This file is a Questions and Answers (Q&A) document providing clarifications and follow-up responses to the Tinker Air Force Base 2026 Multiple Award Construction Contract (MACC) solicitation (FA8137-26-R-0040). The document addresses numerous inquiries from prospective offerors regarding proposal submission requirements, work sample criteria, staffing qualifications, certifications, scoring methodology, and administrative procedures. Key clarifications include: (1) work samples performed by joint venture members or predecessor joint ventures satisfy the requirement for at least five samples performed by the proposing legal entity as prime contractor; (2) for the Small Business pool, Category 1 scoring for projects exceeding $5 million will be scored the same as projects in the $5 million to $10 million range; (3) work sample project values are based on original award amounts plus any unfunded options, excluding executed modifications; (4) design-build projects submitted for Category 5 have no page limits when documentation is provided; (5) staffing position documentation requirements vary, with Contract Program Manager, Design Program Manager, and Superintendent limited to 3-page resumes, Quality Control Manager to 5 pages, and Site Safety and Health Officer to 15 pages total.
The Q&A further clarifies that CMMC Level 1 certification is required for initial IDIQ award (with higher levels potentially required for task orders), teaming agreements are required only for subcontractors whose personnel or qualifications are relied upon for self-scoring, one electronic proposal submission is sufficient (no separate copy required), and 30 MB is the attachment size limit with DoD SAFE link available upon request. Multiple responses indicate that a forthcoming amendment will address inconsistencies in Section L and Section M, provide corrected self-scoring and cross-reference matrices, revise page limits for Quality Control Manager and Site Safety and Health Officer positions, clarify Volume II file organization and naming conventions, and update specification requirements. The Government states that proposal due dates will be determined after the amendment is published, and the document notes that numerous questions reference pending amendments that will substantially revise submission requirements affecting work sample selection, self-scoring methodology, and staffing documentation. No offer guarantee is required for the base IDIQ award.
View the file
Other files
Show 40 more
Latest 50 of 79 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Follow-Up Q&A
| Original Referenced Question | Question | Answer |
| 61 | May qualifying projects performed as prime contractor by either joint venture member satisfy the requirement in Response 61 that at least five work samples be performed by the proposing legal entity? | Projects performed by the J/V or or by the J/V Team members will be accepted as being performed by 'prime offeror' or the 'legal entity' |
| 61 | Response 61 states that at least five work samples must have been performed by the “proposing legal entity” as prime contractor. Response 151 states that Category 5 design-build experience must be demonstrated exclusively by the “Prime Offeror.” (Redacted) is an unpopulated SBA mentor-protégé joint venture. Its members performed qualifying prime contracts before formation of the joint venture, and Section L, Paragraph 4.3.3 permits work samples performed by joint venture partners. | Projects performed by the J/V or or by the J/V Team members will be accepted as being performed by 'prime offeror' or the 'legal entity' |
| NR | May a qualifying design-build project performed as prime contractor by a joint venture member satisfy Category 5, or must the design-build contract have been awarded directly to the joint venture entity? | Projects performed by the J/V or or by the J/V Team members will be accepted as being performed by 'prime offeror' or the 'legal entity' |
| New? | Reference: Section 4, Category 7 – Staffing; Attachment 2c, Appendix C, MACC SB Self-Scoring Matrix, dated 06 May 2026; Paragraph 5.1.4.2, Architects/Engineers |
Paragraph 5.1.4.2 of the Self-Scoring Matrix provides the following scoring criteria for Architects/Engineers (A/E):
| • | 1–3 A/E personnel = 100 points |
| • | Greater than 3 A/E personnel = 200 points |
Please clarify the documentation required to receive the maximum 200 points for this criterion. Specifically, does “>3 A/E” mean that an Offeror must demonstrate a total of at least four (4) qualified A/E personnel across the required A/E disciplines and submit resumes for those individuals, or is the Offeror required to demonstrate at least four (4) qualified individuals for each A/E discipline/position?
For example, to receive the maximum 200 points, would the Offeror submit a total of four or more A/E resumes representing the required disciplines, or would the Government require four or more Mechanical Engineers, four or more Electrical Engineers, four or more Civil Engineers, four or more Architects, etc.?
| Please confirm the number of A/E personnel and corresponding resumes required to substantiate the “>3 A/E” criterion and receive the maximum 200 points. | Offeror to provide resumes/licenses for 4 credentialed professionals to receive maximum points. Additional can be provided, but is not necessary to receive full points | |
| NR | Question tied to the Government's posted response regarding Section L, Paragraph 4.3.3 (the RFI asking whether at least five samples must have been performed by the proposing legal entity as prime contractor). The Government's answer confirmed that at least five of the total work samples must have been performed by the proposing legal entity as prime, in the context of parent, affiliate, subsidiary, and joint venture relationships. |
That answer addressed the parent, affiliate, and subsidiary structure but did not address how the five-sample requirement applies when the proposing legal entity is itself a joint venture. SBA regulations at 13 CFR 121.103(h) limit the period during which a joint venture may receive new contract awards. A compliant small business joint venture is therefore a recently formed entity and cannot have performed five projects as prime contractor that were awarded on or after 1 May 2021, performed for at least six months, and at least 80% complete as of the RFP date. Applying the posted answer to the joint venture entity itself would categorically exclude joint venture offerors, which conflicts with Paragraph 4.3.3's express allowance for joint ventures, Paragraph 3.4 item 7's provisions for prior joint ventures, and Paragraph 3.4's joint venture submission requirements.
