This is a Pre-Construction Survey Report for Asbestos-Containing Materials (ACM) and Lead-Based Paints (LBP) prepared by Quality Environmental Solutions & Technologies, Inc. (QuES&T) for Spees Design Build at the VA Hudson Valley Health Care Castle Point Campus in Wappingers Falls, New York. The survey was conducted across 17 buildings (Buildings 1, 6, 7, 8, 9, 13, 15E, 16, 17, 18, 19, 20, 21, 35, 44, 88, and 111) in support of a Data Center Project and EHRM Infrastructure Upgrades construction initiative. The inspection occurred from August 31 to September 7, 2023, and September 22, 2023, with sampling and analysis performed by certified NYSDOL asbestos inspectors using Polarized Light Microscopy (PLM), PLM-NOB, and Quantitative Transmission Electron Microscopy (QTEM) methods.
The survey identified asbestos-containing materials in nine buildings, with the most prevalent findings in Buildings 7, 8, 9, 16, 17, 18, 19, and 20. Identified ACM includes rough coat plaster (1.1–2.3% chrysotile) on walls and ceilings, joint compound on sheetrock (1.1–1.3% chrysotile), floor tiles (2.1–2.3% chrysotile), and spray-on fireproofing with vermiculite (Buildings 16 and 20). Lead-based paint testing via X-Ray Fluorescence (XRF) identified LBP on various surfaces across Buildings 1, 6, 7, 8, 9, 17, 18, 19, 35, and 44, ranging from 1.3 to 20.1 mg/sq. cm on wood frames, cove base molding, plaster, and concrete. The report recommends that all identified ACM be removed by a licensed asbestos abatement contractor before construction activities commence, in compliance with Title 12 NYCRR Part 56, EPA NESHAP standards, and OSHA regulations. Additionally, workers performing disturbance of any lead-containing surfaces require monitoring and adherence to 29 CFR 1926.62 occupational exposure protocols.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QuES&T Quality Environmental Solutions & Technologies, Inc.
1376 Route 9, Wappingers Falls, NY 12590 Phone (845) 298-6031 Fax (845) 298-6251
NYS MWBD MBE Cert # 49952-2006 NYSUCP DBE Certified NJUCP DBE Certified www.Qualityenv.com
PRE-CONSTRUCTION SURVEY REPORT
FOR
ASBESTOS-CONTAINING MATERIALS (ACM)
LEAD-BASED PAINTS (LBP)
Prepared for:
SPEES DESIGN BUILD
23830 Pacific Highway S, Suite 203
Kent, WA 98032 at
Veteran’s Affairs Hudson Valley Health Care
Castle Point Campus Buildings’
1, 6, 7, 8, 9, 13, 15E, 16, 17, 18, 19, 20, 21, 35, 44, 88, 111.
41 Castle Point Road
Wappingers Falls, NY 12590
QuES&T Project #23-5590 http://www.qualityenv.com/
December 7, 2023
SPEES DESIGN BUILD
23830 Pacific Highway S, Suite 203
Kent, WA 98032
ATTN: Jonathan Greb
Via E-mail: jonG@speesdb.com
Re: Veteran’s Affairs Hudson Valley Health Care
Castle Point Campus
Multiple Buildings’
Pre-Construction Asbestos & Lead
QuES&T Project #23-5590
Dear Mr. Greb, Attached is the Pre-Construction Inspection Report for Asbestos-containing Materials (ACM) & Lead-
Based Paints (LBP) identified throughout areas included within the above-referenced location(s) by
Quality Environmental Solutions & Technologies, Inc. (QuES&T). The inspection included visual assessment of the location in question, and representative sampling, as required, in compliance with the requirements of all applicable federal, state, and local regulations.
The attached report summarizes the inspection protocol and inspection results for your review. QuES&T believes this report accurately reflects the material condition existing in the functional spaces at the time of our inspection.
Should you wish to discuss this matter further or require additional information concerning this submittal, please contact us at (845) 298-6031. QuES&T appreciates the opportunity to assist Spees Design Build in the environmental services area.
