MICS Industry Day 2 Questions and Answers

View the file

Other files

File Type Posted
J_Exhibit_A_CDRL_Amend1_120316.pdf PDF
J9_Acro_Def_Amend1_120316.pdf PDF
L10_AcctSys_CkLst_Amend1_120316.docx DOCX document
L_Exhibit_A_EPE_Amend1_120316.xlsx XLSX spreadsheet
MICS_ID2_AttendeeList_120313.xlsx XLSX spreadsheet
L_Exhibit_B_BOE_Sum_Amend1_120316.xlsx XLSX spreadsheet
Section_M_FRFP_Amend1_120316.docx DOCX document
Section_L_FRFP_Amend1_120316.docx DOCX document
J1_PWS_FRFP_Amend1_120316.pdf PDF
J5_IFP_FRFP_120215.pdf PDF
L_Exhibit_B_BOE_Sum_FRFP_120215_Final.xlsx XLSX spreadsheet
MICS_Offerors_Library_ Request_Form-Final.pdf PDF
J1_PWS_FRFP_20120215.pdf PDF
L1_PPRL_FRFP_120215_fianl.xlsx XLSX spreadsheet
J_Exhibit_A_CDRL_FRFP_Final.pdf PDF
L10_AcctSys_CkLst_FRFP_120126_Final.docx DOCX document
L7_Risk Analysis_Slides_FRFP_120215.pptx PPTX presentation
SF33_Mdl_Contract_120215.docx DOCX document
J9_Acro_Def_FRFP_120215.pdf PDF
J7_GFP_FRFP_120215.pdf PDF
Section_L_FRFP_120215.pdf PDF
Section_M_FRFP_120215.pdf PDF
L2_PPI _FRFP_120216.pdf PDF
L4_PP_Consent_Ltr_FRFP_120126_Final.pdf PDF
J8_SCA_Wage_Det_FRFP_120125_Final.pdf PDF
L3_PPQ_FRFP_120216.pdf PDF
L_Exhibit_A_EPE_FRFP_120215_Final.xlsx XLSX spreadsheet
J4_MDA_OCI_Memo_FRFP_120125_Final.pdf PDF
L8_Prop_Matrix_FRFP_120215_Final.xlsx XLSX spreadsheet
L11_CPIF_Calculator_FRFP_120215.xlsx XLSX spreadsheet
J3_DD254_FRFP_120215.pdf PDF
L5_OCI_Disclosure_Form_120216.pdf PDF
IndustryDay1-Q A-FINAL2.pdf PDF
MICS ID2 Registration Form 1.1_distributed.pdf PDF
MICS ID1 Attendees.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Missile Defense Agency Information Technology Collaboration Systems (MICS) Industry Days 2 (Schriever AFB, CO) - Questions & Answers

No.
Question
Answer
1.
Responsibility Matrix - Slide 42: Is this the current model or is this the future model?
The matrix includes all current tasks and also includes scope for future requirements.
2.
Will you elaborate on how MICS Tier 1 Service Desk will interact with Associate Contractor Tier 1 Service Desk?
For VTC Tier I support a phone separate number or AMX help button goes directly to the Video Control Center (VCC), however if a customer should dial the MDA integrated service desk for a VTC issue the service desk creates a Remedy ticket and routes it to the appropriate RBA crew. All MKO baseline Tier I support is provided by the MDA integrated service desk by creating Remedy tickets and routing to the appropriate RBA crew. The two exceptions to this are executive front office support and the Customer funded Site Management support which both provide Tier I support directly to their Customer.
3.
What is the primary role of Dahlgren within the MDA umbrella?
Headquarters for the Aegis Ballistic Missile Defense (AB) Program.
4.
Are the MKO Site Management Tier I Support personnel all located in HSV currently?
No, Tier I support in relation to MKO Site Management is located in both HSV for discrete customer funded tasks and NCR for Executive front office support.

Future MKO Customer funded Site Management could be located in other regions as well.