| Follow-up question: For a joint venture offeror, please confirm that work samples performed by either joint venture member as Prime Contractor, or by a prior joint venture composed of the same members as Prime Contractor and documented in accordance with Paragraph 3.4 item 7, satisfy Paragraph 4.3.3, and that the five-sample requirement is met by samples performed by the joint venture members or such a prior joint venture, without requiring five samples performed by the offering joint venture entity itself. | Projects performed by the J/V or or by the J/V Team members will be accepted as being performed by 'prime offeror' or the 'legal entity' | ||
| 156 | RFI response #156 of the 9/16/2026 file indicates “The page limit cap will remain at 30 pages” for the work sample documentation. However, the Government has continually acknowledged that the burden of proof rests on Offerors. Not being given adequate space to substantiate claimed points puts Offerors in a precarious position of hoping the Government makes do with information that made the cut due to page restrictions. In other words, lesser page allocation means lesser space to provide objective documentation, forcing USAF to make subjective inferences (e.g., believing certain BLS trades exist based on a brief SOW description or mere citation of a CSI division in the specs table of contents). Kindly reconsider increasing the page limits to 60 pages per work sample (excluding the 3-page cover sheet) to make room for requested contract documents and substantive proof. | there will be no change to the 30 page limit. Governments intent is that the contractor will provide relevant pages from the documents included in the work package, not the entire document (i.e. an entire contract document is not required when the necessary information can be obtained from the cover/signature page. | |
| RFI response #156 of the 9/16/2026 file indicates “The page limit cap will remain at 30 pages” for the work sample documentation. This expressly negates USAF’s original position from the 9-month long presolicitation phase (where presol RFI Responses #15 and 25 say there would be no page limits on the documentation). If the preceding request of a 60-page limit is not approved, please consider granting relief by allowing screenshot excerpts of official forms to fit all proof within 30 pages. | |||
| 87 | RFI response #87 of the 9/16/2026 file indicates that the cross-reference matrix should be submitted as a three-page PDF. It is very likely the template is printing to three pages because there are no inputs on Columns D (Deliverables), F (Reference), and G (Clarifications) to expand the horizontal and vertical widths. Please consider the following: | RFI response #87 is referring the self-scoring matrix, not the cross-reference matrix. Per Attachment 2 - Section L, Table 2 the cross-reference matrix has no page limit. | |
| a. Based on the above fact, USAF should remove the page limit for the cross-reference matrix to allow offerors to cite relevant documentation as accurately as possible. | |||
| b. If USAF insists on a three-page limit, confirm that USAF is aware the resulting PDFs may not be legible, and that Offerors cannot be penalized for such (i.e., deemed noncompliant). | |||
| 152 | Follow up to RFI No. 152: The response concludes with “Alternatively, the Offeror may submit one additional Work Package for a Design Build project.” It appears that the maximum possible number of work sample projects to submit comprise the ten (10) work samples plus an 11th design-build project to score ourselves against for Section 2. Could USAF confirm if we are interpreting the RFI response correctly or not? Please explicitly state the maximum number of work samples offerors can submit relative to RFI Response #152. | For the small business self-scoring matrix, provide the following: |
- For Section 1, catagories 1-4, offerors shall submit from 1-10 projects -For Section 2, Category 5, offerors shall submit 1 project. This project may be one of the projects submitted for section 1 (up to 10 projects total) or may be a new project (up to 11 projects total).
For the full & open self-scoring matrix, provide the following:
- For Section 1, catagories 1-4, offerors shall submit from 1-6 projects.
-For Section 2, Category 5, offerors shall submit 1-2 projects. These may 2 projects submitted for section 1 (6 projects total); a combination of a section 1 project and a new project (7 projects total); or 2 new projects (8 projects total).
Note that for the F&O, only one full design package must be submitted for section 2.
