Attachment_L-8 _Seed_Project_Pricing_Sheet.pdf
PDF 62 KB Posted
- Attached to
- Facilities Acquisitions for Restoration and Modernization (FARM) Federal contract opportunity
- Solicitation number
- FA9101-16-R-0100
About this file
Attachment L-8 Seed Project Pricing Sheet
View the file
Other files for this federal contract opportunity
Show all 50
Facilities Acquisitions for Restoration and Modernization (FARM) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FARM
FA9101-16-R-0100
Attachment 8
ATTACHMENT L-8
SEED PROJECT PRICING SHEET
SEED PROJECT
QUANTITY
UNIT
PRICE
1. Repair (Replace) Suction Valves, SPS
Order of Magnitude: Between $1,000,000 and $5,000,000
Lot
2. Repair 161kV Circuit Switchers (Base Bid and Option 3 Only) NOTE: Do NOT include Options 1, 2, and 4
Order of Magnitude: Between $250,000 and $500,000
3. Replace Boilers 2, 3, and 4 Air Systems Steam Plant A
Order of Magnitude: Between $1,000,000 and $5,000,000
4. Replace Unit Sub 1, Model Shop
Order of Magnitude: Between $250,000 and $500,000
TOTAL