5.
Are all of the discrete tasks currently funded and ongoing?
Yes, all discrete tasks are currently funded and ongoing.
6.
Regarding the Orange boxes in the responsibility matrix, please elaborate on the interaction between MICS and JRDC?
The orange boxes indicate a joint responsibility for IA. The MICS Contractor is responsible for IA for all areas colored in green on the responsibility matrix while the Associate Contractor is responsible for the blue boxes.
7.
Are there currently mobile applications in use today?
No, other than our BlackBerry devices utilizing the Blackberry Enterprise Server (BES). We want to utilize mobile applications in the future in accordance with the DISA STIGS for mobile applications.
8.
Are there dedicated Site Managers for all program offices? How many are needed in HQ?
No, only those which are identified as discrete tasks in the PWS. Refer to workload data to determine the level of support required in HQ. Note, there is a maximum constraint of six (6) personnel in the National Capitol Region (NCR).
9.
Dahlgren was mentioned in passing earlier slides but Dahlgren is not mentioned in the network connectivity.
Dahlgren is directly connected to the MDA network. For more information refer to Industry Day 2, Slide 17.
10.
Is there on-site support for SharePoint at Dahlgren?
There is no requirement for on-site SharePoint support at this time, but it could be a future requirement.
11.
Regarding RAM&T, are users going to be trained on how to write ad-hoc requests/SQL statement?
No, we do not currently train RAM&T users to write SQL statements for reporting purposes; that is the role of the RAM&T administrator.
12.
Regarding RAM&T, can Offerors add a fourth Past Performance citation to address the RAM&T requirement?
No, Offerors are limited to the number of citations as instructed in Section L-04.
13.
Regarding Application Specialists, how is this function performed currently?
This function is currently performed in an ad-hoc manner by Government personnel in response to incidents involving external applications. The Application Specialist is intended to provide a single POC to formally engage on these incidents and to provide an improved service to the MDA customer. Requirements of this function are defined in the PWS (ref. 3.1.2.4).
14.
Will MICS be required to work with the Integrated Test Lab (ITL)?
Yes, MICS will utilize the Integrated Test Lab. JRDC will maintain the platform and MICS will be responsible for the application layer for applications managed by MICS (e.g., SharePoint).
15.
Is there a preference where the MKO staff sits?
Where staff supporting MKO sits is dependent upon your approach and we are not stipulating a location.
16.
Are there any restrictions on staffing in Colorado Springs or Huntsville?
No, there are only staffing restrictions in the NCR (ref. Section L, Attachment 6 - Workload Data).
17.
Is there 24x7 support from the Video Service Operations Center (VSOC) between Colorado Springs and Huntsville?
No. Hours are listed within the PWS (ref. 2.1). Special events are the exception.
18.
Is MKO Tier I support located in Colorado Springs or just Huntsville?
All MKO baseline Tier I support is provided by the MDA Integrated Service Desk by creating Remedy tickets and routing to the appropriate RBA crew. The two exceptions to this are Executive Front Office Support and the Customer funded Site Management support which both provide Tier I support directly to their Customer.
19.
With regard to dedicate SharePoint experts (Site Managers) for the outlying program offices, are there restrictions for NCR?
Yes, there is a maximum of 6 MICS personnel in NCR for support of all MICs requirements. We have not specified a minimum (ref. Section L, Attachment 6 - Workload Data).
20.
How is Dahlgren supported?
Dahlgren is considered a location for "Contract Essential Services". Refer to the Section L, Attachment 6“Work Load Data” for staffing constraints.
21.
Is everything we toured in Colorado Springs going to be in the contract?
Not everything. The Video Services Operations Center (VSOC) is the only area/location that falls within the scope of the MICS contract. However, MICS is responsible for VTC equipment located in both the Huntsville and Colorado Springs data centers.
22.
Are all personnel ITIL certified?
No. (Ref. PWS 2.8)
23.
Will ITIL presentations be available on FedBizOpps?
All Industry Day presentations will be available by e-mail request. Instructions are provided on FedBizOpps notice under “PREPROPOSAL CONFERENCE INDUSTRY/DAYS #2 QUESTIONS AND ANSWERS
24.
When you dial 721-9500 for problems, does it go to the Integrated Service Desk?
To clarify, 1-888-MDA-DESK is the number to the Enterprise MDA Integrated Service Desk (ISD).
25.
Do you maintain a test environment that's separate from the production environment? Is MICS responsible for this?
Yes, the Integrated Test Lab (ITL). JRDC will maintain the platform and MICS will be responsible for the application layer for applications managed by MICS (e.g., SharePoint).
26.
With regard to MDA Knowledge Online support, is the Front Office at HQ (Ft. Belvoir) roughly equivalent to the various Program Offices?
Recommend reviewing 3.1.2.5, 3.1.2.2.1, and Section L, Attachment 6 - Workload data for these requirements. In addition, the most significant deference between Site Management for the Program Offices and Front Office support is the op-temp and the demands of the Front Office Customers.
27.
Does the VSOC provide enterprise wide support?
Yes.
28.
Does the VSOC provide local Tier 1 Support?
On a regular basis no. However Customer Service should be the primary concern for all MICS personnel and Tier 1 support should be provided as required.
29.
System Monitoring - Does the system automatically notify you of system failures or must they be manually entered?
In respect to VTC & MKO, the systems can be monitored but do not send any automatic notifications. In respect to network & environmental, systems are monitored and send automatic notifications.
30.
Do you have MICS specific definitions for Tier I, II, and III support?
We use standard industry definitions for these terms and have not modified them for MICS.
31.
SDVOSB Verification: The GAO is currently investigating awards made to fraudulently uncertified SDVOSB's who used self-certification mechanisms like ORCA/CCR to allege certification. There is extensive government discussion surrounding verification of SDVOSB status. It appears imperative that MDA make a firm determination (before proposal submission) of the process it will use to verify SDVOSB status. Will MDA use ORCA/CCR (self certification) of VA's CVE for verification of SDVOSB status for MICS?
ORCA is the official verification process that will be used.
32.
Is the COMSEC requirement as a user or as a COMSEC account manager?
MICS will be Hand Receipt Holders and maintain Hand Receipts for all COMSEC equipment and keying devices and material in GFE Approved Security Containers.
33.
Records Management: The briefer mentioned new records management software/program being implemented. Will it interface with SharePoint? If so, what is the role the MICS contractor will play in supporting this application? What is the new records management application?
