecommunications applications, MUST be completed by a factory trained and certified technician, unless otherwise required in the firestopping specifications. | KG | 7/6/26 | ||||||
| 083 | Pre-Bid | Telecom | For additional 10% WAOs, are these all assumed to be new rough-ins? | No. There could be locations that are currently existing but not in use or not identified on the drawings. | KG | 7/6/26 | ||||||
| 084 | Pre-Bid | Telecom | Are we to assume that for replacement WAOs in the same location, that we will be able to reuse the existing conduit? | Yes. Please note, if the existing conduit stubbed above the ceiling does not have a plastic bushing on it the Contractor shall place on on it. Also please read General Note 13 on sheet 01ET1000 for OD of category 6A cables in a 3/4 inch cnoduit. | KG | 7/6/26 | ||||||
| 085 | Pre-Bid | Architectural | For any new WAO rough-ins where drywall patching is needed, we are assuming painting from seam to seam, please confirm that is correct. | AE clarifies for painting in WAO and TE spaces follow detail 4/AE421 | NE | 7/6/26 | ||||||
| 086 | Pre-Bid | General | Below-Grade Waterproofing | Specs | Please provide specification for below-grade waterproofing. | AE clarifies that below-grade waterproofing for data center foundation walls to be Bituthene 4000 for basis of design. | NE | 7/16/26 | 7/16/26 | |||
| 087 | Pre-Bid | Architectural | 10 26 00 | Specs | Specification 10 26 00 Wall Protection has been included but not identified on the plans or finish schedule, please clarify where wall protection (corner guards, rigid paneling, or bumper/crash rails) are applicable. | AE clarifies that corner guards are to be used. Refer to marked up sheet 115A-104. | NE | 6/29/26 | ||||
| 088 | Pre-Bid | Mechanical | M-601 | DWGs | Sheet M-601: On the VRF schedule, a spare condenser is indicated and refers to remark 16 which was not included in the schedule. Please clarify if spare condensers will be required. | The "SPARE CONDENSER SEE REMARK 16" contains a typo and the note should read "SPARE CONDENSER SEE REMARK 10." Per this note, spare condenser's will be required. | AP | 7/2/26 | ||||
| 089 | Pre-Bid | Mechanical | M-605 | |||||||||
| 115M-101, Note 2 | DWGs | Sheet M-605 contains schedule for the Exhaust Silencer/ Muffler and Sheet 115M-101 Note 2 says that HVAC is to provide the silencer/muffler. Typically this is included with the generator package. Please revise the notes to indicate that this will be provided by the generator supplier. | Silencer to be installed by mechanical contractor. Mechanical contractor to verify if generator selection includes silencer before ordering. | AP | 7/2/26 | |||||||
| 090 | Pre-Bid | Mechanical | 115M-102 | DWGs | Sheet 115M-102 indicates tie ins to existing CHW and Steam Pipe in the BLDG 111 Pipe Tunnel. Are these tie ins to be done during a System Shutdown or to be done as “WET/HOT TAPS” ? | Connection of chilled water should be done during a system shut down. VA to confirm shut down is acceptable. | AP | 7/2/26 | ||||
| 091 | Pre-Bid | Mechanical | 111M-402 | DWGs | Mechanical Dwg. 111M-402 shows the start of Underground FO Pipe From FO Tank to Data Center Generator. The Drawing indicates that continuation of pipe ½” FOS / ¾” FOR is on CIVIL Drawings (CU-113). Per spec (231000-12 2.5) this pipe is Prefab Containment (Galvanized Sched 40 Steel Conduit with Epoxy Coating/Cathodic Protection). Based on spec this could be a 6” or 8" Containment pipe. Please advise if a containment pipe is required for the fuel piping and what size is required. | Section 2.5 of specification 23 10 00 indicates the spacing between the carrier pipe and the fuel line. | AP | 7/2/26 | ||||
| 092 | Pre-Bid | Mechanical | If a containment pipe for the fuel piping is required, can you provide a detail/section of the undergound pipe showing all required supports and fill? | Yes, per specification 23 10 00 Facility Fuel Oil Systems, section 2.5.C. | AP | 7/2/26 | ||||||