| multi | Multiple RFI responses indicate that the “Government recognizes that the naming convention, page numbering, and file organization for Volume II is confusing. This issue will be addressed in a future amendment.” All these factors (i.e., convention, numbering, and organization) directly impact the citation of proof in the cross-reference matrix. Please consider a three-week extension from the day that the amended solicitation files have ironed out all discrepancies. | Proposal due dates will be determined after completion/publishing of the referenced amedment. |
| 9 | Follow up to RFI No. 9: Please confirm that the same individual and credentials presented to meet the requirements for 5.1.3.3. Certification for Safety Professionals, can also be provided to meet the requirements of 5.1.4.5. Site Safety and Health Officer (Level 1 or 2 as appropriate). | The same individual may be used for 5.1.3.3 and 5.1.4.5. Credentials may be used for both, as long as they meet the requirements for both; i.e. a course for certification as a safety professional may be used as continuing education required for level 1 and 2 SSHOs, as long as it occurs within the time frames specified by EM 385-1-1 |
| 10 | Follow up to RFI No. 10: Please confirm that the same individual and credentials presented to meet the requirements for 5.1.3.4. Certification for Quality Professionals, can also be provided to meet the requirements of 5.1.4.4. Quality Control Manager. | The same individual may be used for 5.1.3.4 and 5.1.4.4. Credentials may be used for both, as long as they meet the requirements for both. |
| Multi | Follow up to RFI No. 13, 14, 15: Throughout overall RFI responses, the Government provides varying answers regarding the page limitations for the Credentials and Staffing Self Scoring sections. Without a conformed copy of Section L with clear guidelines, offerors remain concerned that they are misinterpreting these answers and our documentation for each position is at risk of not be accepted. For example, based on the answer to question 13, a 2-page limit for certifications is reinforced. However, with the responses to questions 14 and 15, the Government recognizes the need to have expanded page limitations to establish the credentials of the Safety Professional and Quality Professional in Certifications/Licenses - Category 6. We remain confused as to whether the same expanded page limits apply to the Quality Control Manager and Site Safety and Health Officer in Staffing - Category 7 where a 3-page limit was originally required and still appears throughout some RFI responses (such as No. 116 and 119). Determining what documentation to compile and submit will take time and not having definitive answers will require additional time for offerors to prepare their submissions. | Certifications (Section 6) are in addition to and will be considered separately from Qualifications (Section 7), which establish minimum requirements. |
If an individual will be used for both sections, provide a separate submittal for each section, conforming to the page limits established for each section/position in these RFRI responses an the future amendment.
| 14 | Follow up to RFI No. 14: Based on the information provided in the response to RFI No. 14, please confirm that the only documentation required for 5.1.4.3. Contract Program Manager, 5.1.4.6. Design Program Manager, and 5.1.4.7. Superintendents is a resume (up to 3 pages) meeting the position requirements. If additional information is required, please specify and increase the required page limitations accordingly. | For the positions of Contract Program Manager, Design Program Manager, and Superintendent, a resume (of up to 3 pages) documenting the position requirements will be sufficient. |
| 21 | Follow up to RFI No. 21: RFI No. 14 states that a resume (limited to 3 pages) is sufficient to establish the qualifications of the Design Program Manager. Is a copy of the Design Program Manager's licensure required, and, if so, is it in addition to the 3-page limit? | For the position of Design Program Manager, include the license number(s)/state(s) that the individual is licensed in as part of the resume. |
| 129 | Follow up to RFI No. 129: The response to this question indicates that the “Resumes will be required to evaluate the ‘knowledge and experience’ of the submitted individuals.” Will the evaluation of these resumes be on a pass/fail basis based on the requirements provided in the solicitation documents for these positions? Can offerors expect that if resumes presented meet the minimum qualifications for these positions, that we will receive the full allotment of points on the Self-Scoring matrix? | Resumes will be evaluated on a pass/fail basis. Resumes that meet the minimum qualifications for the position will will be considered a pass for the purposes of scoring. |
| 31 | Follow up to RFI No. 31: The answer to this question appears to invalidate the information provided in previous RFI responses, such as No. 14, regarding the page limitation for the documentation to establish Certifications/Licenses. These varying responses within the RFIs create confusion and an inability for offerors to prepare and finalize their submissions. Will the Government be issuing conformed copies of the solicitation documents so that offerors have clarity on these specific requirements? | Certifications (Section 6) are in addition to and will be considered separately from Qualifications (Section 7), which establish minimum requirements. |
Reference the response to RFI No. 18 for items that will be considered to meet the requiremnt for a Safety/Quality Control Professional.
| Multi | Follow up to RFI No. 36, 44, 46, 51, 92, 101, 114: Recognizing this confusion and the need for a forthcoming amendment causes rework on the part of offerors, please provide an adequate extension to the proposal due date to allow time for rework and reconfiguration of submission files. | Proposal due dates will be determined after completion/publishing of the referenced amedment. |
| Multi | Follow up to RFI No. 119 and 124: Does the 3/person/position apply to SSHOs and QCMs? This contrasts with the page limitations provided in response to RFI No. 14. Three pages isn't sufficient to demonstrate the credentials of these positions as recognized in previous RFI responses. Additionally, the response to RFI No. 124 contradicts the response to RFI No. 119. Please confirm the expanded page limitations for the QCM and SSHO positions. Until offerors receive definitive guidance on these questions, we are unable to move forward with our submissions. | For Section 7, the positions of Contract Program Manager, Design Program Manager, and Superintendent, are limited to 3 page resume documenting the position requirements. |
For the position of Quality Control Manager and SSHO, the page limit requirements will be revised to reflect the additional documentation required to verify qualifications.
Revised page limits will be included in a future amendment.