The new records management application is Opentext Content Lifecycle Manager that integrates with SharePoint. The MICS contractor will collaborate with the Records Management Support Contractor to ensure the integration stays operational and that SharePoint connection stays current.
34.
Does the Network Operations Center (NOC) manage the VTC COMSEC key? Are there multiple COMSEC Accounts?
The VSOCs control VTC COMSEC keys, equipment and material. There is one COMSEC account, but multiple MICs hand receipt holders. MICs will be required to identify primary and alternate Hand-Receipt-Holders.
35.
Are the VTC suites on the TS networks single level or multiple security levels? If multi-level, what levels are present on the different TS enabled VTC systems?
Most rooms are Unclass/Class using fiber optic switches. Some select rooms Sensitive Compartmented Information Facilities (SCIF) can switch between multiple levels. Refer to Section J, Attachment 3 “DD254” form and Section L, Attachment 6 “Workload Data”.
36.
Is hardware/software tested prior to installation into your server racks? Is there a separate site for that?
Yes. We use the integrated test lab (ITL) environment to test before installation into the production environment.
37.
Are Tier I, II, and III help desk support clearly defined? Where are help desk personnel? How many per location?
Current FTE counts are not being disclosed. Offeror can evaluate workload data and any personnel restrictions and determine the best distribution of personnel. VTC requires Tier I, II, and III support; baseline MKO is only Tier II, and III but the discrete and Executive Services MKO support require Tier I.
38.
Work load data: For MKO Service requests are the short-term projects and long-term projects handled via baseline? Or are they discrete tasks?
All efforts listed in the Section L, Attachment 6 Workload Data are baseline projects.
39.
MKO: How often do projects (MKO service requests) involve .NET custom coding, using tools like Visual Studio? For example, how many of the (3) long-term projects and the (12) short-term projects per year involve .NET custom code?
Most custom MKO projects involve .NET code. We try to use .NET where possible unless we cannot for technical reasons, then other tools are explored (i.e. iDashBoards).
40.
Work load data: Where are events and training held? How many events per location?
The CO will amend the RFP to include additional training workload to include number of courses (classroom, virtual, CBT), delivery method, and region.
41.
Work load data: In the library, there is a "Workload" document that quantifies expected efforts. Where can we find a breakdown of VTC & MKO workload per location? How many sites per location? Remote site support?
Sites per location are listed in the Section L Attachment 9 Configuration & Maintenance List. We do not have work load data per location. Remote sites only require onsite support for equipment replacement as required.
42.
What determines responsibility for system installation between JRDC & MICS?
This is determined by the project requirements through the EAB process. Refer to the Responsibility Matrix for technical responsibilities associated with a service.
43.
End User Training: On Slide 40, is the number of classes indicated intended to portray Instructor-led classes? Live classes?
The CO will amend the RFP to include additional training workload to include number of courses (classroom, virtual, CBT), delivery method, and region.
44.
Is the VTC engineering in the IT Operations Center part of MICS?
Yes. This function is specifically co-located with our Associate Contractor's Tier 3 network engineers.
45.
Are equipment items in the Configuration & Maintenance List the O&M responsibility of the MICS Contractor?
Yes, with the exception of telephone equipment. However, the MICs Contractor is responsible for ensuring all items listed are located in the room, operational, and are being tracked.
46.
MKO & Application Development: One of the example projects provided involved development of database components involving MS SQL Server Integration Services (SSIS) and reporting services. Development of SSIS packages is a typical DBA skill set. Do you anticipate a need for DBA skill sets on MICS based on this point?
We are not dictating skill sets. Offerors should propose to meet requirements.
47.
Is the MICS Contractor expected to conduct the enterprise architecture reviews and update the architecture?
MICS is not responsible for Enterprise Architecture however, as part of the Engineering Architecture Board (EAB) MICs will review all project documentation for standardization and possible impacts to scope and magnitude.
48.
Where are the key sites to have staffing?
Refer to the PWS to build your technical and management approach and see Section L, Attachment 6 - Work Load Data, 5.0 Staff Constraints.
49.
OCI Disclosure Form submitted - we are on several MIDAESS teams. Is this a concern?
PCO will review and provide details in response to OCI inquiries. The CO will discuss with Offerors on a one-on-one basis, if necessary, to address individual Offeror’s OCI concern.
50.
Management location - is there a preference for the program management location?
This is part of the Offeror's technical and management approach. We are not dictating this.
51.
How long will you be accepting questions from Offerors?
RFP clarification questions will be reviewed until proposal due dates 26 Mar and 6 Apr.
52.
Exhibit A spreadsheets - are you looking for how we develop indirect rates? Are we only to provide the information that is shown in the example?
Section L-07, Cost/Price Section, provide instructions to Offerors. Examples are notional; the expectation is that the Offeror's will provide their own data.
53.
Are hours listed on the tab fixed?
There are no fixed hours. Any initial data on the spreadsheets are notional and are for example purposes only.
54.
Are there any constraints on the escalations?
No, but it must be reasonable.
55.
Is it a true best value?
Yes, IAW FAR 15.3 and DFARS 215.3.
56.
We just became SDVOSB - if we don't have the VIP letter yet is that an issue?
No, the CO will verify your SDVOSB status on ORCA.
57.
Do you want a separate CD for pricing volumes?
Yes - Volume VI should be on separate DVDs. Please refer to Section L: Table L-01-1 Volume organization for instructions.
58.
EVMS - We are implementing upon award, is that satisfactory?
The Offeror shall submit the appropriate Notice of Earned Value Management System (EVMS) or plan IAW DFAR 252.234-7001. If a plan is required it will be incorporated into the contract at Section J, Attachment 10 – Earned Value Management Plan.
59.
How embedded do you want us to be on this contract when it comes to cloud technologies? What do you see going to the cloud?
This is primarily an O&M contract therefore we need to maintain/sustain what we have. For the purpose of your proposal, refer to section L-05.5 concerning your cloud computing approach. The PWS includes scope to leverage cloud technologies as a possible solution as future requirements are identified.