| 093 | Pre-Bid | Mechanical | The fuel pipe run from Tank to Data Center is approx. 190 feet with a 17 foot vertical drop in elevation. Based on this has a 6”/8” Sched 40 Containment pipe system may not be recommended? Are there any alternative systems that will be permitted ? (i.e. factory-engineered flexible double-wall fuel oil piping) | Section 2.5 of specification 23 10 00 indicates the spacing between the carrier pipe and the fuel line. Any alternatives must comply with specification 23 10 00. | AP | 7/2/26 | ||||||
| 094 | Pre-Bid | Mechanical | M-601 | DWGs | On Drawing sheet M-601, there is a note on the VRF schedule that indicates Spare Condenser see Remark 16. There is no Remark 16. Please confirm that Spare Condensers are not required. | The "SPARE CONDENSER SEE REMARK 16" contains a typo and the note should read "SPARE CONDENSER SEE REMARK 10." Per this note, spare condenser's will be required. | AP | 7/2/26 | ||||
| 095 | Pre-Bid | Mechanical | 115M-102 | DWGs | On Drawings 115M-102, tie ins are indicated for the existing CHW and steam pipe in the Building 111 Pipe tunnel. Are these Tie ins to be done during a System Shutdown ? or to be done as “WET/HOT TAPS” ? | Shutdown notice and window duration limits shall be coordinated with VA COR, additional requirements are provided in Division 1 Specifications. | AP | 7/2/26 | ||||
| 096 | Pre-Bid | Telecom | Please provide incumbent security systems manufacturers (PACS, VASS, Access Detection). | A/E defers to the VA for equipment manufacturer information. | JG | 7/14/26 | ||||||
| 097 | Pre-Bid | Telecom | Please provide contact information for the security maintenance contractor for the PACS, VASS, Access Detection systems. | A/E defers to the VA for security maintenance contractor contact information. | JG | 7/14/26 | ||||||
| 098 | Pre-Bid | Telecom | Are there licenses available for the additional security cameras? | A/E defers to the VA. | JG | 7/14/26 | ||||||
| 099 | Pre-Bid | Electrical | Is there a basis of design or preferred manufacturer for the engine generators (263213)? | Generator basis of design is Cummins. All other manufacturers with equal products will be reviewed. Defer to VA for preferred Generator manufacturer. | SHM | 7/1/26 | ||||||
| 100 | Pre-Bid | General | Is this project tax exempt? If so, can the certificate be provided? | A/E defers to VA Contracting for determination on tax exempt status | JG | 7/14/26 | ||||||
| 101 | Pre-Bid | Civil | CJ100, Civil General Note 6 |
Spec Section 31 20 00,
| 31 20 11 | DWGs | ||||||||||
| Specs | Sheet CJ100, Civil General Note 6 states that if surplus soil must be removed from the site, the soil shall be handled per Specification Section 31 20 11. The issued specification table of contents appears to include Section 31 20 00 Earthwork, but does not include Section 31 20 11. Please provide Section 31 20 11 or clarify the applicable specification requirements for surplus soil handling, testing, classification, hauling, disposal, and documentation. | This is a numbering error; 31 20 11 is Earthwork (Short Form) but 31 20 00 Earthwork is utilized for the spec section. | LS | 7/6/26 | 7/6/26 | ||||||
| 102 | Pre-Bid | Enviro | 02 82 11 | Specs | Specification Section 02 82 11 includes requirements for the Contractor’s Professional Industrial Hygienist / Certified Industrial Hygienist and IH Technician, including air monitoring, inspections, daily logs, and completion documentation. Please confirm whether these CPIH/CIH/IH Technician services are required to be provided by the Contractor or abatement subcontractor in addition to the asbestos contractor’s NYS DOL competent person/supervisor, or whether the competent person/supervisor may perform these functions where allowed by NYS DOL requirements. | A/E defers to VA station / Contracting for formal determination; A/E understands that VA is its own AHJ and has final determination on which local and state codes and requirements are to be followed | JG | 7/14/26 | |||