Sincerely, Shannon D. Talsma
Field & Technical Services
NYS/AHERA Inspector/Project Monitor Cert. #AH 23-61PEC-SHAB
NYS Mold Assessor Cert. #23-6O1D6-SHMO
Niton-Certified XRF Technician mailto:jonG@speesdb.com
TABLE OF CONTENTS
EXECUTIVE SUMMARY Page 1 - 5
1.0 INTRODUCTON Page 5
2.0 ASBESTOS SURVEY Page 6 - 9
2.1 Inspection Summary
2.2 Sample Collection & Analytical Procedures
2.3 Identified Asbestos-containing Materials (ACM)
3.0 LEAD-BASED PAINT SURVEY Page 9 - 11
3.1 Inspection Summary
3.2 Identified Lead-based Paints (LBP)
4.0 RECOMMENDATIONS Page 11 - 12
4.1 Asbestos
4.2 Lead
5.0 DISCLAIMERS Page 13
Table I Identified Asbestos-containing Materials (ACM) Page 7 - 9
Table II Identified Lead-based Paints (LBP) Page 10 - 11
Appendix A Sample Location Drawings & Asbestos Sample Results
Appendix B Asbestos Drawings
Appendix C Lead Based Paint XRF Analytical Data
Appendix D Laboratory, Company & Personnel Licenses & Certifications
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
EXECUTIVE SUMMARY
Quality Environmental Solutions & Technologies, Inc. (QuES&T) was retained by Spees Design Build to conduct a Pre-Construction Survey for the presence of Asbestos-containing Materials (ACM) & Lead-based Paints (LBP) in support of the Data Center Project, located at the VA Hudson Valley Health Care, Castle Point Campus, 41 Castle Point Road, Wappingers Falls, NY 12590.
The survey included a visual inspection/assessment for suspect hazardous material(s), as detailed above, which are likely to be affected by planned demolition/renovations/construction activities. Inspection and sampling was limited to areas/materials slated for demolition/renovation/construction.
The survey was conducted by QuES&T personnel on August 31st – September 7th, 2023 and September
22nd, 2023. Asbestos & Lead inspections and/or sampling was conducted by NYSDOL Asbestos
Inspector(s) Shannon D. Talsma (AH# 23-61PEC-SHAB). The lead survey was conducted by Niton-
Certified XRF Technician Shannon D. Talsma utilizing X-Ray Fluorescence Technology (XRF).
ASBESTOS
Laboratory analysis and/or existing sampling data indicated the following materials as Asbestos-containing Materials (greater than 1% asbestos) (Refer to Table I & Appendix A for details and locations)
Building #1
**No Asbestos-containing Materials (ACM) identified upon PLM & QTEM/PLM analysis.**
Building #6
Building #7
Second Floor, Room #209, Wall, Partition, On Pyro Bar Brick, Rough Coat Plaster: 1.1% Chrysotile
Second Floor, Room #209, Wall, Partition, On Pyro Bar Brick, Rough Coat Plaster: 1.2% Chrysotile
Third Floor, Room #317, Ceiling, Above Suspended Ceiling, Rough Coat Plaster: 1.1% Chrysotile
Third Floor, Room #317, Ceiling, Above Suspended Ceiling, Rough Coat Plaster: 1.2% Chrysotile
Building #8
First Floor, Room #108A, Above Suspend Ceiling, Ceiling, Rough Coat Plaster: 1.1% Chrysotile
First Floor, Room #108A, Wall, Partition, Behind Sheetrock, Rough Coat Plaster: 1.1% Chrysotile
First Floor, Room #108A, Wall, Partition, Behind Sheetrock, Rough Coat Plaster: 1.1% Chrysotile
Building #9
First Floor, Room #119, Wall, Partition, On Sheetrock, Joint Compound: 1.2% Chrysotile
First Floor, Room #119, Wall, Partition, On Sheetrock, Joint Compound: 1.1% Chrysotile
Second Floor, Room #211, Wall, Partition, On Sheetrock, Joint Compound: 1.2% Chrysotile
Second Floor, Room #211, Wall, Partition, On Sheetrock, Joint Compound: 1.3% Chrysotile
Third Floor, Room #309, Wall, Partition, On Sheetrock, Joint Compound: 1.2% Chrysotile
Third Floor, Room #309, Wall, Partition, On Sheetrock, Joint Compound: 1.1% Chrysotile
Third Floor, Room #309, Wall, Partition, On Sheetrock, Joint Compound: 1.1% Chrysotile
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Building #9 contd.