| 130 | Follow up to RFI No. 130: Please clarify if the copies of current professional licenses for Architects/Engineers is in addition to the 3-page limit for resumes. | Submission is limited to 3 page/individual. Include the license number(s)/state(s) that the individual is licensed in as part of the resume. | |
| Multi | Follow up to RFI No. 132, 172, 173: Will the Government be issuing an updated Self Scoring matrix that removes the Category 7 allowance that previously employed positions (as of May 2021) will be accepted as valid? | Yes, a revised Self Scoring Matrix will be included in a future amendment. | |
| 167 | Follow up to RFI No. 167: Regarding the documentation required to validate Trade/Construction Laborers, can this information be provided in a list format, demonstrating employee labor classifications and employment status? | A company generated employee roster identifying each employee, trade/classification, and date of hire will be sufficient. | |
| 176 | Follow up to RFI No. 176: Will a revised Section L be issued to capture all of these clarifications? There still appears to be inconsistencies throughout the RFI responses so offerors are uneasy with what is acceptable and what is not. Please provide offerors with sufficient time to adapt and adjust once the revisions are validated via a conformed copy of Section L. | Yes, A revised Section L will be issued in a future amendment | |
| 146 | 1. Question 146: Given the decision to retain the 60% metric for roofing projects is the government open to removing the dollar value restriction on this category? Given Tinker AFB’s own stance, as noted at prior Industry Day events, on procuring roofing work via roofing specific IDIQs, the contractor feels that this requirement is too restrictive to be fairly competitive for small businesses, especially given the limited time cutoff for projects. Again, most small business GCs do not enter into roofing-specific contracts with the federal government; those opportunities are normally awarded directly to roofing / specialty trade contractors. | The purpose of Category 4 is for offerors to demonstrate a breadth of experience; it is not anticipated that every offeror will be able to provide a project for every type of specialized construction, nor is it necessary to achieve the minimum score. Doller value restrictions (> $1M) will not be revised. | |
| 147 | 1. Question 147: If a work sample provided for this specialized construction category, or any for that matter, meaningfully meets the scope requirements but is under the $1M dollar value threshold, is this considered unresponsive and worth 0 points on the self scoring matrix? Or if a project satisfies the scope requirement but is valued at less than $1M, does it score partial points in the category? For example would a $500k fire suppression project on a military base receive partial points (50%) or 0 points in this scenario on the self scoring matrix? | Points are awarded on an all or nothing basis; partial point will not be awarded for for work samples that do not meet the minimum ($1M) threshold. | |
| 157 | 1. Question 157: Can the government further clarify this point? Is there any reason that a work sample’s contract value should not include government approved modifications? The contractor believes that basing a work sample’s contract value on the award value alone not only misrepresents the true (total) value of the contract, it is an unfair point that will limit competition. | There are a number of reasons that a contract's monetary value could be modified that have that are not related to the scope of the work being performed; therefore, to ensure fair and equitable comparison, only original contract value plus any unfunded options (awarded at a later date or not) will be considered. | |
| 67 | 4. | Question 67: Given that the government is not open to changing the past performance window, is the government at least amenable to changing the requirement from “awarded on…” to “completed on or after May 2021”? The contractor feels that this language around “awarded on or after…” significantly limits the pool of available past performance to a window of more like 3.5-4 years (or less for longer duration projects) when you take into account the additional requirement of 80% complete and over $1M. | The criteria for submitted projects will revised to include projects that were completed after May 2021 OR are at least 80% at the time of the solicitation. |
| 143 | Question 143: Pending the answers to the previously noted follow ups the contractors proposal is unable to meaningfully progress. Is the government willing to offer a short extension to the due date to accommodate for incorporating the posted Q&A as well as the pending follow ups? | Proposal due dates will be determined after completion/publishing of the referenced amedment. | |
| 28 | In RFI Response #28 it states OK licensure will be required for any credentialed professional signing/sealing Issued for Construction (IFC) Drawings. It is our understanding that per FAR Clause 52.236, architects/engineers performing work at a Federal location may be registered in any State. Will you consider revising your requirement to allow architects/engineers licensed in other states to sign IFC drawings for task orders forthcoming from this contract? | RFO 52.236-25 states that work shall be prepared or reviewed and approved by a registered architect/engineer; it does not limit the Government from stating registration must be from a particular state.That being said, licensure from any state will be accepted for signed/sealed documents. | |
| Multi | DoD SAFE Link — Follow-up to Questions 40, 42, 90, 175, and 207: The Government stated that a DoD SAFE link may be provided upon request. Please provide instructions for requesting the DoD SAFE link. | Send requests for DoD SAFE link to the MACC Workflow: AFSC.PZIOC.MACCworkflow@us.af.mil | |
| Multi | SSHO Level 3 Documentation — Follow-up to Questions 14, 15, and 176: The Government stated that “for the position of SSHO, required documentation will be resume demonstrating relevant experience, certificate documenting required OSHA training, and documentation of required continuing education; total submission will be limited to 15 pages.” The EM 385-1-1 requirement for SSHO Level 3 does not include OSHA training or continuing education. Please clarify the documentation required for the SSHO Level 3 role. | The Level 3 role requires a person to be designated as a QP (Qualified Person) or CP (Competent Person) according to paragraph 2-2 of EM 385-1-1. Documentation showing this designation will suffice. | |
| Multi | Work-Sample Contract Value — Follow-up to Questions 64, 115, and 157: The Government stated that work samples will be based on the original award, excluding executed modifications. Will the Government reconsider this requirement and permit the value of a project to be based on the final executed contract value, including Government-authorized modifications and exercised option CLINs? | There are a number of reasons that a contract's monetary value could be modified that have that are not related to the scope of the work being performed; therefore, to ensure fair and equitable comparison, only original contract value plus any unfunded options (awarded at a later date or not) will be considered. | |
| Multi | Work-Sample Period of Performance — Follow-up to Questions 64, 115, and 157: Will the Government reconsider its response and permit the period of performance to be based on the final executed contract period, including Government-authorized modifications, exercised option periods, and approved extensions? | There are a number of reasons that a contract's monetary value could be modified that have that are not related to the scope of the work being performed; therefore, to ensure fair and equitable comparison, only original contract value plus any unfunded options (awarded at a later date or not) will be considered. | |
| Multi | Forthcoming Solicitation Amendment — Follow-up to Questions 9, 10, 11, 27, 45, 57, 107, 148, 187, 204, and 210, among others: The Government’s September 16 responses identify numerous revisions that will be incorporated through a forthcoming solicitation amendment, including revised Sections L and M, corrected self-scoring and cross-reference matrices, additional specifications, and further Volume II submission instructions. Please confirm whether these revisions will be issued as Amendment 0004 and provide the anticipated issuance date. | Date that the Amendment will be issued is TBD. |
Proposal due dates will be determined after completion/publishing of the referenced amedment.