| 103 | Pre-Bid | Enviro | HA100 | DWGs | Sheet HA100, Note 2 states that the Contractor shall remove all ACM for all specified areas whether or not shown or accurately indicated, and that the specifications do not limit the Contractor’s responsibility to seek and remove all ACM. Please confirm that the abatement scope for bidding is limited to ACM/PACM materials identified in the contract documents within the indicated limits of disturbance, and that concealed or additional ACM not identified in the documents will be addressed by contract modification if encountered. | A/E concurs with this statement; the Contractor's scope shall account for ACM/PACM identified in the limits of the contract documents. In the event that ACM are encountered in areas that are not identified (unforseen conditions) abatement of said materials shall be addressed via contract modification. | JG | 7/14/26 | |||
| 104 | Pre-Bid | Enviro | 088HA101 | DWGs | |||||||
| Specs | Building 88 hazardous material documents appear inconsistent. The environmental survey sample-location sheet for Building 88 indicates no ACM identified upon PLM/QTEM analysis, while Sheet 088HA101 requires removal/disposal of ACM/PACM sheetrock, wall joint compound, and 2x2 ceiling tile, and Specification Section 02 82 11 includes estimated Building 88 abatement quantities including floor tile/mastic, ceiling tile, and drywall/joint compound. Please confirm the required asbestos/PACM abatement scope for Building 88, including whether floor tile/mastic is included. | The environmental survey was completed while the anticipated scope for this location (002A) was a TR and full renovation of this space. The scope changed after the survey was completed to a wall-mounted TE reflected in the contract drawings. There will be limited abatement activities to account for the reduced scope of work associated with the demolition activities scheduled for the wall-mounted TE. | JG | 7/14/26 | |||||||
| 105 | Pre-Bid | Structural | 115-S-200 | DWGs | Sheet 115-S-200 identifies a prefabricated ramp and notes that foundation and pier requirements are to be coordinated with the final selection of the ramp manufacturer. Please provide the basis-of-design manufacturer/model for the prefabricated ramp system, or confirm the minimum performance, material, finish, loading, railing/handrail, post-spacing, foundation/pier, and delegated-design requirements to be used for bidding. | Ramp shall be a galvanized steel premanufactured ramp with 3'-6" guardrail designed for a concentrated live load of 200lb in any direction or a distributed load for 50plf in any direction. The ramp structure itself shall have capacity to support its self-weight as well as 100 psf live load and a concentrated load of 300lb. | ARL | 7/5/26 | |||
| 106 | Pre-Bid | Structural |
Mechanical
| Civil | Page 7 | Geotechnical Report | The Geotechnical Report, page 7, indicates that groundwater/perched water was encountered in the borings and further states that, for bidding purposes, the Contractor should assume groundwater at a depth of 5' or shallower , with dewatering sufficient to maintain groundwater at least 2 feet below the bottom of excavation. The structural drawings/general notes do not appear to identify a specific dewatering system or groundwater elevation basis for the Building 115 Data Center excavation. Please confirm the required dewatering basis of bid for the Building 115 Data Center excavation, including whether bidders are to assume groundwater at existing ground surface for the duration of excavation/foundation work, and whether engineered dewatering, monitoring, discharge treatment/permitting, standby equipment, and 24-hour operation are required to be included. | Groundwater level and dewatering requirements should follow the recommendations in the geotechnical report. | ARL | 7/5/26 |
| 107 | Pre-Bid | Structural |
Mechanical
| Civil | Page 10 | Geotechnical Report | The Geotechnical Report, page 10, states that required excavations for the proposed Data Center will likely require an earth retention system and that excavation support systems are to be designed by a New York licensed professional engineer. The contract drawings do not appear to show a specific shoring, sheeting, or earth-retention system for the Building 115 Data Center excavation. Please confirm whether temporary excavation support/shoring/sheeting for the Building 115 Data Center is required to be included as a Contractor-designed means-and-methods item, and whether any restrictions apply due to adjacent existing buildings, tunnel/corridor construction, utilities, pavements, or VA operations. | Sheeting and shoring is a means and methods item, but is likely required due to the grade changes on the site. Existing adjacent footings have been indicated on the structural drawings to the best of EOR's ability. Sheeting/shoring shall be designed so that stability of existing building foundations is not affected. | ARL | 7/5/26 | |||||||