First Floor, Room #119, Wall, On Pyro Bar Brick, Rough Coat Plaster: 1.4% Chrysotile
First Floor, Room #119, Wall, On Pyro Bar Brick, Rough Coat Plaster: 1.3% Chrysotile
First Floor, Room #119, Above Suspended Ceiling, Ceiling, Rough Coat
Plaster: 1.2% Chrysotile
Second Floor, Room #211, Wall, On Pyro Bar Brick, Rough Coat Plaster: 1.2% Chrysotile
Second Floor, Room #211, Above Suspended Ceiling, On Cementitious Deck, Rough Coat Plaster: 1.1% Chrysotile
Second Floor, Room #211, Wall, Partition, On Pyro Bar Brick, Rough Coat
Plaster: 1.2% Chrysotile
Third Floor, Room #309, Above Suspended Ceiling, Ceiling, Rough Coat
Plaster: 1.2% Chrysotile
Building #13
Building #15E
Building #16
Basement, Room #F-008, Above Suspended Ceiling, On Metal Deck: *Vermiculite*
Building #17
Second Floor, Room #G-203, Wall, Perimeter, Rough Coat Plaster: 2.0% Chrysotile
Second Floor, Room #G-203, Wall, Perimeter, Rough Coat Plaster: 2.0% Chrysotile
Second Floor, Room #G-203, Wall, Perimeter, Rough Coat Plaster: 1.2% Chrysotile
First Floor, Room #G-107, Floor, Under Carpet Tile, 9” x 9” Floor Tile: 2.1% Chrysotile
First Floor, Room #G-107, Floor, Under Carpet Tile, 9” x 9” Floor Tile: 2.3% Chrysotile
Building #18
Basement, Room #39, Wall, Partition, Rough Coat Plaster: 1.3% Chrysotile
Basement, Room #39, Wall, Partition, Rough Coat Plaster: 1.3% Chrysotile
Second Floor, Room #D-124, Above Suspended Ceiling, Ceiling, Rough
Coat Plaster: 1.3% Chrysotile
Second Floor, Room #D-124, Above Suspended Ceiling, Ceiling, Rough
Coat Plaster: 1.3% Chrysotile
Third Floor, Room #314-C, Above Suspended Ceiling, Ceiling, Rough
Coat Plaster: 1.3% Chrysotile
Third Floor, Room #314-C, Above Suspended Ceiling, Ceiling, Rough
Coat Plaster: 1.3% Chrysotile
Third Floor, Room #314-C, Above Suspended Ceiling, Ceiling, Rough
Coat Plaster: 1.3% Chrysotile
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Building #19
First Floor, Room #C-104, Wall, Partition, Rough Coat Plaster: 1.1% Chrysotile
First Floor, Room #C-104, Wall, Partition, Rough Coat Plaster: 1.2% Chrysotile
First Floor, Room #C-104, Above Suspended Ceiling, Ceiling, On
Concrete, Rough Coat Plaster: 1.3% Chrysotile
Second Floor, Room #C-208, Above Suspended Ceiling, Ceiling, Rough Coat Plaster: 1.5% Chrysotile
Second Floor, Room #C-208, Wall, Partition, Rough Coat Plaster: 1.1% Chrysotile
Building #20
Second Floor, Room #B-205B, Above Suspended Ceiling, On
Metal Beam: *Vermiculite*
Second Floor, Room #B-205B, Above Suspended Ceiling, On
Metal Beam: *Vermiculite*
Second Floor, Room #B-205B, Above Suspended Ceiling, On
Metal Beam: *Vermiculite*
First Floor, Room #B-122, Above Suspended Ceiling, On
Metal Beam: *Vermiculite*
First Floor, Room #B-122, Above Suspended Ceiling, On
Metal Beam: *Vermiculite*
Building #21
Building #35
Building #44
Building #88
Building #111
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
LEAD
Based on review of the data generated by the Niton XLp-300A XRF Spectrum Analyzer, the following surfaces within the scope of work were identified as lead-based as defined by HUD/EPA (equal to or in excess of 1.0 milligram per square centimeter) (Refer to Table II & Appendix B for details):
Interior’s
Basement, Foundation, Wall, Brick & Mortar, White 2.5 mg/sq. cm
Basement, Foundation, Wall, Brick & Mortar, White 4.2 mg/sq. cm
Basement, Foundation, Wall, Brick & Mortar, White 2.9 mg/sq. cm
Basement, Foundation, Wall, Brick & Mortar, White 4.5 mg/sq. cm
Building #6, Garage #8
Main Level, Door, Frame, Wood, White 2.7 mg/sq. cm
Third Floor, Room #319, Window, Frame, Wood, White 14.3 mg/sq. cm
Third Floor, Room #319, Wall, Cove Base Molding, Wood, White 19.8 mg/sq. cm
Third Floor, Room #319, Door, Frame, Wood, White 13.0 mg/sq. cm
Second Floor, Room #209, Window, Frame, Wood, White 12.4 mg/sq. cm
Second Floor, Room #209, Door, Frame, Wood, White 10.1 mg/sq. cm
First Floor, Room #115, Wall, Cove Base Molding, Wood, Gray 20.1 mg/sq. cm
First Floor, Room #115, Window, Sill, Wood, White 5.1 mg/sq. cm
First Floor, Room 108A, Window, Frame, Wood, White 8.8 mg/sq. cm
Building #9
Third Floor, Room #309, Window, Frame, Wood, Tan 11.0 mg/sq. cm
Third Floor, Room #309, Window, Sill, Wood, Tan 5.7 mg/sq. cm
First Floor, Room #G-107, Ceiling, Plaster, Tan 7.4 mg/sq. cm
First Floor, Room #G-107, Above Suspended Ceiling, Wall, Plaster, Tan 2.6 mg/sq. cm
First Floor, Room #G-107, Above Suspended Ceiling, Wall, Plaster, White 2.4 mg/sq.cm
Third Floor, Room #D-314C, Wall, Upper, Plaster, White 1.9 mg/sq. cm
Third Floor, Room #D-314C, Ceiling, Plaster, Tan 4.1 mg/sq. cm
Second Floor, Room #D-214, Ceiling, Plaster, Tan 4.6 mg/sq. cm
Basement, Room #39, Wall, Plaster, White 4.0 mg/sq. cm
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Second Floor, Room #208-C, Ceiling, Plaster, Green 3.2 mg/sq. cm
First Floor, Room #35-003, Step, Concrete, Yellow 1.3 mg/sq. cm
First Floor, Room #44-101, Wall, Plaster, Tan 2.0 mg/sq. cm
It should be noted that several components tested did in fact contain minimal lead-levels below the EPA threshold level of 1.0 mg/sq. cm for classification as Lead-Based Paint (LBP) and are considered lead-containing coatings by the OSHA Regulation, “Lead Exposure in Construction” (29 CFR 1926.62).