NOTE: TSF: 3 is notional and is not being priced or executed.

60.
The EAB process can slow down progress in the System Development Lifecycle. Are you open to other methodologies?
Other methodologies can be proposed however, the EAB process shall be adhered to.
61.
What is the biggest challenge you have in your business processes today?
We want to be flexible and responsive to our customers and leadership. We want to enable our customers to more effectively and efficiently perform their jobs through collaboration and tools.
62.
How are you positioned for Von Braun IV (VBIV: new facility slated for HSV)? Is it funded? And how does that affect the MICS effort?
There is currently no MICS requirement for VBIV. For all new facility build outs, refer to the Section J ‘PWS” VTC Responsibility Matrix.
63.
Do you envision dedicated support for TS SCI/SAP areas or will it be supported out of baseline?
The current model provides support out of baseline O&M. Any service request or outages would be handled through the RBA process and Remedy ticketing system.
64.
Do you have an idea of how future DoD budget cuts may affect the MICS effort?
Budget cuts are always a possibility; this is why we have identified this as a possible risk (ref. Section L, Attachment 7).
65.
Property Management: Are we to solely follow the procedures established by the Associate Contractor? What is MICS responsible for?
The associate contractor is on contract for property management of IT assets. MICS is responsible for configuration management of Software related/patches, firmware versions, life cycle management, and VTC room configuration. The Contractor shall establish plans, systems, and procedures only to the extent that the plans, systems, and procedures augment those of the Property Management Associate Contractor and Government Property Administrators (ref. PWS 3.1.3.3).
66.
eScheduler: There is currently not the capability to automatically pass the information to TMS for building bridged calls. Is automating within scope?
Yes, it is within scope to suggest ways to automate eScheduler.
67.
Is there a strategy for the workflows used within MDA?
We leverage the SharePoint workflow capability where possible. We are open to recommendations on business automation.
68.
Is there a workflow inside the Cognos engine that you are using?
IBM does have a Cognos workflow product called IBM Cognos TM1 Workflow - but we do not use it or have licenses for it.
69.
Have you extended workflows in any other solutions? e.g., Nintext?
We use Nintex as an analytics tool. We are not currently using Nintex’s workflow capability.
70.
Mobile Device Development: Is there a type of mobile device that MDA is currently looking at other than the BlackBerry?
MDA is working with DISA for approved mobile devices; however no decision has been made on a course of action. We are not tied to any particular device at this time.
71.
Are there any planned applications or type of functionality [mobile devices] wanted by MDA Leadership?
There is scope in the MICS contract for future capability however, MDA leadership has not defined any requirements at this time.
72.
Is there a timeline for the SharePoint 2010 roll-out?
Not at this time. An upgrade to 2010 would be a future contract mod, most likely a project.
73.
Do you foresee PowerPoint going away as a result of you selecting SharePoint as a presentation tool?
No, presentations are just one of the many requirements for SharePoint.
74.
Cloud Computing: Any further clarification on the Cloud Computing requirement in the PWS?
From a proposal prospective, we are looking for the Offeror’s understanding and knowledge of a cloud computing approach. We are not looking for anything readily executable. We want Cloud Computing to be considered as a possible solution. Follow instructions for completing Section L-05.5.
75.
Is SaaS a possible consideration to Customers outside of the agency?
No. SaaS is not a consideration at this time to customers outside of the agency.
76.
Who do we collaborate with the most on future collaboration technologies? Dr. Armstrong?
The MICS Service Line Managers can propose new technologies to the Government for the Unified Communications, Business Applications, and Portal and Data Services service lines. You will need to be familiar with what the DoD has approved and not approved in developing strategies for these service lines.
77.
With regard to the Tier II & III support, can we do that from Contractor facilities?
Offerors would have to provide additional details in their proposal but it may be possible to have Tier III SME reach back…non organic to the contract. However, Tier II (organic/in house) will need to be on-site.
78.
You have a lot of tail sites already connected to your network. Is it a possibility for providing tail site connectivity to an off-site location (Contractor or Government owned) for Tier III MKO support?
Offerors would have to provide specific details in their proposal in order for the Government to analyze and evaluate this approach.
79.
We have Level III reach back support located within the NCR. Can we utilize those individuals who would not require seats, and just focus on having individuals with both Tier I & II skill sets to physically sit within the MDA space?
Offerors would have to provide additional details in their proposal for evaluation, however it may be possible to have Tier III SME reach back (non-direct charge) in the NCR. This determination may be impacted by BRAC law constraints. Tier II support will need to be on-site.
80.
How do we integrate our technical capabilities for mobile applications within our proposal if there is no formal requirement for mobile application development?
We anticipate mobile applications to be a future requirement which is why scope is included in the PWS (ref. PWS 3.2). Refer to Section L regarding requirements of your proposal.
81.
What is the level of importance placed upon us to demonstrate our commitment to continue the path of converging the two combined technologies within this acquisition?
The intent is to drive efficiencies and provide greater functionality as these technologies merge. Refer to Section M for evaluation criteria of your proposal.
82.
What's the current culture of training as far as paper handouts in classrooms?
Currently, MDA utilizes multiple delivery methods for training which includes courses with handouts and some that are paperless. Training delivery is part of your approach to training.
83.
With regard to LMS, is that considered its own database? Will that be later tied into as a module within MKO?
We're still developing the requirement for LMS. We'll do a contract mod if a requirement for MICS develops.
84.
Section L, Exhibit B - Are the lavender columns for "Execution", "Operations", and "Maintenance" summary columns for PWS Groups used as the BOE inputs to pricing and do they include the information in the gray column?
For columns colored in gray (e.g., 3.1.1.4, 3.1.2.1, etc.) on this spreadsheet the Government requires the BOE Summary to include labor categories, hours, etc. to be broken down for each of these tasks. For columns in color (e.g., green, purple, etc.), the Government requires the BOE Summary to include labor categories, hours, etc. to be rolled up for each of these task ranges.
85.
Does Dahlgren fall up under this COMSEC process?
MICS will be Hand Receipt Holders and maintain Hand Receipts for all COMSEC equipment and keying devices and material in GFE Approved Security Containers.
86.
Is MDA willing to assist the MICS Contractor in registration/utilization of GSA/GWACS?
Yes, Offerors will be authorized to use Government Supply Sources IAW FAR Part 51 and DFARS Part 251.1.
87.
Do you currently have arrangements in place today to authorize use GSA/GWACS?
We are currently utilizing GSA/GWACS to some degree.
88.
Would this activity [GSA/GWACS] include support agreements?
Yes, as required in the PWS Task: 3.5
89.
Does the VSOC interface with the IT Ops center?
Yes, they do during certain events (e.g., all hands, flight tests, or outages).
90.
When will MDA transition to the cloud services?
We consider our MDA CNet and UNet an internal cloud. Any further transitioning to other platforms is dependent on future requirements, security considerations, budget, etc. Scope of the contract gives us capability to migrate to the cloud. It would be a discreet task to migrate to a cloud computing environment other than the internal MDA cloud.
91.
DISA has an existing cloud, but would you build your own?
We consider our MDA CNet and UNet an internal cloud.
92.
What are the number of VTC bookings for Schriever? Do you know how many booking were in 2010/2011?
Bookings were given across the enterprise and not by region (ref Section L, Attachment 6 – Workload Data).
93.
What's anticipated to be on the cloud beside the MKO?
We do not have any firm requirements of what would be on the cloud. For the purpose of your proposal, refer to Section M (04.4.3) for the evaluation criteria.

