Revised Sec_L_-_Exhibit_B1_-_B7_UEWR-Test_Pricing_Exhibits_with_Labor_Cats_05.17.12.xlsx
XLSX spreadsheet 211 KB Posted
- Solicitation number
- HQ0147-11-R-0006
- Issued by
-
DOD Missile Defense Agency
About this file
Revised Exhibits B1 through B7
View the file
Other files
Show 40 more
Latest 50 of 79 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FBLR Exhibit B1
| Exhibit B1: Fully Burdened Labor Rate (FBLR) |
| PRIME/SUBCONTRACTOR |
| CONTRACTOR/SUBCONTRACTOR: __________________________________________ |
| Prime & Major-Sub Contractor Labor Category to RFP Labor Category Crosswalk | Fringe Benefits | Overhead | G&A Base | G&A | FBLR Labor Rate Through G&A | * Fee/Profit for Subcontractors Only | 12-Month Period 1 FBLR including sub fee | ||||
| %age of E | %age of E | (E)+(F)+(G) | %age of H | (H) + (I) | % of J | (J) + (K) | |||||
| Insert Fringe Rate ** ▼ | Insert Govt-Site Overhead Rate ** ▼ | Insert G&A Rate ** ▼ | Insert Profit Factor ** ▼ | ||||||||
| RFP Labor Category | Contractor Labor Category | % of total Labor Category | Contractor Labor Category Direct Labor Rates | Prime or Major Sub Direct Labor Rate | 20.0% | 15.0% | 10.0% | 0.0% | |||
| Example (Please Delete in Proposal) |
campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee
| Chief Bottle Washer | 1st Class Bottle Washer | 50% | $ 24.00 | $ 21.36 | $ 4.27 | $ 3.20 | $ 28.84 | $ 2.88 | $ 31.72 | $ - 0 | $ 31.72 |
| Container Cleaner III | 25% | $ 18.95 | |||||||||
| Jug Washer | 25% | $ 18.50 |
| Program Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Deputy Program Manager/Chief Engineer | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Scientist | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Senior Engineer | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Engineer III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Engineer II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Engineer I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician IV | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Administrator | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Administrative Support II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Administrative Support I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other (define) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| * Prime Fee is included on the CLIN Pricing Exhibit | |
| NOTE: The Indirect rate structure on this Exhibit is notional. Offerors must tailor this Exhibit to match their unique rate structure and cost accounting system. | |
| Fully Burdened Labor Rate (FBLR) Exhibit B1 | |
| CONTRACTOR/SUBCONTRACTOR: __________________________________________ | CFY 2 |
| Prime & Major-Sub Contractor Labor Category to RFP Labor Category Crosswalk | Fringe Benefits | Overhead | G&A Base | G&A | FBLR Labor Rate Through G&A | * Fee/Profit for Subcontractors Only | 12-Month Period 2 FBLR including sub fee | ||||
| %age of E | %age of E | (E)+(F)+(G) | %age of H | (H) + (I) | % of J | (J) + (K) | |||||
| Insert Fringe Rate ** ▼ | Insert Govt-Site Overhead Rate ** ▼ | Insert G&A Rate ** ▼ | Insert Profit Factor ** ▼ | ||||||||
| RFP Labor Category | Contractor Labor Category | % of total Labor Category | Contractor Labor Category Direct Labor Rates | Prime or Major Sub Direct Labor Rate | 20.0% | 15.0% | 10.0% | 0.0% | |||
| Example (Please Delete in Proposal) |
campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee
| Chief Bottle Washer | 1st Class Bottle Washer | 50% | $ 24.72 | $ 22.00 | $ 4.40 | $ 3.30 | $ 29.70 | $ 2.97 | $ 32.68 | $ - 0 | $ 32.68 |
| Container Cleaner III | 25% | $ 19.52 | |||||||||
| Jug Washer | 25% | $ 19.06 |
| Program Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Deputy Program Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Scientist | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Senior Engineer | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Engineer III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Engineer II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Engineer I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Administrator | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician IV | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Technician I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Administrative Support II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Administrative Support I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert III | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert II | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert I | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other (define) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| * Prime Fee is included on the CLIN Pricing Exhibit | ||||||||