OSHA does not recognize a minimum limit for lead concentrations in paint for the purposes of disturbance. Monitoring of workers performing demolition/cleaning/disturbance of painted surfaces shall be completed to document personnel occupational exposure. Items containing any amount of lead concentration are considered lead-containing coatings per 29 CFR 1926.62, OSHA Lead Exposure in
Construction.
1.0 INTRODUCTION:
Quality Environmental Solutions & Technologies, Inc. (QuES&T) performed a Pre-Construction Survey for the presence of Asbestos-containing Materials (ACM) & Lead-based Paint (LBP) in conformance with the requirements of all applicable federal, state, and local regulations. The survey included a visual inspection/assessment, and representative sampling of suspect hazardous materials, as required, throughout accessible interior and exterior locations to be affected by future renovations of Multiple
Buildings throughout the VA Campus.
Certified QuES&T personnel, Shannon D. Talsma conducted field inspection(s) on August 31st –
September 7th, 2023 and September 22nd, 2023. The inspection scope was established based on review of work scope drawings. Results and findings from previous surveys conducted by QuES&T were not utilized in this inspection.
QuES&T established functional spaces based either on physical barriers (i.e. walls, doors, etc.) or homogeneity of material. Within each functional space identified, a visual inspection was performed using reasonable care and judgment, to identify and assess location, quantity, friability, and/or condition, as applicable, of all accessible installed building materials observed at the affected portion of the building/structure.
Limited localized demolition of building surfaces was performed, as part of this survey, to access concealed surfaces. No disassembly of installed equipment was conducted as part of this inspection. ACM and/or LBP, concealed within structural components and equipment interiors or that is accessible only through extensive mechanical or structural demolition may not have been identified as part of this survey.
Homogenous material types were established based on appearance, color, and texture. The findings presented in this report are based upon reasonably available information and observed site conditions at the time the assessment was performed. The findings and conclusions of this report are not meant to be indicative of future conditions at the site and does not warrant against conditions that were not evident from visual observations or historical information obtained from others.
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
2.0 ASBESTOS SURVEY:
2.1 INSPECTION SUMMARY
QuES&T performed a Pre-Construction Survey, in conformance with Title 12 NYCRR Part 56-5.1, for
Spees Design Build in support of the Construction Project at VA Hudson Valley Health Care, Castle
Point Campus, 41 Castle Point Road, Wappingers Falls, NY 12590. The survey included a visual inspection / assessment for Presumed Asbestos-containing Materials (PACM) and suspect miscellaneous
Asbestos-containing Materials (ACM) throughout accessible interior and exterior locations to be affected by future renovations, as detailed above. No previous sampling data were utilized in this inspection.
Limited localized demolition of building surfaces was performed, as part of this survey, to access concealed surfaces. No disassembly of installed equipment was conducted as part of this inspection. ACM concealed within structural components and equipment interiors or that is accessible only through extensive mechanical or structural demolition may not have been identified as part of this survey. When any construction activity, such as demolition, remodeling, renovation, or repair work, reveals PACM or suspect miscellaneous ACM that has not been identified, as part of this survey, all construction activities shall cease in the affected area.
The survey included both visual inspection of accessible spaces and representative sampling of suspect building materials for ACM. Samples collected were analyzed by a laboratory approved under the New
York State Department of Health Environmental Laboratory Approval Program (NYSDOH ELAP).
Samples were analyzed in the laboratory by Polarized Light Microscopy (PLM), Polarized Light
Microscopy-NOB (PLM-NOB) and/or Quantitative Transmission Electron Microscopy (QTEM), as required. Sample collection and laboratory analysis were conducted in compliance with the requirements of Title 12 NYCRR Part 56-5.1, 29 CFR 1926.1101 and standard EPA & OSHA accepted methods.
Samples consisting of multiple layers were separated and analyzed independently in the laboratory.
2.2 SAMPLE COLLECTION & ANALYTIAL PROCEDURES
Representative bulk sampling was performed on suspect building materials for laboratory analysis using
PLM, PLM-NOB, and/or QTEM. The following is a summary of installed building materials sampled:
• Wall Materials – Brick, Mortar, Joint Compound, Sheetrock, Plaster, Mortar, Brick, Concrete, Pyro Bar Brick, Cove Base Molding, Mastic, Ceramic Wall Tile, Grout, Cementitious Block.