NOTE: TSF: 3 is notional and is not being priced or executed.

94.
What is the Executive Officers coverage for VTC? We are capped by BRAC, but do you have any usage rates for the NCR?
Regarding Executive Support for VTC, refer to PWS 3.1.2.5 for requirements. There are approximately 36 Executive Bookings per day at MDA, roughly 15 per day are supported in NCR.
95.
Are there calls that MDA makes above the JWICS level?
Refer to the DD254 for security requirements for this contract.
96.
Is there a Top Secret MKO?
No.
97.
Will the BRAC numbers for the personnel constraint increase with the completion of the new Dahlgren building?
The new Dahlgren facility is not required to be addressed in your proposal. Any impact to scope and magnitude would be addressed in a future contract mod.
98.
You have a lot of emphasis on ITIL. Do you have processes that we are able to see that are based upon ITIL?
Refer to briefings from Industry Day 1 and 2 for examples of MDA’s implementation of ITIL processes.
99.
How many directorates have the dedicated Site Managers like GM?
Seven (7) (ref. PWS 13-001 through 13-008)
100.
What's your view of using Lync down the road?
Lync is currently being deployed on the Unclass Network.
101.
Are you using the DISA approved version of Cisco Unified Communication Manager?
Yes
102.
Is there a plan to integrate Lync with VTC and are you currently working that now? Is Lync being used on both Unclass/Class networks?
Currently, our Lync and VTC architectures are independent. Future integration would be dependent on DISA, other regulatory restrictions, and funding. Lync is currently being deployed on the Unclass Network.
103.
What are the FTE constraints within the NCR?
The National Capitol Region Staffing is limited as outlined in “Section L, Attachment 6 - Work Load Data.”
104.
In Section L, Exhibit B the BOE narratives count total says 9 but we believe it should be 10. Which is correct?
The RFP will be amended to reflect 10 BOE narratives The Offerors BOE Narratives (Reference Section L-08.1 and L-08.2) shall be aligned to the PWS sections identified in this spreadsheet (e.g., Phase-in 3.6, Execution 3.1 - 3.1.1.4, etc.), NOT to the CLINs. BOE Narratives will apply ONLY to work being proposed to in this proposal under CLINs 0001, X100, and X500 - X507. Offerors shall not align the BOE Narratives to CLINs.
105.
What positions require TS clearances? Which of the 9 positions in the discrete tasks are included?
We have not defined "positions" for TS clearance requirements. Reference DD254, PWS, and Workload Data for technical and business requirements at the TS level. Note, there are no TS requirements for the current discrete (i.e., customer funded 13.001-13.008) PWS tasks.
106.
Ref L-03. VOLUME II – CONTRACT L-03.1 Tab 1: Standard Form 33 (Section A), Contract Sections B-K, and Contract Section J Attachments

L-03.1.1 The Offeror shall submit a signed Standard Form 33 (SF33), complete with Sections A-K and all Section J attachments. The Offeror must complete Section A Solicitation/Contract Form blocks 12, 13, 14, 15A, 15B, 15C and provide signature and date for blocks 16, 17, and 18; block 12 must state 180 days. The submission of Section A-J and Section J Attachments constitutes an offer, which the Government may accept. The original unbound copy should be clearly marked under separate cover and should be provided with three (3) holes punched on the side of pages.

1.) This statement seems to indicate is the Govt’s desire to receive a completely reproduced copy of the RFP Sections A – J, to include Section J attachments. Should Section J attachments such as the PWS, IFP, etc. be reproduced and re-submitted? Section J – Attachment 2 Management Plan is marked as Contractor provided and per Section L instructions, is to be included in the Management Volume. Is it the Govt’s intent that the Management Plan should also be included in Tab 1 of Volume II – Contract?

1).Yes, the Government requires a reproduced copy of Sections A-J. The Offeror shall prepare the proposal as set forth in Section L Table L-01-1 “Volume Organization” (Pages 9 and 10). The title and contents of the volume are defined in the table. All Section J attachments, including Offeror provided attachments, should be included in Volume II-“Contract”. The Management Plan is a Section J Attachment and should be submitted Volume II “Contract”.

107.
Reference Section L-01.7.3.1 and L-01.7.3.2, Will the Govt. allow smaller font size for tables and exhibits on paper size 8 ½ x 11in?

No: Except for the reproduced sections of the solicitation document, the text shall be Microsoft Word Times New Roman and no less than 12-point font.

108.
Reference Section L FRFP 120215, Sections L-07.5.7 - 07.5.10 CLINS X600 – X999 – Since the Govt. does not have definitive requirements, is the expectation that Offerors should enter “$0.00” in each of these CLINS?
MDA does not have any definitized Routine Projects and Discrete Tasks requirements; these CLINS are included as placeholders for future requirements. Offerors may enter $0.00 in the CLINS or leave them blank.
109.
Reference L-06.2.1.2.6 Workforce Management - Process to ensure personnel have appropriate security clearances at contract start and throughout the life of the contract.

1.) Will the Govt. provide an estimate of how many TS cleared personnel are required for performance under the MICS contract?

2.) Are Interim Secret Clearances at Phase In start or Contract start acceptable?

3.) At what location(s) do most of the TS cleared personnel reside or at what location(s) is most of the activities performed requiring TS classified personnel?

1.) No: The Offeror should refer to Section L, Attachment 6 “Workload Data” to determine the appropriate requirement for TS requirements.