| 108 | Pre-Bid | Electrical | 26 32 13 | Specs | Specification Section 26 32 13 states that the rated power of the generator is stated on the drawings. The new generator being installed for the MCR/Data Center does not appear to have its rated power indicated on the drawing sheets. Please specify the required generator power rating, voltage, phase, fuel type, standby/prime rating basis, and any required load-bank or paralleling provisions. | Generator nameplate ratings are shown on Sheet 115EP601, 115EP701, and Specification 26 32 13. | SHM | 7/6/26 | |||||
| 109 | Pre-Bid | Architectural | Please clarify the type of fire extinguisher to be installed in the semi-recessed fire extinguisher cabinets, including extinguisher class, rating, size/capacity, and whether clean-agent/CO2 extinguishers are required in any IT, electrical, generator, or Data Center spaces. | AE clarifies that fire extinguisher to be 2A:10B:C and dry chemical extinguishers are not permitted | NE | 7/9/26 | 7/9/26 | ||||||
| 110 | Pre-Bid | Technology | 009-TN102 | DWGs | Sheet 009-TN102 shows two 12-strand OS2 / 24-strand OM4 fiber cables, B-side, coming from the ISP Demarc at Building 9 I.R.M. Server Room 224. Detail D6/TN500, Fiber Optic Backbone – Leg B, shows fiber to demarc for ISP extension as 24 OS2 SM / 24 OM4. Please clarify the required fiber count, fiber type, number of cables, terminations, and routing for the Building 9 ISP demarc extension. | "Drawing already been revised> Building 9 I.R.M requires (1) 12 strand OS2 SM (1) 24 strand OM4 MM" | IMEG - AS | 46216 | 46216 | ||||
| 111 | Pre-Bid | Telecom | 01 00 00, | ||||||||||
| 009-TN102 / TN 500 | Specs, DWGS | Specification Section 01 00 00, Phasing, references a 288-strand umbilical cable between the existing and new MCRs. Sheet 009-TN102 / TN500 appears to show one 12-strand OS2 / 24-strand OM4 cable from Building 9 I.R.M. Room 224 for each Core A / Core B switch. Please clarify whether the Contractor is required to furnish, install, terminate, test, and certify a 288-strand umbilical cable between Building 9 I.R.M. Room 224 and the new Building 115 Data Center/MCR. If required, provide the exact cable type, strand count by fiber type, pathway/routing, termination hardware, rack/cabinet locations, patch panel quantities, whether the cable is temporary or permanent, and whether this is separate from the 12-strand fiber cables shown on the TN plans. | Recently updated guidance from the VA states that in place of the 288 strand fiber optic cable from the old MCR to the new MCR, should be a 96 strand OS2 to support connectivity between the A and B core routers during relocation. The design for Building 9 room 224 is also reduced to a 96 strand OM4 as long as the maximum fiber optic cable length does not exceed 1,312 linear feet. If it exceeds that then it must be replaced with an OS2 of the same strand count. These fiber optic cables will terminate in the new MCR in the MDA a and B cabinets and in the IRM room and old MCR where the existing core routes reside. | KG | 7/6/26 | ||||||||
| 112 | Pre-Bid | Telecom | 115-ET100 |
115-ET101
| 015E-ET400 | DWGs | Drawings 115-ET100, 115-ET101, and 015E-ET400 show access control devices, but do not show associated access control panels/controllers. Please clarify where the access control devices shown on these drawings are to be connected. If devices are intended to connect to existing access control panels/controllers, please identify the existing panel/controller locations and confirm available capacity. If new panels/controllers are required, please provide the required quantity, locations, and routing requirements. | Sheet 115ET101 Shows a call out for a PACS Control Panel between grid lines 2 and grid line A. This must be a new control panel with capacity equal to the shown controlled doors including the controlled door in the Generator Building on sheet 115ET100. | KG | 7/6/26 | ||