• Ceiling Materials – Ceiling Tile, Glue Dabs.
• Flooring Materials – Carpet Mastic, Cementitious Slab, Floor Tile, Mastic, Tar Paper Vapor
Barrier, Leveler, Linoleum Sheet Flooring, Peel and Stick Floor Tile, Ceramic Floor Tile, Grout, Mudset.
• Thermal System Insulation Materials (TSI) – Pipe Insulation.
• Miscellaneous Materials – Spray On Fireproofing, Anti Sweat Tar.
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Certified QuES&T personnel (Appendix C), Mr. Shannon D. Talsma (Cert. #AH 23-61PEC-SHAB) performed visual assessments throughout interior and exterior construction areas. A total of five hundred-thirteen (513) samples/layers of installed and accessible suspect building materials were analyzed by a laboratory approved under the NYSDOH ELAP. Two hundred forty-two (242) samples/layers were analyzed using Polarized Light Microscopy (PLM) for friable materials; one hundred fifty (150) samples/layers were analyzed using Polarized Light Microscopy (PLM-NOB) for non-friable organically bound materials; and one hundred twenty-four (124) samples/layers were analyzed by Confirmatory-
QTEM following negative-determinations using PLM-NOB protocols.
2.3 IDENTIFIED ASBESTOS-CONTAINING MATERIALS (ACM)
TABLE I: IDENTIFIED ACM
VA Hudson Valley Health Care
Castle Point Campus
Multiple Buildings
41 Castle Point Road
Wappingers Falls, NY 12590
(CONSTRUCTION AREAS)
(Refer to Appendix A for details)
KEY: ACM = Materials containing greater than 1% of asbestos;
LF = Linear Feet; SF = Square Feet; PACM = Presumed Asbestos-containing Materials;
Friable = ACM capable of being released into air, and which can be crumbled, pulverized, powdered, crushed, or exposed by hand-pressure.
Location Material Approximate
Quantity Friable? Condition
(INTERIORS)
**No Asbestos-containing Materials identified upon PLM & QTEM/PLM analysis.**
Building #6
Second Floor, Room #209, Wall, Plaster 800 SF Yes Good
Partition, On Pyro Bar Brick, Rough Coat
Third Floor, Room #317, Ceiling, Plaster 800 SF Yes Good
Above Suspended Ceiling, Rough
Coat
First Floor, Room #108A, Above Plaster 800 SF Yes Good
Suspended Ceiling, Ceiling, Rough
Coat
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Location Material Approximate
Quantity Friable? Condition
Building #9
First Floor, Room #119, Wall, Joint Compound 400 SF Yes Good
Partition, On Sheetrock
Second Floor, Room #211, Wall, Joint Compound 400 SF Yes Good
Partition, On Sheetrock
Third Floor, Room #309, Wall, Joint Compound 400 SF Yes Good
Partition, On Sheetrock
Building #13
Building #15E
Building #16
Basement, Room #F-008, Wall, Spray On Fireproofing 400 SF Yes Good
Perimeter, Above Suspended, Ceiling, On Metal Deck
Second Floor, Room #G-203, Wall, Plaster 1,000 SF Yes Good
Perimeter, Rough Coat
First Floor, Room #G-107, Floor, Floor Tile 600 SF No Good
Under Carpet Tile, 9” x 9”
Basement, Room #39, Wall, Plaster 800 SF Yes Good
Partition, Rough Coat
Second Floor, Room #D-124, Above Plaster 800 SF Yes Good
Suspended Ceiling, Ceiling, Rough
Coat
Third Floor, Room #314-C, Plaster 800 SF Yes Good
Above Suspended Ceiling, Ceiling, Rough Coat
First Floor, Room #C-104, Wall, Plaster 800 SF Yes Good
Partition, Rough Coat
Second Foor, Room #C-208, Plaster 800 SF Yes Good
Above Suspended Ceiling, Ceiling, Rough Coat
Building #20
Second Floor, #B-205B, Above Spray On Fireproofing 200 SF Yes Good
Suspended Ceiling, On Metal *Vermiculite*
Beam
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Location Material Approximate
Quantity Friable? Condition
First Floor, #B-122, Above Spray On Fireproofing 200 SF Yes Good
Suspended Ceiling, On Metal *Vermiculite*
Beam
Building #21
Building #88
Building #111
3.0 LEAD SURVEY:
3.1 INSPECTION SUMMARY
QuES&T conducted a Limited Pre-Construction Lead Survey, utilizing X-Ray Fluorescence Technology
(XRF), throughout specific interior and exterior areas of the VA Hudson Valley Health Care, Castle Point
Campus, Building #1, located at 41 Castle Point Road, Wappingers Falls, NY 12590 in support of the
Spees Design Build Construction Project. The survey was limited to specific accessible, representative building components & immovable objects, potentially affected by scheduled renovation/construction activities.