2.) Yes, for those areas and positions that require a Secret clearance. A Top Secret/SCI is still required as a minimum for those areas and positions that require a Top Secret Clearance/SCI.

3.) Refer to Section L, Attachment 6 “Workload Data”, Section 6.0

110.
Reference L-08 VOLUME VII – Total Resources

The instructions for this volume regarding Basis of Estimate Narratives, The Basis of Estimate Summary form and the EPE forms in the Cost Volume do not seem to align properly. See specific questions below:

1.) Reference L-08.1: Tab 1, Basis of Estimate Narratives

The instructions call for nine (9) BOE narratives, specifically for the labor CLINs - CLINs X100 and CLINS X500-X507. However, the Basis of Estimate Summary form (Exhibit B) is structured by PWS tasks and not CLINs. Furthermore, the PWS tasks included on the Basis of Estimate Summary form do not map to CLINs X501-507 which are the FFP Customer Support Tasks. Therefore, the hours associated with the FFP CLINS X501-X507 will not be included on the Basis of Estimate Summary form (Exhibit B). Please clarify the following:

•The Basis of Estimate Narratives are intended to be organized by the nine (9) labor CLINs identified above.
•Please explain whether it was intentional to exclude the tasks associated with CLINs X501 – X507 on the Basis of Estimate Summary form (Exhibit B) and if so, please explain why?

2.) Reference L-08.2: Tab 2, Basis of Estimate Summary

The instructions state that all hours recorded in Exhibit B, BOE Summary must match the total hours in the EPE, Cost Model Exhibit A. As noted in question 4.a above, the hours associated with CLINs X500-X507 CLINS are not accounted for in the BOE Summary form (Exhibit B) but they are included in the EPE. Therefore, the hours would not match. Can you please provide clarification?

3.) Reference Section_L_FRFP_120215 Exhibit B, BOE Summary attachment

In this exhibit, there are certain tasks that appear to be identified separately from the PWS tasks that are grouped together under specific buckets – see Execution, Operations, and Maintenance. Is it a correct assumption that the government wants to see the labor category(ies) and hours specific to the uniquely identified task called out separately, as well as have those hours included in the overall hours count for their respective task groupings? For example, the BOE Summary appears to individually identify Task 3.1.1.4 under the Execution bucket (Column E). However, the labor category and hours for task number 3.1.1.4 would also be summed in Column F (Tasks 3.1 – 3.1.1.4). Similar scenarios occur in the Operations and Maintenance buckets.

1.) The CO will amend the RFP (Section L) to provide more clarification to this section and add ten (10) Basis of Estimate Narratives (BOE) including CLINS X501-X507. The BOE Narratives should not be written to the associated CLIN(s) but should be written to specific tasks in the PWS. The CLINS are provided as a reference to ensure that Offerors would not attempt to bid to the Discrete Tasks (CLIN X600—X699).

2.) Offeror should construct Narratives to the PWS tasks and not the specific CLINS. The RFP will be amended to provide more clarification.

3.) The CO will amend the RFP to include a notes section to say “The Offerors BOE Narratives (Reference Section L-08.1 and L-08.2) shall be aligned to the PWS sections identified in this spreadsheet (e.g., Phase-in 3.6, Execution 3.1 - 3.1.1.4, etc.), NOT to the CLINs. BOE Narratives will apply ONLY to work being proposed to in this proposal under CLINs 0001, X100, and X500 - X507. Offerors shall not align the BOE Narratives to CLINs.

111.
Reference General

Will overtime be authorized for special events and surge requirements?

All requests for overtime will be assessed on a case-by-case basis and be approved if justified.

112.
Reference PWS 3.1.2 and 3.1.2.3

Will the Govt. provide detail on the anticipated amount of CBT training versus desk-side training delivered by technicians?

The Govt. has provided the historical number of training events in Section L Attachment 6 “Workload Data”, which includes all methods of delivery. There is no specific amount of CBT training versus desk-side training required. The method of delivery and approach to training is up to the Offeror to propose (ref. Section L). The CO will amend the RFP to include additional training workload to include number of courses (classroom, virtual, CBT), delivery method, and region.

113.
Reference PWS 3.1.2 and 3.1.2.3

Industry Day #1, Slide 144 (p 72) provided a breakdown of classes taught. Can MDA provide further training details, such as the schedule of all of the instructor led training classes that were conducted last calendar year, including the title of the training, the dates, the duration, the technology trained, the # of students, and whether or not the class was offered via VTC or another remote attendance capability?

The CO will amend the RFP to include additional training workload to include number of courses (classroom, virtual, CBT), delivery method, and region.

114.
Reference PWS 3.1.2.1.2 and 3.1.2.1.3

Please provide a breakout of the 263 conference rooms (# of Small, Medium, and Large).

Refer to “Configuration and Maintenance List” Section L Attachment 9.

115.
Reference PWS 3.1.2 & 3.1.3.1

Can the MDA provide a deeper breakout of service desk tickets? Including the following information:

1.) The # of tickets per month that are for MKO vs. VTC?

2.) The # of tickets per month that are resolved at Tier I, II and III?

3.) The # of tickets per month that represent request, incident and problem records?

4.) The average resolution times for the tickets of the various types identified above in this question?

1.) Response: Annual ticket data is provided for MKO and VTC. Refer to Section L, Attachment 6 “Workload Data”.

2.) We do not have this data identified by Tier.

3.) Currently, the data is not accurate enough to rely on the categorization due to immature procedures when tickets were created.

4.) While Remedy contains the resolution times associated with resolved tickets, the relatively immature processes of using Remedy to track MKO and VTC tickets has resulted in data significantly skewed that it provides no reasonable basis of estimate. (e.g., many tickets have been opened then immediately closed to document work performed after the fact.)

116.
Reference PWS 3.1.2.2 and 3.1.2.2.1

When calculating the % availability of the MKO systems for the correlating CPO, are the classified and unclassified systems weighted equally?

The availability of each system (UMKO and CMKO) will be considered independent of each other.