| Multi | Proposal-Due-Date Extension — Follow-up to Questions 143, 186, and 200: The Government stated that proposal-due-date extensions would be considered and provided if deemed necessary. Based on the volume of newly issued responses, the number of forthcoming solicitation revisions, the September 21 follow-up-question deadline, and the fact that the forthcoming amendment has not yet been issued, please extend the proposal deadline to allow at least 10 business days following issuance of the amendment. | Proposal due dates will be determined after completion/publishing of the referenced amedment. |
| 193 | LEED Professional — Follow-up to Question 193: The Government confirmed that a “design firm serving as a teaming subcontractor may be used for the relevant Category 6 certifications and Category 7 personnel, including LEED Professionals, architects/engineers, and the Design Program Manager.” Please clarify whether a LEED Professional submitted under Category 6 may satisfy the Category 6 certification requirement if that individual is not also proposed under Category 7. If so, what documentation must be provided to establish that the individual is employed by either the offeror or its teaming design firm? | LEED Professional submitted under Category 6 does not have to be included in Category 7. Ducumentation required would be a brief resume and a copy of the relevant certification (subject to the page limits discussed alsewhere in the solicitation documents. |
| 175 | Sharing CUI With Teaming Partners — Follow-up to Question 175: The Government’s response explains how CUI may be submitted to the Government but does not address how offerors may share CUI with subcontractors, design firms, and teaming partners supporting proposal preparation or subsequent task-order performance. Please clarify the applicable CMMC requirements for entities that must receive or access CUI and identify the authorized methods for transmitting, accessing, and collaborating on CUI among the prime contractor and its authorized team members | For the solicitation and award of the base contract, there are no documents the Government has provided which is considered to be CUI; proposals will be handled as CUI after receipt by the Government. |
If an offeror plans to submit a work sample for a project marked CUI, then propopsals shall be transmitted via DoD SAFE.
Instructions for handling future task orders containing CUI will be addressed on a case-by-case business.
NR For Category 4 Specialized Construction, please clarify the documentation acceptable to demonstrate that the claimed specialized construction comprises at least 60% of the total project. Where the awarded contract does not separately price the specialized scope, will the Government accept an approved Schedule of Values, billing/pay applications, subcontract values, contemporaneous project cost records, or company-generated cost allocation supported in accordance with Section L 4.3.4? When the 60% calculation is value-based, should the denominator be the project's original award value, consistent with the Government's responses concerning Category 1 project value? Any of the methods will be accepted to demonstrate scope.
The denominator will be the project's original award value.
| NR | The Government states that a Category 5 Design-Build work sample has no page limit and that the Offeror shall provide the “entire design package.” Please confirm whether “entire design package” means the complete final/IFC design package applicable to the completed project—including final specifications, drawings, and calculations—or whether the Government also requires intermediate design submissions such as 35%, 65%, 95%, 100%, backcheck, and superseded design documents. | "Entire Design Package" consists of the final design deliverable, which includes, but is not limited to: Issued for Construction Drawings, Specifications, and the final desgin analysis/narrative. |
| Multi | In Responses 47, 73, 153, and 165, the Government states that projects exceeding $10 million are acceptable for the Small Business pool, but refers to the “Small Business Self Scoring Matrix (Appendix D).” Please confirm that these responses are intended to apply to Appendix C, Small Business Self-Scoring Matrix, and confirm that an otherwise qualifying Small Business project with an original award value greater than $10 million will receive the same Category 1 points as a project within the $5 million-$10 million tier. | Correct, these responses are intended to apply to Appendix C, Small Business Self-Scoring Matrix. |
Category 1 upper range will be changed to '> $5M' and will be scored the same as the previous ''$5M - $10M' range.
| Multi | Several RFI responses refer to teaming agreement documentation for Design partners, but do not explicitly identify what suffices as such. Many solicitations allow for the Designer to submit a signed Letter of Commitment (addressed to the Offeror). Will the Government accept a signed Letter of Commitment as a form of teaming agreement documentation for this solicitation? | Reference the response to original question #135 for requirements regarding Teaming Subcontractors |
| NR | The Government’s September 16, 2026 Questions and Answers identify multiple substantive revisions that will be incorporated through a future amendment, including revisions to Sections L and M, Appendices C and E, Specifications 01 35 26 and 01 45 00, staffing eligibility, Design-Build work-sample requirements, and Volume II file organization. These revisions directly affect work-sample selection and assembly, self-scoring, evidence cross-referencing, staffing documentation, and final proposal production. Please advise when the forthcoming amendment and all corrected attachments will be issued. To permit offerors adequate time to incorporate and quality-control the revised requirements, will the Government extend the proposal due date to provide a minimum of ten business days following issuance of the forthcoming amendment and corrected attachments? | Date that the Amendment will be issued is TBD. |
Proposal due dates will be determined after completion/publishing of the referenced amedment.
