FIELD_ORDER.pdf

PDF 34 KB Posted

Attached to
2027 Rock Salt for Drinking Water Softening
Solicitation number
IFB-2026-010
Issued by
Hamilton County, Indiana

About this file

This is a Field Order document issued by the City of Carmel, Indiana, serving as a directive for the contractor to execute work that interprets contract documents or implements minor changes without altering the contract price or timeline. The Field Order form provides space for project identification, including the field order number, date, project name, and project number, along with a description section and attachments area. The document is designed to authorize work modifications that do not require financial or schedule adjustments, with instructions that any changes deemed to require modifications to contract price or contract time must be submitted as an itemized proposal to the Engineer for evaluation and potential supersession by a formal Change Order.

The Field Order references the related contract opportunity for 2027 Rock Salt for Drinking Water Softening, for which the City of Carmel's Board of Public Works and Safety was accepting sealed bids through the City's e-Procurement Portal with a deadline of 8:00 am on Wednesday, August 19, 2026. The procurement called for approximately 8,000 tons of Coarse Southern United States Rock Salt meeting American Water Works Association (AWWA) specification B200-22 and NSF60 compliance standards, with material required to be clean and free of dirt and debris for use in drinking water softening applications.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF CARMEL

OWNER: CITY OF CARMEL

FIELD ORDER NUMBER

DATE:

PROJECT NAME:

PROJECT NO:

You are hereby directed to execute promptly this Field Order which interprets the Contract Documents or orders minor changes in the Work without change in Contract Price or Contract Time.

If you consider that a change in Contract Price or Contract Time is required, please submit your itemized proposal to the ENGINEER immediately and before proceeding with this Work. If your proposal is found to be satisfactory and in proper order, this Field Order will in that event be superseded by a Change Order.

Description:

Attachments:

ENGINEER:

Approved By: _______________________________________ Owners Representative

Date: ___________________________________