| NOTE: The Indirect rate structure on this Exhibit is notional. Offerors must tailor this Exhibit to match their unique rate structure and cost accounting system. |
&"Times New Roman,Italic"&11HQ0147-11-R-0006 Exhibit B-1
Minor Subs FBLR Exhibit B2
| Exhibit B2: Minor Subcontractor Fully Burdened Labor Rates (FBLR) |
| Prime Contractor: |
| Minor Subcontractor | RFP Labor Category | 12-Month | 12-Month | 12-Month | 12-Month | 12-Month |
| Period | Period | Period | Period | Period | ||
| Examples: | 1 | 2 | 3 | 4 | 5 | |
| Consulting Inc. | Database Development Specialist III | $ 86.02 | $ 87.74 | $ 89.50 | $ 91.29 | $ 93.11 |
| Software Development Specialist III | $ 64.52 | $ 65.81 | $ 67.13 | $ 68.47 | $ 69.84 |
| Very High Tech Incorporated | Engineer / Scientist / Technical Analyst IV | $ 85.00 | $ 86.70 | $ 88.43 | $ 90.20 | $ 92.01 |
| Engineer / Scientist / Technical Analyst III | $ 56.00 | $ 57.12 | $ 58.26 | $ 59.43 | $ 60.62 | |
| Chief Bottle Washer | $ 45.00 | $ 45.90 | $ 46.82 | $ 47.75 | $ 48.71 |
HQ0147-11-R-0006
Exhibit B-2
Composite Team FBLR B3
| Exhibit B3: Prime's Composite (Team) Fully Burdened Labor Rate (FBLR) | (Prime only) |
| Prime Contractor: |
| 12-Month Period 3 Loaded Labor Rate including sub fee | 12-Month Period 4 Loaded Labor Rate including sub fee | 12-Month Period 5 Loaded Labor Rate including sub fee | ||||||||||
| 12-Month Period 1 | 12-Month Period 2 | % Period 2 | % Period 3 | % Period 4 | ||||||||
| RFP Labor Category | Staffing approach for each Proposed Labor Category | FBLR From Exhibit B1 or B2 | Prime Burden on Sub Labor if applicable | Prime & Subs Per Hour Labor Cost | Composite Cost Per Hour | FBLR From Exhibit B1 or B2 | Prime Burden on Sub Labor if applicable | Prime's Per Hour Labor Cost | Composite Cost Per Hour | Insert Escalaution Factor ** ▼ | Insert Escalaution Factor ** ▼ | Insert Escalaution Factor ** ▼ |
| 1% | 1% | 2.0% | 2.0% | 2.0% | ||||||||
| Example (Please Delete in Proposal) |
campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirect rates, and Fee
| Chief Bottle Washer | SB Prime Inc. | 50% | $ 31.72 | $ 31.72 | $ 34.65 | $ 32.68 | $ 32.68 | $ 35.88 | $ 36.60 | $ 37.33 | $ 38.08 | ||
| XYZ Corp. | 30% | $ 32.00 | $ 0.32 | $ 32.32 | $ 33.29 | $ 0.33 | $ 33.62 | ||||||
| Very High Tech Incorporated | 20% | $ 45.00 | $ 0.45 | $ 45.45 | $ 46.81 | $ 0.47 | $ 47.28 |
| Program Manager | $ - 0 | $ - 0 | $ - 0 |
| Deputy Program Manager/Chief Engineer | $ - 0 | $ - 0 | $ - 0 |
| Scientist | $ - 0 | $ - 0 | $ - 0 |
| Senior Engineer | $ - 0 | $ - 0 | $ - 0 |
| Engineer III | $ - 0 | $ - 0 | $ - 0 |
| Engineer II | $ - 0 | $ - 0 | $ - 0 |
| Engineer I | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst III | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst II | $ - 0 | $ - 0 | $ - 0 |
| Program Analyst I | $ - 0 | $ - 0 | $ - 0 |
| Technician IV | $ - 0 | $ - 0 | $ - 0 |
| Technician III | $ - 0 | $ - 0 | $ - 0 |
| Technician II | $ - 0 | $ - 0 | $ - 0 |
| Technician I | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator III | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator II | $ - 0 | $ - 0 | $ - 0 |
| Computer Operator I | $ - 0 | $ - 0 | $ - 0 |
| Security Manager | $ - 0 | $ - 0 | $ - 0 |
| Security Administrator | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant III | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant II | $ - 0 | $ - 0 | $ - 0 |
| Security Assistant I | $ - 0 | $ - 0 | $ - 0 |
| Administrative Support II | $ - 0 | $ - 0 | $ - 0 |
| Administrative Support I | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert III | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert II | $ - 0 | $ - 0 | $ - 0 |
| Subject Matter Expert I | $ - 0 | $ - 0 | $ - 0 |
| Other (define) | $ - 0 | $ - 0 | $ - 0 |
NOTE: The Indirect rate structure on this Exhibit is notional (a single prime burden on Subcontracts Labor dollars) . Offerors must tailor this Exhibit to match their unique rate structure and cost accounting system.