Multi Please confirm the following resume expectations and page limits are correct: Contract Program Manager (up to 2 resumes), Superintendent (up to 3 resumes), and Design Program Manager (up to 2 resumes): 3 pages per person per position. Quality Control Manager (up to 3 resumes): 5 pages total for all. SSHO (up to 8 total resumes):15 pages total for all. Contract Program Manager, Superintendent, and Design Program Manager are correct.
QCM and SSHO page limits are per person/resume.
Multi The Government’s responses to the Q&As repeatedly reference an amendment that will revise the proposal submission requirements in a multitude of areas, having a large impact on the proposal preparation. As of the date of this question, the referenced amendment has not been issued, and proposals are currently due in four business days. Given that offerors have not yet had the opportunity to review and incorporate the revised requirements into their proposals, we ask the Government to extend the proposal due date by a minimum of four weeks from the date the amendment is issued. Date that the Amendment will be issued is TBD.
Proposal due dates will be determined after completion/publishing of the referenced amedment.
Multi The Government’s response to solicitation questions states that the matrix provided in Appendix E is incorrect and will be revised through a forthcoming amendment. Given the complexity and level of detail required by the Appendix E matrix, as well as its significance to the overall proposal submission, adequate time is necessary for offerors to review the revised matrix and incorporate the updated requirements into their proposals. As of the date of this question, the referenced amendment has not been issued, and proposals are due in four business days. We respectfully request that the Government extend the proposal due date by a minimum of four weeks from the date the amendment containing the revised Appendix E matrix is issued. Date that the Amendment will be issued is TBD.
Proposal due dates will be determined after completion/publishing of the referenced amedment.
| 154 | Response to question 54 conflicts with responses to other questions that state the $10M threshold has been removed (i.e. 47, 153, 165). Please confirm the second requirement in section 1 of the self-scoring matrix will be revised to read, “prime contractor >$5M multiple trades. | Category 1 upper range will be changed to '> $5M' and will be scored the same as the previous ''$5M - $10M' range. |
| 157 | Response to 157: The solicitation establishes a minimum project dollar value ($1M and $5M, respectfully) for work samples for small businesses. The Solicitation does not state this is based upon the award amount, and we have selected and began working on our projects based on the current/completed contract amount. Response to 157 states, “Work samples will be based on the original award, excluding any executed modifications.” We ask the Government to consider revising this response to allow offerors to demonstrate compliance with the minimum dollar threshold based on the final construction value, inclusive of Government-directed modifications. |
On federal construction projects, the original award value may not fully represent the ultimate scope, complexity, or magnitude of the work performed. For example, funding limitations at the time of award may result in the Government initially awarding only a base scope or a limited number of options. During performance, additional funding may become available, resulting in the exercise of additional work or the issuance of substantial modifications that materially increase the construction scope and contract value.
| Excluding these projects solely because their original award value was below the stated threshold may exclude relevant projects whose final scope, complexity, and construction value meet or exceed the Government’s experience requirements. We respectfully request that the Government permit the final construction value, including Government-directed modifications, to be used when determining whether a project satisfies the minimum dollar threshold for work sample eligibility. Limiting projects to the award amount only severely limits small business competition. | There are a number of reasons that a contract's monetary value could be modified that have that are not related to the scope of the work being performed; therefore, to ensure fair and equitable comparison, only original contract value plus any unfunded options (awarded at a later date or not) will be considered. | ||
| 184 | Response 184: The government response states that a sister subsidiary or affiliate is not considered as part of the prime offeror, and it is noted in response 61, that at least 5 samples must be performed by the proposing legal entity as prime contractor. For a newly established NHO-owned 8(a) company, would the Government consider the past performance of its recently graduated sister company (within last 6 months). The Prime offeror will utilize the same critical management and leadership personnel, key employees, technical personnel, corporate systems, processes, and other resources that were responsible for successful performance of the referenced contracts. Will the Government remove the requirement that the Offeror, when successfully completing the 8a program, itself provide five (5) work samples and allow a newly established NHO-owned 8(a) company to satisfy this requirement using qualifying work samples from its NHO-owned sister subsidiary whose management, workforce, technical personnel, resources, and assets will be directly and meaningfully utilized in contract performance? | Work samples performed by a sister, subsidiary, or affiliate company can and will be counted, but as stated elsewhere, the offeror (or in the case of a JV, the offeror and the JV team members) must provide a minimum number of the work samples. | |
| 33 | #33 states ‘The Government will accept any documentation that allows the government to validate 80% completion rate.’ As invoices typically trail the actual construction completion of a project by 30 – 60 days, will the USG accept project schedules which illustrate percentage of actual construction completion? | Approved 'Progress Report' (AF3065 or similar) or 'Earned Value Report' showing at least 80% completion will be accepted if invoicing showing current progress is not available | |
| 52 | #52 – The USG states project examples for the design-build project example will have no page limit. Other responses appear to contradict this, and no clarifying document has been issued. Please confirm the USG will not limit the number of pages submitted for the design-build project under Section L, Category 5 . | There will be no page limit for the Category 5 design-build project. | |
| 57 | #57 – Please confirm the minimum value of projects for design experience, $1M minimum, is based on the total value, not initial contract value, as amendments to scope are subject to A/E review, sign and seal so full liability is established. | Projects submitted for Category 2 shall have an initial contract value, plus any unfunded options (awarded at a later date or not) of $1M or greater. | |
| 76 | #76 – Would the USG accept projects that combine subcategories to qualify for the 60% threshold. Ex. A particular project with 40%=AT/FP, 15%=fire suppression/utility systems & 10%=roofing, would meet the 60% threshold through a combination of scopes. Would the USG accept that project if it is only utilized to satisfy the subcategory with the largest percentage of scope and not utilized to satisfy any other subcategories? | Subcategories cannot be combined to meet the 60% threshold. |
The purpose of Category 4 is for offerors to demonstrate a breadth of experience; it is not anticipated that every offeror will be able to provide a project for every type of specialized construction, nor is it necessary to achieve the minimum score.