Niton-certified XRF Technician(s) Shannon D. Talsma of QuES&T, collected a total of one hundred seventy-four (174) samples (including calibrations) on August 31st – September 7th, 2023 and September
22nd, 2023.
3.2 IDENTIFIED LEAD-BASED PAINT(S) (LBP)
Based on review of the data generated by the Niton XLp-300A XRF Spectrum Analyzer, the following surfaces tested were identified as lead-based as defined by HUD/EPA (equal to or in excess of 1.0 milligram per square centimeter):
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
TABLE II: IDENTIFIED LEAD-BASED PAINT
VA Hudson Valley Health Care
Castle Point Campus
Multiple Buildings
41 Castle Point Road
Wappingers Falls, NY 12590
(CONSTRUCTION AREAS)
Location
LBP
Component Substrate Color LBP Condition Approximate Quantity
Building #1, Basement Wall Brick & Mortar White Intact 2000 SF
Building #6, Garage #8, Main Level Door, Frame Wood White Fair 10 SF
Building #7, Third Floor, Room #319 Window, Frame Wood White Intact 6 SF
Building #7, Third Floor, Room #319
Cove Base
Molding Wood White Intact 10 SF
Building #7, Third Floor, Room #319 Door, Frame Wood White Intact 6 SF
Building #7, Second
Floor, Room #209 Window, Frame Wood White Intact 6 SF
Building #7, Second
Floor, Room #209 Door, Frame Wood White Intact 6 SF
Building #7, First Floor, Room #115
Wall, Cove Base
Molding Wood Gray Intact 10 SF
Building #7, First Floor, Room #115 Window, Sill Wood White Intact 2 SF
Building #8, First Floor, Room #108A Window, Frame Wood White Intact 6 SF
Building #9, Third Floor, Room #309 Window, Frame Wood Tan Intact 6 SF
Building #9, Third Floor, Room #309 Window, Sill Wood Tan Intact 2 SF
Building #17, First Floor, Room #G-107 Ceiling Plaster Tan Fair 400 SF
Building #17, First Floor, Room #G-107
Above
Suspended
Ceiling, Wall
Plaster Tan Fair 800 SF
Building #17, Room #G-
Above
Suspended
Ceiling, Wall
Plaster White Intact 800 SF
Building #18, Third
Floor, Room #D-314C Wall, Upper Plaster White Intact 800 SF
Building #18, Third
Floor, Room #D-314C Ceiling Plaster Tan Intact 400 SF
Building #18, Second
Floor, Room #D-214 Ceiling Plaster Tan Fair 400 SF
Building #18, Basement, Room #39 Wall Plaster White Intact 800 SF
Building #19, Second
Floor, Room #208-C Ceiling Plaster Green Fair 400 SF
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Location
LBP
Component Substrate Color LBP Condition Approximate Quantity
Building #35, Room
#35-003 Step Concrete Yellow Intact 4 SF
Building #44, First Floor, Room #44-101 Wall Plaster Tan Intact 400 SF
It should be noted that several components tested did in fact contain minimal lead-levels below the EPA threshold level of 1.0 mg/sq. cm for classification as Lead-Based Paint (LBP) and are considered lead-containing coatings by the OSHA Regulation, “Lead Exposure in Construction” (29 CFR 1926.62).
OSHA does not recognize a minimum limit for lead concentrations in paint for the purposes of disturbance. Monitoring of workers performing demolition/cleaning/disturbance of painted surfaces shall be completed to document personnel occupational exposure. Items containing any amount of lead
4.0 RECOMMENDATIONS:
4.1 ASBESTOS
All construction personnel as well as individuals who have access to locations where asbestos containing materials (ACM) exists should be informed of its presence and the proper work practices in these areas.
Conspicuous labeling of all ACM is suggested to ensure personnel is adequately informed. Personnel should be informed not to rest, lean or store material or equipment on or near these surfaces and not to cut, saw, drill, sand or disturb ACM. All removal, disturbance, and repair of ACM should be performed in compliance with Title 12 NYCRR Part 56 by persons properly trained to handle ACM. Facility custodial and maintenance personnel should receive training commensurate with their work activities; as defined in