&"Times New Roman,Italic"&11HQ0147-11-R-0006 Section J, Exhibit B3 Composite Team FBLR Page &P of &N
CLIN Pricing Exhibit B4
| Task Order 0001 CLINS | |||||||||||
| Contract Type => | FPI | FPI | FPI | FPI | FFP | FPI/FFP | |||||
| Contract Labor Categories | 0001 | 0002 | 0004 | 0005 | 0012 | Task Order 0001 Totals | 12-Month Period 2 | 12-Month Period 3 | 12-Month Period 4 | 12-Month Period 5 | Totals |
| Chief Bottle Washer |
campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee 250 250 250 250 250 1,250 1,250 1,250 1,250 1,250 6,250
| Proposed DPLH | Program Manager | - 0 |
| Deputy Program Manager/Chief Engineer | - 0 | |
| Scientist | - 0 | |
| Senior Engineer | - 0 | |
| Engineer III | - 0 | |
| Engineer II | - 0 | |
| Engineer I | - 0 | |
| Program Analyst III | - 0 | |
| Program Analyst II | - 0 | |
| Program Analyst I | - 0 | |
| Technician IV | - 0 | |
| Technician III | - 0 | |
| Technician II | - 0 | |
| Technician I | - 0 | |
| Computer Operator III | - 0 | |
| Computer Operator II | - 0 | |
| Computer Operator I | - 0 | |
| Security Manager | - 0 | |
| Security Administrator | - 0 | |
| Security Assistant III | - 0 | |
| Security Assistant II | - 0 | |
| Security Assistant I | - 0 | |
| Administrative Support II | - 0 | |
| Administrative Support I | - 0 | |
| Subject Matter Expert III | - 0 | |
| Subject Matter Expert II | - 0 | |
| Subject Matter Expert I | - 0 | |
| Other (define) | - 0 |
| Total Hours | 250 | 250 | 250 | 250 | 250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 6,250 |
| CONTRACT FBLRs | |||||||||||
| Chief Bottle Washer | $ 34.65 | $ 34.65 | $ 34.65 | $ 34.65 | $ 34.65 | $ 34.65 | $ 35.90 | $ 37.15 | $ 38.40 | $ 39.65 |
| Proposed Yearly FBLRs | Program Manager | ||||||||||||
| Deputy Program Manager/Chief Engineer | |||||||||||||
| Scientist | |||||||||||||
| Senior Engineer | |||||||||||||
| Engineer III | |||||||||||||
| Engineer II | |||||||||||||
| Engineer I | |||||||||||||
| Program Analyst III | |||||||||||||
| Program Analyst II | |||||||||||||
| Program Analyst I | |||||||||||||
| Technician IV | |||||||||||||
| Technician III | |||||||||||||
| Technician II | |||||||||||||
| Technician I | |||||||||||||
| Computer Operator III | |||||||||||||
| Computer Operator II | |||||||||||||
| Computer Operator I | |||||||||||||
| Security Manager | |||||||||||||
| Security Administrator | |||||||||||||
| Security Assistant III | |||||||||||||
| Security Assistant II | |||||||||||||
| Security Assistant I | |||||||||||||
| Administrative Support II | |||||||||||||
| Administrative Support I | |||||||||||||
| Subject Matter Expert III | |||||||||||||