117.
Reference PWS 3.1.2.2 and 3.1.2.2.1

Is the CPO for % availability for the MKO systems broken out in any way other than overall system availability? For example, if the MKO sites are up and running, but the search component of the system is not returning results, is that factored into the % availability of the system?

All outages will be reviewed on a monthly basis for relevancy to MICS requirements. The Government’s intent is to validate any negative performance in order to determine the root cause of the issue prior to making a final determination of performance. Any negative performance beyond the MICS contractor’s control will not be assessed against the MICS contractor.

118.
Reference PWS Section 3.2 – Effective and Efficient Delivery of Future Collaboration Services

This PWS task is mapped to CLIN X100, X200, X300, X600-699, X700-799. As a future task with no requirements defined at this time, please provide clarification on how this task should be factored into the pricing for CLINS X100, X200 & X300.

The tasks described in PWS Section 3.2 could be funded under the baseline efforts (CLINS X100-X300) or Discrete Tasks (CLINS X600-799). There is currently no defined requirement for Offeror(s) to bid this task for the MICS RFP.

119.
Reference PWS Task 3.3 Software Development & Mobile Apps AND Section L, Exhibit B- BOE Summary

Task 3.3 is listed in the Exhibit B, BOE Summary located in Section L. This task is mapped to CLIN X600-699, X700-799. Section L -07.5.7 and L-07.5.8 state, “While at this time MDA does not have any definitized [….] requirements, these CLINS are included as placeholders for future requirements. Should Task 3.3 be removed from the BOE Summary? If not, will the Govt. please provide direction on how Offerors should project labor for this future task and correlate that to the EPE, as directed?

MDA does not have any definitized Routine Projects and Discrete Tasks requirements; these CLINS are included as placeholders for future requirements. Task 3.3 in the BOE Summary will be reflected as “Reserved” and no BOE narrative is required for Task 3.3.

120.
Reference PWS 3.1.1 CDRL Life Cycle Management Plan A021

Will the Govt. provide additional information on the existing Life Cycle Mgmt. Plan (to include hardware and applications?)

There is no existing Life Cycle Management Plan. All existing data that could be used for the development of a Life Cycle Management Plan has been provided. Refer to “Configuration and Maintenance List” Section L Attachment 9 and “Workload Data” Section L, Attachment 6.

121.
Reference PWS Task 3.1.1.1.4

Will the Govt. provide a sample of a current SLA and OLA?

Not at this time. We currently do not have a standard document to serve as an example.

122.
Reference PWS Task 3.1.2

Does the Govt. have a spares management policy?

No.

123.
Reference PWS Task 3.1.2

1.) For VTC service desk requirements, where do Tier I, Tier II and Tier III resources reside currently?

2.) For all other collaboration services, where do Tier II and Tier III resources currently reside?

1.) VTC resources reside across the Enterprise with Video Control Centers (VCC) located in NCR and Huntsville and Video Services Operation Centers (VSOC) located in Huntsville and Colorado Springs.

2.) Currently, MKO Tier II and III resources reside in Huntsville and National Capital Region.

124.
Reference PWS Task 2.1

Do the Core Hours of 0730 – 1830hrs EST include the Service Desk, as well?

The MDA Integrated Service Desk (ISD) supported by the Associate Contractor is Operational 0500hrs-2300hrs EST, Monday through Saturday. The Core Hour requirements for MICS remains as stated in Section J, Attachment 1- Performance Work Statement (PWS).

125.
Reference L-05.3 Tab 2: (TS2) Customer Training Approach , PWS 3.1.2.3

Is any of the vendor-specific training currently developed for existing systems/products either proprietary or copy-righted such that it would prevent the awarded Contractor’s trainers from using the existing, product-specific training information without being in violation of a copyright or proprietary data restriction, etc?

No, we have not discovered any current training products that are proprietary or copy-righted.

126.
Reference L-05.3 Tab 2: (TS2) Customer Training Approach, PWS 3.1.2.3

Is there an existing customer satisfaction survey tool? Is the Govt. looking for the Offeror to recommend a survey tool?

We currently use SharePoint and Remedy as our tools for capturing customer satisfactions. We are not asking the Offeror’s for recommendations on survey tools.

127.
Reference PWS 3.1.2.3

Is there a “Train the Trainer” type class structure?

Currently, we do not have “Train the Trainer” type classes, but do not have objections to this method if it proves appropriate for the subject.

128.
The Offerors’ Library includes a “MDA IT Services Annual Summary Report” that was published on 31 January 2011. Can the MDA make available the latest report that would have been recently published?

The 2012 “MDA IT Services Annual Summary Report” is now available and will be provided via e-mail as an update to the final Offerors Library.

129.
Can the MDA provide an example of a requirements specification, such as one that was recently submitted for a PMIB SRR?
The Government is unable to provide a response to this question/request at this time. If a response is available in the future it will be provided via FedBizOpps.
130.
How should we treat information provided during the Industry Days? If information provided during Industry Days is not directly contradicted in the solicitation, can we treat the information as “official” and accurate on which to base assumptions, etc?

All information provided during both Industry Days was an overview of the solicitation. In the event there are inconsistencies, the RFP/solicitation shall prevail over information presented at Industry Days 1 & 2.

131.
Reference Section L-07.5.2 Program and Collaboration Services – Baseline (CLINs X100)

The second paragraph references “CLINs X001” in three (3) places. Should these instances read “CLINs X100”?

Yes the Contracting Officer will amend the RFP to correct L-07.5.2 to read X100.

132.
Reference SF 33 Schedule B and Section L-07.5.2 Program and Collaboration Services–Baseline (CLINs X100).

The instructions in the above referenced Section L specifies to calculate all labor costs associated with the Baseline tasks and include the totals in the Target Cost lines of the SF 33 Contract Section B. The Target Cost line item is included in both the X100 CLIN structure and the X200 (Performance Incentive Fee for X100) CLIN structure. Further, the Target Cost total is added to the target fee in each CLIN - CPIF in CLIN X100 and PIF in CLIN X200. Is this potentially a double counting of Target Costs?