29 CFR 1910.1001.
As specified in Title 12 NYCRR Part 56-5.1 (h) and (i), "If the building/structure asbestos survey finds that the portion of the building/structure to be demolished, renovated, remodeled, or have repair work contains ACM, PACM, suspect miscellaneous ACM assumed to be ACM, or asbestos material, which is impacted by the work, the owner or the owner’s agent shall conduct, or cause to have conducted, asbestos removal performed by a licensed asbestos abatement contractor in conformance with all standards set forth in this Part. All ACM, PACM, suspect miscellaneous ACM assumed to be ACM, or asbestos material impacted by the demolition, renovation, remodeling, or repair project shall be removed as per this Part, prior to access or disturbance by other uncertified trades or personnel. No demolition, renovation, remodeling or repair work shall be commenced by any owner or the owner’s agent prior to the completion of the asbestos abatement in accordance with the notification requirements of this Part…All building/structure owners and asbestos abatement contractors on a demolition, renovation, remodeling, or repair project, which includes work covered by this part, shall inform all trades on the work site about
PACM, ACM, asbestos material and suspect miscellaneous ACM…Bids may be advertised and contracts awarded for demolition, remodeling, renovation, or repair work, but no work on the current intermediate portion of the project shall commence on the demolition, renovation, remodeling or repair work by any owner or agent prior to completion of all necessary asbestos abatement work for the current intermediate portion of the entire project, in conformance with all standards set forth in this Part.”
Prior to conducting demolition or construction work at the building, all ACM affected/impacted by such activities shall be removed utilizing a licensed asbestos abatement contractor and NYSDOL/EPA/NYC certified personnel prior to construction/demolition activities. All work conducted should be in accordance with all legal requirements, including but not limited to U.S. Environmental Protection
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
Agency (EPA) National Emissions Standards for Hazardous Air Pollutants (NESHAP) [40 CFR Part 61], New York State Industrial Code Rule 56 Asbestos Regulations (ICR 56) and Chapter 1 of Title 15 of the
Rules of the City of New York Regulations, as applicable. Advance notification of the asbestos project to the USEPA, NYSDOL, and NYCDEP may be required.
All suspect building materials not sampled during this survey should be considered ACM until these materials are sampled and analyzed for ACM in the laboratory. Concealed ACM: In addition to the
ACMs identified at the site, there is a possibility that concealed ACM may exist at the subject facility. As such, if any concealed suspect ACM is encountered during future construction related activities, the work should immediately stop. Prior to resuming the work, the suspect ACM should either be 1) Sampled by an appropriately certified asbestos professional and submitted to an Approved NYSDOH ELAP laboratory for asbestos analysis or 2) Presumed to be ACM (PACM) and removed by a licensed asbestos abatement contractor for disposal in accordance with all applicable regulations.
4.2 LEAD
In addition to any identified Lead-based Paints (LBP), several components tested did in fact contain minimal lead-levels below the EPA threshold level of 1.0 mg/sq. cm for classification as LBP and are considered lead-containing coatings by the OSHA Regulation, “Lead Exposure in Construction” (29 CFR
1926.62). OSHA does not recognize a minimum limit for lead concentrations in paint for the purposes of disturbance. Monitoring of workers performing demolition/cleaning/disturbance of painted surfaces shall be completed to document personnel occupational exposure. Items containing any amount of lead
Activities involving the disturbance of LBP in homes, child-occupied facilities, and/or pre-schools built before 1978 must follow the requirements outlined by EPA regulations (40 CFR 745).
In areas where demolition and/or renovations are to occur and lead is present, the demolition debris waste stream should be further analyzed during segregation for compliance with EPA regulations to ensure proper disposal. TCLP testing can be performed prior to waste segregation, but results may not be indicative of the actual waste streams produced during demolition.
Pre-Construction Environmental Survey SPEES DESIGN BUILD
QuES&T Project #23-5590 @VA Hudson Valley Health Care, Multiple Buildings
ENVIRONMENTAL CONSULTING & TRAINING
5.0 DISCLAIMERS
The findings presented in this report are based upon reasonably available information and observed site conditions at the time the assessment was performed. Conditions may have changed since that time and the findings and conclusions of this report are not meant to be indicative of future conditions at the Site.
This report does not warrant against conditions that were not evident from visual observations or historical information obtained, or conditions that could only be determined by physical sampling or other intrusive investigation techniques that are outside the proposed scope of work.
It should be noted that the information contained within this report is based solely upon site observations and the results of laboratory analysis for samples collected by QuES&T. These observations and results are time dependent, subject to changing site conditions and revisions to Federal, State and Local regulations. QuES&T warrants that these findings have been promulgated after being prepared in general accordance with generally accepted practices in the abatement industries. QuES&T also recognizes that inspection laboratory data is not usually sufficient to make all abatement and management decisions.
Due to the potential for concealed Asbestos-containing Materials (ACM) or other regulated materials, this report should not be construed to represent all ACM or regulated materials within the site(s). All quantities of ACM or other regulated materials identified, and all dimensions listed within this report are approximate and should be verified On-site.
This inspection report is not intended to be used as the sole basis for soliciting pricing for regulated materials abatement. An abatement plan, specification, drawing and/or Variances should be developed to identify scope, timing, phasing, and remediation means & methods for any asbestos project. The Linear and/or Square Footages (LF / SF) listed within this Report are only approximates. Abatement
Contractor(s) are required to visit the building(s) in order to take actual field measurements within each listed location.
Appendix A:
SAMPLE LOCATION DRAWINGS &
ASBESTOS SAMPLE RESULTS
Quality Environmental Solutions & Technologies, Inc.