| 113 | Pre-Bid | Structural | CU101 |
CU112
115AE301
| 115AE302 | DWGs | Architectural sections 115AE301/115AE302 show drain tile at the Building 115 below-grade foundation / connector walkway conditions, while CU101 appears to show storm drainage but does not appear to show footing drain plan layout, limits, invert elevations, cleanouts, or discharge connection. Please clarify the required footing drain / drain tile system for Building 115, including plan extent, whether it is required continuously around below-grade walls and connector walkway walls, pipe size/material, slope, cleanouts, filter fabric/free-draining backfill requirements, invert elevations, and whether the drain tile discharges to the storm system shown on CU101/CU112, to the sump pit, to daylight, or to another location. | Drainage at footings for building 115 not required structurally. | ARL | 7/6/26 | ||||||
| 114 | Pre-Bid | Telecom | 00-TN000 | DWGs | Sheet 00-TN000, Technology Installation Notes, Note 2 states: “This contractor to provide full time RCDD supervision for all Division 27 work.” Please clarify whether the RCDD is required to be physically present onsite whenever Division 27 work is being performed, or whether full-time project supervision by an assigned RCDD, including submittal review, coordination, field inspections, testing oversight, and closeout review, is acceptable. Please also confirm whether the RCDD must be directly employed by the Division 27 contractor or may be provided by a qualified subcontractor/consultant. | Clarification, AN RCDD is only required to be supervising all Division 27 activities and to assure that all work is being done according to the BICSI TDMM (latest Edition) standards and best practicies. The RCDD is expected to be in a supervisory position directing the work and activities of the installation team during the project. | KG | 7/6/26 | |||
| 115 | Pre-Bid | Structural | 115AE301 | DWGs | Sheet 115AE301 shows Building 115 Level 00 at -14'-0", foundation elevation at -16'-0", and sump pit at -18'-5", with below-grade walls extending substantially below adjacent exterior grade. The sections identify asphalt base foundation sealer, continuous vapor barrier, drain mat, and drain tile; however, the drawings do not appear to clearly define the full extent, discharge route, or performance basis of the below-grade water-management system. Please clarify whether the Building 115 below-grade walls are designed for hydrostatic pressure, or whether the design assumes hydrostatic pressure is relieved by drainage. If drainage relief is assumed, please provide the required extent and details for waterproofing/dampproofing, drain mat, protection board, footing drain/drain tile, free-draining backfill, cleanouts, filter fabric, sump/storm/discharge connection, and any required underslab drainage. Please also confirm whether the specified asphalt base foundation sealer is intended to serve as dampproofing only, or whether a waterproofing membrane is required at below-grade walls retaining soil at Level 00/generator enclosure/transformer/corridor/connector walkway conditions. | Drainage at footings for building 115 not required structurally. | ARL | 7/6/26 | |||
| 116 | Pre-Bid | Structural | 115-S-200 | DWGs | Sheet 115-S-200 and the Building 115 sections appear to show the Data Center Level 00 / foundation condition coordinated with the existing T(E) tunnel slab/footing elevation at approximately -14'-0". Please confirm that the Data Center footing depths are intentionally set to avoid surcharge or undermining of the existing tunnel/foundation system. Please also confirm whether any stepped footing or alternate footing elevations are permitted where the existing tunnel influence does not govern, or whether the footing elevations shown are required throughout as detailed. | Footings have been set based on existing footing elevations and proposed grade elevations and are required throughout as detailed. | ARL | 7/5/26 | |||
| 117 | Pre-Bid | 26 05 41, 3.2.E.1 |
26 05 41, 3.3.B.1
This is the start of the file's text. The full file is on GovTribe.