No, this is not double counting Target Costs. The instructions in Section L.07.5.2 clearly states the Offeror shall propose all labor associated with Program and Collaboration Services – Baseline in CLINs X100 of the EPE and include the totals in the Target Cost lines of the SF33 Contract Section B. Reference “Note” in Section L-07.5.2.

The Cost Incentive Fee amount should go into CLINs X100; the performance Incentive Fee amount should go into CLINs X200.

Reference Industry Days #1 (day 2) briefing charts 21 – 24.

133.
L-06.4.1 requires an appendix to Volume V, Tab 2 in slide format. Is this appendix contained in the 25 page limit given for Tab 2 or is it excluded from that page limit?
The appendix is included in the 25 page limit for Volume V, Tab 2.
134.
L-08.1 states that we are to provide BOE for CLINs 0001, X100, X500-X507 (a total of 10 CLINs) for each year of the contract. It further states that this equals a total of 9 BOE. Please explain/clarify how this results in 9 BOE narratives.
"Offerors must describe the approaches for providing products and services defined in each PWS roll-up section listed on the columns of the Section L Exhibit B - BOE Summary. The result will be nine (9) BOE Narratives." This refers specifically to Section L Exhibit B - BOE Summary; not the CLINS.
135.
Reference PWS 3.1.2.2 and 3.1.2.2.1

What level of access will the MICS team have to the MS SQL servers that are dedicated to the MKO systems? For example:

1.) Will the MICS team be able to create and configure SharePoint content databases, or will operations like that take the form of a request from the MICS team to the associate contractor responsible for the “Managed Web/App/DB Hosting” technical service?

2.) Will the MICS team be able to apply database updates that correlate with SharePoint patches, or will that also have to be a request to the associate contractor?

3.) Will the MICS team be able to query the MKO databases directly (read-only) to aide in the troubleshooting process?

The Government is unable to provide a response to this question/request at this time. If a response is available in the future it will be provided via FedBizOpps.

136.
Reference PWS 3.1.3.3

What tool(s) does the MDA use for source code control, e.g. versioning, branching, etc. of .NET source code?

Visual Studio Team Suite 2010

137.
Reference PWS Task 3.1.2.2

1.) What iterative development methodologies are currently used at MDA? Does MDA employ any forms of Agile methodology, or does MDA have any preferences regarding methodologies to be used?

2.) How does MDA manage requirements currently? Does MDA employ formal requirements management tools such as DOORS or MS TFS with underlying databases to store and manage requirements artifacts throughout the life cycle, or are requirements artifacts simply documented in Microsoft Office productivity tools and managed outside a specific tool environment?

3.) What tools are currently used by quality assurance testers to test custom SharePoint applications and other custom applications aside from a web browser? Is the Govt. looking for the Offeror to recommend a testing tool?

4.) Attachment J7 indicates the MDA will provide software development workstations. What unique tools are available/licensed for software developers, e.g. Visual Studio? Which versions of the tools are in use at this time?

5.) Which programming languages are in use by current solutions at the MDA that are expected to be maintained by the MICS contractor, aside from C#.NET? Is Java, Cold Fusion, or others in use?

6.) How many SharePoint development projects are completed per year? How many development projects are completed per years that are not SharePoint based solutions?

7.) Is the MICS contractor responsible for database administration for the development and testing environments used by the MICS development and testing efforts?

1.) Development approach is dependent on the project. However, a spiral development model is most commonly used.

2.) Requirements artifacts are generally documented in Microsoft Office productivity tools and managed in the SharePoint environment.

3.) The Government is unable to provide a response to this question/request at this time. If a response is available in the future it will be provided via FedBizOpps.

4.) Visual Studio Pro 2010, SharePoint Designer 2007, iDashboard - xPlatform, iDashboard Enterprise Edition, Quest LiteSpeed Enterprise for SQL Server v6.0, Quest SpotLight on SQL Server v7.6, Quest - TOAD for SQL Server Xpert Edition, Snagit v10 - Multi User, Quest - TOAD DBA Suite for Oracle, Nintex Reporting 2008, Adobe Technical Suite v3.5, Quest Recovery Manager for SharePoint, & Quest Site Administrator for SharePoint.

5.) Programming languages most commonly used are: C#.NET, ASP.NET, HTML, CSS, JavaScript, Flash/Action Script, Silverlight, XML, and SQL.

6.) Reference Section L, Attachment 6 – Workload Data (2.7)

7.) Yes

138.
Reference L-03.2

“The Offeror shall submit, in this Tab, a statement specifying the extent of agreement with all terms, conditions, and/or provisions included in the solicitation. Exceptions, if any, to the terms, conditions, and/or provisions of this solicitation shall be included in this Tab. Exceptions to the terms, conditions, and/or provisions of this solicitation in any form (identified as exceptions, assumptions, clarifications, etc.) shall not be included elsewhere in the proposal.” [Emphasis added] AND

L-08.1 Tab 1: Basis of Estimate Narratives “…The Offeror shall submit a Basis of Estimate (BOE) Narrative for CLINs 0001, X100, and X500 – X507 which includes Labor Categories and summary labor hours for each 12-month period of performance. …. Each of these narratives must explain all assumptions and rationale inherent in the Offeror’s proposed staffing approach; additionally, Offerors shall describe their proposed RBA structure. Discuss all proposed staff in terms of Labor Categories and labor hours thoroughly so that evaluators will understand the role each proposed Labor Category plays in the proposed approach to the subject PWS tasks. Also, thoroughly explain assumptions and rationale inherent in the quantity of labor hours proposed for each Labor Category.” [Emphasis added]

The instructions in L-03.2 and L-08.1 Tab 1 seem to…