| Subject Matter Expert II | |||||||||||||
| Subject Matter Expert I | |||||||||||||
| Other (define) | |||||||||||||
| Proposed Labor Cost | |||||||||||||
| Chief Bottle Washer | $ 8,662 | $ 8,662 | $ 8,662 | $ 8,662 | $ 8,662 | $ 43,310 | $ 43,311 | $ 43,312 | $ 43,313 | $ 43,315 | 216,560 | ||
| - 0 | |||||||||||||
| Program Manager | - 0 | - 0 | |||||||||||
| Deputy Program Manager/Chief Engineer | - 0 | - 0 | |||||||||||
| Scientist | - 0 | - 0 | |||||||||||
| Senior Engineer | - 0 | - 0 | |||||||||||
| Engineer III | - 0 | - 0 | |||||||||||
| Engineer II | - 0 | - 0 | |||||||||||
| Engineer I | - 0 | - 0 | |||||||||||
| Program Analyst III | - 0 | - 0 | |||||||||||
| Program Analyst II | - 0 | - 0 | |||||||||||
| Program Analyst I | - 0 | - 0 | |||||||||||
| Technician IV | - 0 | - 0 | |||||||||||
| Technician III | - 0 | - 0 | |||||||||||
| Technician II | - 0 | - 0 | ` | ||||||||||
| Technician I | - 0 | - 0 | |||||||||||
| Computer Operator III | - 0 | - 0 | |||||||||||
| Computer Operator II | - 0 | - 0 | |||||||||||
| Computer Operator I | - 0 | - 0 | |||||||||||
| Security Manager | - 0 | - 0 | |||||||||||
| Security Administrator | - 0 | - 0 | |||||||||||
| Security Assistant III | - 0 | - 0 | |||||||||||
| Security Assistant II | - 0 | - 0 | |||||||||||
| Security Assistant I | - 0 | - 0 | |||||||||||
| Administrative Support II | - 0 | - 0 | |||||||||||
| Administrative Support I | - 0 | - 0 | |||||||||||
| Subject Matter Expert III | - 0 | - 0 | |||||||||||
| Subject Matter Expert II | - 0 | - 0 | |||||||||||
| Subject Matter Expert I | - 0 | - 0 | |||||||||||
| Other (define) | - 0 | - 0 | |||||||||||
| Totals | |||||||||||||
| Total Target Cost | 8,662 | 8,662 | 8,662 | 8,662 | 8,662 | 43,310 | 43,311 | 43,312 | 43,313 | 43,315 | 216,560 | ||
| Prime Target Profit Rate % | 5% | 5% | 5% | 5% | 5% | 5% | 5% | 5% | 5% | ||||
| Prime Profit (Task Order 001 CLIN 0012 only)$ | 433.00 | 433.00 | |||||||||||
| Target Profit $ | 433 | 433 | 433 | 433 | 1,732 | 433 | 433 | 433 | 433 | 3,465 | |||
| Totals | 9,095 | 9,095 | 9,095 | 9,095 | 8,662 | 45,475 | 43,744 | 43,745 | 43,746 | 43,748 | 220,025 |
NOTE: PLEASE REMEMBER TO REMOVE EXAMPLE FROM PROPOSAL
Section J, Exhibit B4 CLIN Pricing
Overhead Exhibit B5 Exhibit B5: Overhead or Other Indirct Rates
Company Name: [ ] Prime [ ] Major Subcontractor
Overhead or Service Center Pool = _______________ Base of Application = __________________________
* Specify Type of Overhead Burden: Labor, Onsite, Offsite, Engineering, Procurement, Service Center(s), etc.
OFFEROR'S FISCAL YEAR BEGINS ____________ AND ENDS ____________.