| 78 | #78 – Would a specification Table of Contents be sufficient back-up documentation for any yes responses in the score sheet? Or does the USG require us to provide all pages for the entire specification section applicable? | Entire Design Package consists of the final design deliverable, which includes, but is not limited to: Issued for Construction Drawings, Specifications, and the final desgin analysis/narrative. A specification table of contents will not meet this requirement. |
| Multi | #91 & 96 – Responses ask for Section L para. 5.1.2.2 and 5.2.2.2 project examples to provide entire design package. Several of our project examples have technical specifications around a thousand pages and design calculations more than 300 pages. Can the table of contents for these portions of the design packages be submitted in lieu of all pages? | Entire Design Package consists of the final design deliverable, which includes, but is not limited to: Issued for Construction Drawings, Specifications, and the final desgin analysis/narrative (calculations). A table of contents will not meet this requirement. |
| 148 | #148 – We await the replacement table for Appendix F and will require at least 5 – 10 business days to coordinate teaming member and subcontractor credentials, resumes and experience. | Date that the Amendment will be issued is TBD. |
Proposal due dates will be determined after completion/publishing of the referenced amedment.
| 149 | #149 – Response is silent to the question regarding Category 3 multiple multi-trade projects executed in parallel. Please confirm projects other than those used in Category 1 may be used to satisfy the requirements of Category 3 multiple multi-trade projects executed in parallel. | All projects evaluated for categories 2, 3, and 4 shall utilize projects submitted for category 1. |
| 161 | #161 – Volume II page numbering cannot be determined until this clarification is issued and time must be allowed to determine the impact of the totality of responses prior to the new page numbering guidance being applied. Please provide a submission deadline extension of at least 4 weeks to allow offers time to incorporate changes required by the new guidance, revise offers, relabel/renumber Volume II (and possibly others) and resubmit. | Date that the Amendment will be issued is TBD. |
Proposal due dates will be determined after completion/publishing of the referenced amedment.
| 203 | #203 – We understand there is no offer guarantee required for the IDIQ. Is there an aggregate minimum bonding requirement for the multiple simultaneous projects executed in parallel scenario envisioned as laid out in Response #149. | No minimum individual project or agregate bonding capacity is specified. However, small business offerors should recognize that that bonding capacity that does not allow for multiple projects up to $10M will limit their ability to participate in the MACC. | |
| NR | Would you please clarify whether the "60% threshold" or "TCV over $1M" takes priority? For example, if we have a $40M project with $1M of fire suppression, the project meets the TCV of over $1M, but does not meet the 60% of total project threshold. Would such a project be considered compliant? | The 60% threshold takes priority. | |
| 118 | #118 EM 385-1-1 defines the qualifications for SSHO level I as: | ||
| • | OSHA 30‑hour + 24 hrs competency training every 3 years. | ||
| • | ≥5 years safety experience (or 3 with qualifying degree/certification). | ||
| • | Full‑time, dedicated; no dual supervisory role |
Can the Government clarify what types of training or continuing education satisfy the “24 hours of competency training” requirement? Specifically, does this include any safety‑related continuing education completed after obtaining the OSHA 30‑hour card, or are there specific types or categories of training required? Types of courses/training that will meet the competency training requirement:
- Formal SOH Courses: Online or classroom courses focusing on EM 385-1-1 topics (such as Fall Protection, Confined Spaces, Excavation, and Electrical Safety)
- EM 385-1-1 Refresher courses covering USACE standards
- SOH Instructorship: Time spent preparing and instructing SOH-related courses
- Professional SOH Activities: Writing professional safety and health articles, teaching classes, or participating in professional safety organization meetings NR Two questions:
1. Will the credentialed professionals be part of the org chart, since they are not mentioned on DD Form 1423?
2. Will these positions require a resume? The Design Program Manager is the only 'credentialed professional' who must appear on the org chart.
