Section J - Attachment 24
View the file
Other files for this federal contract opportunity
Show all 50
Shared Early Warning System (SEWS) II has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Support Incentive Fee
| Target Cost: | $3,500,000 | Minimum Fee: | $105,000 | ||
| Target Fee: | $210,000 | ||||
| Fee % | Cybersecurity Assessment | Degraded System Resolution | System Outage Restoral | Maximum Fee: | $315,000 |
| 3.00% |
SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: Minimum fee percentage
| more than 6% difference between contractor and independent verification (min fee) | resolves less than 90% without gov intervention (min fee) | Contractor RR is more than 65% but less than 70% (min fee) | |||
| 4.00% | more than 5% but less than 6% difference between contractor and independent verification | resolves less than 91% but more than 90% of issues without gov intervention | Contractor RR is more than 70% but less than 75% | ||
| 5.00% | more than 4% but less than 5% difference between contractor and independent verification | resolves less than 92% but more than 91% of issues without gov intervention | Contractor RR is more than 75% but less than 80% | Total Allowable Cost: | $2,900,000 |
| 6.00% |
SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: target fee percentage
| more than 3% but less than 4% difference between contractor and independent verification (target fee) | resolves less than 94% but more than 92% of issues without gov intervention (target fee) | Contractor RR is more than 80% but less than 85% (target fee) | |||||||
| 7.00% | more than 2% but less than 3% difference between contractor and independent verification | resolves less than 96% but more than 94% of issues without gov intervention | Contractor RR is more than 85% but less than 90% | ||||||
| 8.00% | more than 1% but less than 2% difference between contractor and independent verification | resolves less than 98% but more than 96% of issues without Gov intervention | Contractor RR is more than 90% but less than 95% | Percent Earned | Value | ||||
| 9.00% | |||||||||
| SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: max fee percentage | less than 1% difference between contractor and independent verification (max fee) | resolves 100% of issues without Gov intervention (max fee) | Contractor RR is more than 95% (max fee) | Performance Incentive Fee Earned (Cyber): | more than 3% but less than 4% | 6% | $52,500 | ||
| Performance Incentive Fee Earned (DSR) | less than 94% but more than 92% | 6% | $52,500 | ||||||
| Performance Incentive Fee Earned (SOR) | more than 80% but less than 85% | 6% | $52,500 |
Cost Incentive Fee Earned: $78,750
Performance Incentive Fee Earned: $157,500
| Total Incentive Fee Earned (before NFI Deductions): | $236,250 |
| NFI Deductions | $0 |
| Total Incentive Fee less NFI Deductions | $236,250 |
| Total Government Payment | $3,136,250 |
| Total Actual Fee Percentage (Allowable Cost) | 8.15% |
| Percentage of Fee Pool Breakout | Min | TF | Max | |||||||
| Total Percent of Fee Pool | 100.00% | $105,000 | $140,000 | $175,000 | $210,000 | $245,000 | $280,000 | $315,000 | ||
| Performance Fee: | 75.00% | |||||||||
| SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: The percentages for the QPIs that contribute to the performance fee have to equal 100% of the 75%. | $78,750 | $105,000 | $131,250 | $157,500 | $183,750 | $210,000 | $236,250 | |||
| Cybersecurity Assessment | 33.33% |
SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: 33.333% of the Performance incentive fee pool will be 25% of the overall fee pool
| $26,250 | $35,000 | $43,750 | $52,500 | $61,250 | $70,000 | $78,750 |
| Degraded System Resoultion | 33.33% |
SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: 33.333% of the Performance incentive fee pool will be 25% of the overall fee pool
| SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: max fee percentage | $26,250 | $35,000 | $43,750 | $52,500 | $61,250 | $70,000 | $78,750 | |
| System Outage Restoral | 33.33% |
SLATTERY, MELANIE R CTR USAF AFMC AFLCMC/HBQN: 33.333% of the Performance incentive fee pool will be 25% of the overall fee pool
| $26,250 | $35,000 | $43,750 | $52,500 | $61,250 | $70,000 | $78,750 | |
| Cost Fee Pool: | 25.00% | $26,250 | $52,500 | $78,750 |
Sheet2
| Cybersecurity Assessment | Degraded System Resolution | System Outage Restoral |
| more than 6% | less than 90% | more than 65% but less than 70% |
| more than 5% but less than 6% | less than 91% but more than 90% | more than 70% but less than 75% |
| more than 4% but less than 5% | less than 92% but more than 91% | more than 75% but less than 80% |
| more than 3% but less than 4% | less than 94% but more than 92% | more than 80% but less than 85% |
| more than 2% but less than 3% | less than 96% but more than 94% | more than 85% but less than 90% |
| more than 1% but less than 2% | less than 98% but more than 96% | more than 90% but less than 95% |
| less than 1% | 100% | more than 95% |