| Contractor | Contractor | Contractor | Contractor | Contractor | Contractor | Contractor | Contractor | |
| Cost Elements within | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year |
| the Overhead Burden Pool | Prior Yr 3 | Prior Yr 2 | Prior Yr 1 | _________ | _________ | _________ | _________ | _________ |
| Payroll Taxes |
| FICA (Fed Income Tax) |
| FUI (Federal Unemployment) |
| SUI (State Unemployment) |
| WC (Workers Comp) |
| Fringes: |
| Retirement |
| Health/Life Insurance |
| Paid Leave |
| Other |
| Other (Identify) |
| Facilities |
| Depreciation |
| Total Overhead Pool Expenses |
| Application Base ($) |
| Contractor FY Rate (%) |
HQ0147-11-R-00006
Section J, Exhibit B5 Overhead
G&A Exhibit B6
| Exhibit B6: General and Administrative Expenses | |||
| Company Name: | [ ] Prime | [ ] Major Subcontractor | |
| OFFEROR'S FISCAL YEAR BEGINS ____________ AND ENDS ____________. | |||
| Base of Application = __________________________ |
| Contractor | Contractor | Contractor | Contractor | Contractor | Contractor | Contractor | Contractor | |
| Cost Elements | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year | Fiscal Year |
| Within the G&A Expense Pool | Prior Yr 3 | Prior Yr 2 | Prior Yr 1 | _________ | _________ | _________ | _________ | _________ |
Labor: (Identify)
Labor Related Cost: (Taxes & Fringes Etc.)
| B&P |
| IR&D |
| Corporate Allocations: |
| Other (Specify): |
| Facilities |
| Depreciation |
| Total G&A Expenses |
| Distribution Base Dollars: |
| Existing Business Base |
| This Contract Base |
| Forecasted Business Base |
| Total Distribution Base $ |
| Calculated G&A Rates (%) |
Section J, Exhibit B6 G and A
Cost Format A - Exhibit B7
| COST FORMAT A - TABLE 1 | |||
| COST ELEMENT SUMMARY | |||
| Contract Phase-in | |||
| PROPOSED | |||
| COST ELEMENT | HOURS/BASE | RATE | AMOUNT |
| DIRECT LABOR | |||
| LABOR CATEGORY 1 | 1 | $ 1.00 | $ 1 |
| LABOR CATEGORY 2 | 1 | $ 1.00 | $ 1 |
| LABOR CATEGORY 3 | 1 | $ 1.00 | $ 1 |
| LABOR CATEGORY 4 | 1 | $ 1.00 | $ 1 |
| ETC. | 1 | $ 1.00 | $ 1 |
| TOTAL DIRECT LABOR | 5 | $ 5 |
| FRINGE BENEFITS | $ 5 | 1.0% | $ 0 |
| LABOR OVERHEAD | $ 5 | 1.0% | $ 0 |
| TOTAL INDIRECT LABOR EXPENSE | $ 0 |
| SUBCONTRACTS/INTERCOMPANY | |
| SUBCONTRACT 1 (See Sub CFY Cost Summaries) | $ 1 |
| SUBCONTRACT 2 (See Sub CFY Cost Summaries) | $ 1 |
| INTERCOMPANY 1 (See Attached CFY Cost Summaries) | $ 1 |
| INTERCOMPANY 2 (See Attached CFY Cost Summaries) | $ 1 |
| TOTAL SUBCONTRACTS/CONSULTANTS/INTERCOMPANY | $ 4 |
DIRECT MATERIALS (See Attached Bill of Materials) $ 1
MATERIAL OVERHEAD $ 1 1.0% $ 0
| OTHER DIRECT COSTS | |
| TRAVEL (See Attached Travel Detail) | $ 1 |
| CONSULTANT 1 | $ 1 |
| CONSULTANT 2 | $ 1 |
| ODC - List separately | $ 1 |
| ODC - List separately | $ 1 |
| TOTAL ODCS | $ 5 |
SUBTOTAL $ 15
G&A $ 15 1.00% $ 0
SUBTOTAL $ 15
| FACILITIES CAPITAL COST OF MONEY | |||
| DIRECT LABOR | $ 5 | 0.10000 | $ 1 |
| G&A | $ 15 | 0.10000 | $ 2 |
| ETC. | $ 1 | 0.10000 | $ 0 |
| TOTAL FCCM | $ 2 |
TOTAL COSTS $ 17
Profit $ 15 1.00% $ 0
TOTAL PRICE $ 18
NOTE: This table is an example. The format should be revised as needed for consistency with the contractor's accounting system.
TABLE 1
CONTRACTOR
COST ELEMENT SUMMARY
RFP HQ0147-11-R-0006
Exhibit B-7
FOR OFFICIAL USE ONLY
NEGOTIATION SENSITIVE
Sheet1