Credentialed professionals (Architects/engineers) for category 7 will require a brief resume to establish they are an employee of the offeror or a teaming subcontractor. Include license information within the resume
| 31 | The last sentence indicates we can make the documentation small enough to fit within the two page limit. Is that your intent? | Documentation can be shrunk if necessary to fit within the two page limit, however, the documentation must still be legible. |
| 52 | See question 55 for page count on D/B projects. | There is no limit on the page count for the Category 5 desgin build project. |
| NR | We understand the D/B project does not have a page count. If we elect to use D/B projects for Section 1 projects and to provide sufficient documentation you want, then will those D/B for Section 1 have no page limits? | A project from Section 1, Category 1 may be used for Section 2, Category 5. In this case, the project will have no page limit. |
Alternatively, a project separate from those submitted for Section 1 may be submitted to meet the DB requirment.
| NR | Many projects have options that increase the funding and are not part of the original award amount. However, these projects may exceed a threshold if the options exercised are included. Please consider changing the "current total contract value" to the final contract amount, which will match the documentation. | There are a number of reasons that a contract's monetary value could be modified that have that are not related to the scope of the work being performed; therefore, to ensure fair and equitable comparison, only original contract value plus any unfunded options (awarded at a later date or not) will be considered. |
| 55 | If we have multiple D/B projects used in Section 1 work samples, will those D/B work samples for Section 1 not be subject to the 30 page limit? (see Q 55 also) | Only a section 1 project also being used for Section 2 will have no page limit; any other DB projects submitted for Section 1 will be subject to the page limit. |
| 96 | As we interpret the answer to this question it applies to any D/B? Please confirm? | The response to question 96 aplis only to the DB project used submitted to satisfy the requirements of category 5. |
| NR | The documentation for a work sample is just for the original award and does not include any MODs or other documentation for time extensions, etc? Please confirm that is the intent. | the value of Work samples are limited to original award plus any unfunded options in the original proposal. |
| Multi | There are many answers that refer to a forth coming amendment. With these questions being asked by Sept. 21st and the proposal is due on the 25th, please consider at least a 14 day extension, since it will take us that long to adjust our proposal, do our internal reviews and make a final executive review. | Date that the Amendment will be issued is TBD. |
Proposal due dates will be determined after completion/publishing of the referenced amedment.
| 153 | To clarify what you mean by neutral for projects that exceed the $10M threshold, do you mean the same as a project that falls within the $5 to $10M range? If not then please clarify what "neutral" means. | Category 1 upper range will be changed to '> $5M' and will be scored the same as the previous ''$5M - $10M' range. |
| 166 | Please clarify if this means the original award value or the overall project value? | the value of Work samples are limited to original award plus any unfunded options in the original proposal. |
| Multi | There are many answers that refer to a forth coming amendment. With these questions being asked by Sept. 21st and the proposal is due on the 25th, please consider at least a 14 day extension, since it will take us that long to adjust our proposal, do our internal reviews and make a final executive review. | Date that the Amendment will be issued is TBD. |
Proposal due dates will be determined after completion/publishing of the referenced amedment.
| This is a question that was asked in the Aug. 25th list of Q&A However, we could not find it in the Sept. 16 issued Q&A, which had 211 questions and answers. likewise the Aug. 25th listing had 230 questions listed. We did not do a cross check, but it appears some (possibly many) of the original questions were not answered in the Sept. 16th edition. The question to the left (#122) has a direct impact on our decision to submit a full and open proposal. We suggest a cross check of the two Q&A lists to answer all questions submitted, since they may impact decisions to pursue or not. | questions missed from the original round are answered below. | ||
| 8 | • | Follow-Up to RFI #8: The Government’s response confirms that CMMC Level 1 certification is required for the initial IDIQ award. Please clarify what documentation or information must be submitted with the proposal to demonstrate compliance with this requirement. Specifically, is the Offeror required to provide its CMMC Unique Identifier (UID) or any other evidence of its CMMC Level 1 certification? | Offeror shall provide the following to document CMMC Level 1 Certification: |
-SPRS Submission screenshot. Screenshot should show 'Final Level 1 Self-Assessment" status, correct date, and applicable CAGE codes -Signed Executive Affirmation confirming the company is actively maintaining Level 1 security practices -Offeror's UID for independent confirmation by the Government.
9 • Follow-Up to RFI #9: The Government’s response states that qualifying safety credentials “include, but are not limited to” certain degrees and certificate programs, and that training used to fulfill the minimum continuing education requirements for Level 1 or Level 2 SSHOs may also be utilized for this category. Please clarify whether completion of any one qualifying degree, certificate program, or continuing education course is sufficient to receive the points available under this criterion, or whether a specific number or combination of credentials/training hours is required. Additionally, please confirm what documentation Offerors should submit to substantiate the claimed points. Certifications (Section 6) are in addition to and will be considered separately from Qualifications (Section 7), which establish minimum requirements.
Certificate or degree programs may be used as part/all of the 24 hour continuing edication requirement of EM 385-1-1, as long as they occur within the specified windows.
11 • Follow-Up to RFI #11: The Government’s response states that updated Specification 01 45 00 will be included in a future amendment. Please advise when the amendment is anticipated to be issued. Given that the revised specification contains requirements that Offerors must consider when preparing their proposals, will the Government extend the current September 25, 2026 proposal due date by 14 calendar days to October 9, 2026, to provide Offerors adequate time to review the revised requirements and incorporate any necessary changes into their proposal submissions? Date that the Amendment will be issued is TBD.
Proposal due dates will be determined after completion/publishing of the referenced amedment.