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 00G
LOBBY 101 & RM 102
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 1 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
Sample Location (ACM)
02, 0401, 03
07, 08, 09
No Asbestos-containing Materials (ACM) identified uponPLM & QTEM/PLM analysis
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/26/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 01
GARAGE #8
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building #6 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/26/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 01
ROOM 115
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 7 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location
01, 03, 05, 07
02, 04, 06
09, 12
10, 13
16, 21
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-02
Issued For:
Asbestos Survey
Version #
LEVEL 02
ROOM 209
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 7 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
17, 23, 27
18, 22, 26
28, 29
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-03
Issued For:
Asbestos Survey
Version #
LEVEL 03
ROOM 317
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 7 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
19, 24
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-00
Issued For:
Asbestos Survey
Version #
LEVEL 00
ROOM 05B
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 8 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
B05
15, 17
16, 1820 19
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 1
ROOM 108A
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 8 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
108A
0102, 04
03, 05
07, 09
08, 10
06, 11
23, 25
24, 26
27 28
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/25/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 1
ROOM 119
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 9 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
01, 08
10, 20, 11, 21, 12, 17
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-02
Issued For:
Asbestos Survey
Version #
LEVEL 2
ROOM 211
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 9 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location
14, 15, 18, 22
26, 28, 32
27, 29, 33
13, 23
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-03
Issued For:
Asbestos Survey
Version #
LEVEL 3
ROOM 309A
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 9 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
309A
01, 09
0316, 19
39 34, 35
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-00
Issued For:
Asbestos Survey
Version #
LEVEL 00
ROOM 01
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building #13 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
01 02, 04
03, 05
06, 08, 10, 12
07, 09, 11, 13
No Asbestos-containing Materials (ACM) identified uponPLM & QTEM/PLM analysis
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-00
Issued For:
Asbestos Survey
Version #
LEVEL 00
ROOM 011A
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 15E 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
011A
02, 04
03, 05
07, 10
06, 09
08, 11
12, 14, 13, 15, No Asbestos-containing Materials (ACM) identified uponPLM & QTEM/PLM analysis
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-00
Issued For:
Asbestos Survey
Version #
LEVEL 00
ROOM F-008
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 16 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
F-008
01, 05
02, 04
06, 07, 15, 16
08, 19, 10, 12, 14
21, 22
09, 11, 13
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-00
Issued For:
Asbestos Survey
Version #
LEVEL 00
ROOM G-014
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 17 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
G - 014
09, 13
10, 14
11, 15
32, 44
33, 45
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 1
ROOM 107
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 17 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
06, 16
12, 17
30, 34, 36
31, 35, 37
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-02
Issued For:
Asbestos Survey
Version #
LEVEL 2
ROOM G203
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 17 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
02, 04
03, 05
08, 19
20, 22, 24, 28, 21, 23, 25, 29, 42, 43
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-00
Issued For:
Asbestos Survey
Version #
LEVEL 00
ROOM 39
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 18 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location
04, 09 05, 10
11, 18
12, 19
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 1
ROOM 115
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 18 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
Room 115
01, 07
03, 08
41, 43, 45, 47
42, 44, 46, 48
51, 52
57, 58
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-02
Issued For:
Asbestos Survey
Version #
LEVEL 3
ROOM 314C
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 18 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
314C
16, 17, 23, 24
26, 28, 32, 34, 36, 38
15, 22
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 1
ROOM C104
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 19 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
C104
02, 07
13, 14
15, 16
01, 06, 12
03, 08
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-02
Issued For:
Asbestos Survey
Version #
LEVEL 2
ROOM 208
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 19 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
04, 09 05, 10, 11
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 1
ROOM 122
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 20 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Location (Non-ACM)
01, 06
11, 12 17, 18
13, 15
14, 16
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-01
Issued For:
Asbestos Survey
Version #
LEVEL 01
ROOM 142A
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 21 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement. An abatement plan, specification, drawing and/or variances should be developed to identify scope, timing, phasing and remediation means & methods for any asbestos project.
SAMPLE LOCATION KEY
Sample Locations
08, 09, 10
13, 15, 16, 17, 18, 20
01, 06, 23, 142A
1376 Route 9 Wappingers Falls, NY 12590
Phone: (845) 298- 6031 Fax: (845) 298-6251
Prepared By:
DS
QuES&T Project #:
23-5590
Date:
9/19/2023
SL-02
Issued For:
Asbestos Survey
Version #
LEVEL 02
ROOM A-203
SAMPLE LOCATIONS
Spees Design Build 23830 Pacific Highway S, Suite 203, Kent, WA 98032
Building 21 41 Castle Point Road, Wappingers Falls, NY 12590
Project Manager:
LJH
CLIENT
PROJECT LOCATION
**Drawing Not to Scale** This Drawing is not intended to be used as the sole basis for soliciting pricing for asbestos abatement.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .