09 06 22 Answers to Questions 1-16 .doc

DOC document 29 KB Posted

Attached to
System Techical Support Services for FOSOV Ground Mobility Vehicles in accordance with attached Performance Work Statement (PWS)
Solicitation number
H92222-09-R-0027
Issued by

About this file

This attachment provides answers to the first 16 questions submitted by vendors as of June 22 2009. on RFP H92222-09-R-0027. This is not a complete list of answers because some questions submitted by one vendor on June 22 2009 are still being reviewed.

View the file

Other files

File Type Posted
Answers to Questions 56 57 09 07 15.pdf PDF
Amendment 0004 Final 09 07 10.pdf PDF
Amendment 0004 Conformed Final 09 07 10.pdf PDF
09 07 08 Answers to Questions 26 27 29-32.pdf PDF
09 06 30 Answers to Questions Final 17-25.pdf PDF
Amendment 0003 Final.pdf PDF
Amendment 0003 Conformed.pdf PDF
Amendment 0002 Conformed Final.pdf PDF
Amendment 0002 Final.pdf PDF
CDRL A014 TIR _2_x.pdf PDF
CDRL A019 SAR.pdf PDF
CDRL A013 Conceptual Design.pdf PDF
CDRL A007 ERR.pdf PDF
09 06 09 PWS Final.pdf PDF
CDRL A011 Critical Safety.pdf PDF
CDRL A009 Transp Report.pdf PDF
Amendment 0001 Conformed Final.pdf PDF
CDRL A005 ECP _2_.pdf PDF
CDRL A018 Engineering Services Report.pdf PDF
CDRL A010 Agenda.pdf PDF
CDRL A004 Parts Mgt Plan _2_.pdf PDF
CDRL A006 NOR.pdf PDF
CDRL A016 Meeting Minutesx.pdf PDF
Amendment 0001 Final.pdf PDF
CDRL A008 CSAR.pdf PDF
Atch 03 - SOO Sample 2 GMV —
CDRL A003 Product Dwgs.pdf PDF
CDRL A012 FIR.pdf PDF
CDRL A001 Cost Report.pdf PDF
CDRL A002 Tech Rpt Study.pdf PDF
CDRL A015 RFD _2_.pdf PDF
CDRL A017 ESM _2_.pdf PDF
CDRL A011 Critical Safety.doc DOC document
H9222-09-R-0027 Solicitation.doc DOC document
CDRL A007 ERR.doc DOC document
Atch 03 - SOO Sample 2 GMV Mod.doc DOC document
CDRL A006 NOR.doc DOC document
CDRL A004 Parts Mgt Plan.doc DOC document
CDRL A003 Product Dwgs.doc DOC document
CDRL A008 CSAR.doc DOC document
CDRL A005 ECP.doc DOC document
Atch 02 - SOO Sample Task 1 Armor Coupon Testing.docx DOCX document
CDRL A030 Meeting Minutes.doc DOC document
CDRL A012 FIR.doc DOC document
Atch 01 - STS PWS 09 05 29.docx DOCX document
CDRL A001 Cost Report.docx DOCX document
CDRL A009 Transp Report.doc DOC document
CDRL A002 Tech Rpt Study.docx DOCX document
090204 STS PWS.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP H92222-09-R-0025

Questions and Answers

1. Is there an incumbent and if so, who might that be? No, there is not an incumbent.

2. Do you anticipate a multiple award ID/IQC or a single award? Single award.

3. Is there an organization currently providing this type of support to SOCOM that would be capable of responding to this solicitation? There are multiple organizations (both private and public) that currently provide the support.

4. FAR 52.219-6, Notice of Total Small Business Set-Aside is listed as an incorporated clause, but the size standard is not completely clear. Can you confirm small business set-aside status and clarify the size standard? The size standard, as listed in the Small Business Association “Table of Small Business Size Standards” Matched to the North American Industry Classified System Codes”, is 27 million dollars in average annual receipts.

5. Could you please confirm that this is now a small business set aside, and if possible, the total of anticipated hours for the term of the contract? This is a Small Business Set Aside and the total estimated amount of the five (5) year indefinite quantity contract is 25 million dollars.

6. For the FBO Synopsis under solicitation number H92222-09-R-0027, Is the contracting office requesting Comments on the attached PWS or is this a Sources Sought Notice? If applicable, what was the response date? The Government is now seeking offerors in accordance with the solicitation. However, comments and questions on the solicitation are welcome.

7. Is this project considered a new requirement? Yes

8. If this program is not considered a new requirement;

a. Who is the incumbent? There is no incumbent.

b. What is the contract number? N/A

9. I was hoping to find out if this is a new requirement or if there is an incumbent. If there is an incumbent on this acquisition, would you please provide me with the following information: This is a new requirement, not a re-compete and there is no incumbent or existing contract. There is no incumbent.

Award Date:

Contract #:

Contractor Name:

Contract Expiration Date:

Award Value:

10. Also, is there an anticipated timeframe for an RFP release? Thank you for any information you are able to provide. RFP was released 5 June 2009.

11. Can you give me a timeframe for when the RFP might be released? RFP was released 5 June 2009.

12. The solicitation seems pretty clear in that any STS provider will be unable to act as a prime vendor for any future SOCOM vehicle programs. Is this the case? No, this is not the case. Winning this contract will have no impact on your firm’s ability to compete on other SOCOM contracts.

13. What is the small business set-aside size standard for this solicitation? 27 million dollars in average annual receipts as defined by the Small Business Association.

14. Para. L.3.3(1) states:

“The offeror shall complete the pricing in the Schedule starting in Section B of the RFP for the Sample Tasks.” (emphasis added).

It is unclear what is intended to be included in the “Max Cost” lines for the non-task order CLINS (i.e. the yearly CPFF completion and LOE CLINS).

No entry is required in the “Max Cost” lines for the non-task order CLINs. Individual Task Orders will be issued under these CLINs after contract award. The Task Orders will be issued and priced IAW the clauses cited under each CLIN in Section B.

15. This same language in L.3.3(1) seems to conflict with L.3.3.4 which states:

“Offerors shall provide a fixed fee that will be applicable to all task orders for the life of the contract. This fixed fee should be based on the estimated amount of total obligations for each year as follows: Base Year $3M...”

It is unclear what is required for Section B where it asks for “Fixed Fee” for the yearly completion and LOE CLINS, and also what is required for ”Net Amount” for the Sample Task Order CLINS.

Offerors must either enter the fixed fee percentage for all CLINs in Section B, AND/or state in the COST Volume the fixed fee percentage to be used for all CLIN’s IAW L-3.3.4. Note: As stated in paragraph L-3.3.4 at the top of page 54, "the fixed fee PERCENTAGE proposed...will be applied to all four sample task orders."

16. Para. L.3.3.4 appears to suggest that a dollar amount rather than a rate should be proposed for the fixed fee for each year. It is unclear as to whether this proposed fee amount is for evaluation purposes only or whether it will become a binding contract amount. If the proposed fee is an amount which becomes contractually binding (as opposed to a rate), it is unclear how this will be applied to individual task orders - the number, scope/complexity, and amounts of which are unknown and could vary widely within a year or between years. It is also unclear how the response to Para. L.3.3.4 is considered in the evaluation based on the formula in M.3.3.1.3.

The proposed fee amount stated by Para. L.3.3.4 should be expressed as a rate. The Offerors are required to propose one fixed-fee rate, which will be binding for all CLINs AND ALL years. The rate will be binding for both completion and level-of-effort type CLINs.

The proposed (binding) fixed-fee rate will be applied to the total cost (less COM) proposed/negotiated for each task order issued under the basic contract. The purpose of having a binding fee, established through competition of this procurement, is to facilitate timely negotiations. This is also the main purpose of having “loaded labor rates” during the base year.

The proposed fee should be based on the average complexity of the tasks contained in the Performance Work Statement (PWS). The tasks in the PWS vary in complexity, however the range in complexity is not very significant. Some Task Orders may be more complex than others. However, the overall risk to the contractor on a cost-type contract is very minor.

The total evaluated cost plus fixed fee is determined using the following steps:

Step 1: Determine the total evaluated cost (TEC) based on the formula in M-3.3.1.3.

Step 2: Apply the Offeror’s proposed fixed fee percentage to the TEC

Note: the Offeror’s proposed fixed-fee rate for all Sample Tasks should be the same as the rate proposed IAW L.3.3.4.