This is a Statement of Work (SOW) for a Multiple Award Construction Contract (MACC) for General Construction Services at Tinker Air Force Base, Oklahoma, effective October 2026 (Revision 4).
The contract encompasses a broad range of sustainment, maintenance, repair, alteration/renovation, and minor construction projects at Tinker AFB. Work execution follows five classification methods: Design-Build (Conventional, Fast-Track, or Progressive), Construction with Limited Design, and Construction Only. Design-Build projects require contractor-provided 100% design completion with submissions at 35%, 65%, 95%, and 100% levels, with final designs sealed by credentialed professionals licensed in Oklahoma. Construction with Limited Design involves government-provided design development (35-65%) with contractor completion to working documents. Construction Only projects receive 100% government design packages. The contractor must maintain key personnel including a Contract Program Manager (10+ years experience), Quality Control Manager (per specification 01 45 00), Site Safety and Health Officer (Level One or Two per EM 385-1-1), Project Superintendent(s) (5+ years experience, Level Three SSHO qualified), and Design Program Manager for design-build work (credentialed professional, 10+ years experience). The contract includes restrictions on concurrent key position assignments across multiple task orders. Normal work hours are 0700-1600 Monday-Friday; weekend/holiday work requires three days' written notice to the Contracting Officer at no additional cost. Contractor personnel require AFMC Form 387 badges; controlled/restricted area access requires AF Form 1199C secure area badges with background checks submitted 14 days prior. The contractor must provide performance bonds, certificates of insurance, Health and Safety Plan (within 10 days of award), Quality Control Plan, organizational charts, and quarterly progress meetings. Design submittals require TAFB Form 3000 and government review periods of 14 days for most submittals. Pre-construction submittals must be provided 10-30 days after Notice to Proceed; material submittals within 30 days. A baseline schedule using Critical Path Method and Gantt Chart format is due within 10 days of NTP, with cost loading totaling 100% of contract value and final 10% reserved for final acceptance. Progress reports are submitted weekly with percentage completion by work element. The contractor must provide as-built record drawings, Operations & Maintenance manuals and training, DD Form 1354 for real property transfer, equipment inventory lists, and warranty documentation (minimum one year on all work). Closure documentation must be submitted within the task order period of performance. All documents must follow standardized file naming conventions and be submitted electronically in PDF or AutoCAD DWG format. The contract references multiple specifications and unified facilities criteria including UFC 1-200-01 (DoD Building Code), UFC 3-600-01 (Fire Protection), UFC 3-260-02 (Airfield Pavement Design), and AFMAN 91-203 (Occupational Safety).
View the file
Other files
Show 40 more
Latest 50 of 79 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
- i -
Statement of Work
Multiple Award Construction Contract for General Construction Services
Revision: 4
Tinker Air Force Base, Oklahoma
October 2026
Prepared By:
72 ABW Civil Engineering Directorate 7535 5th Street, Building 400
Tinker AFB, OK 73145
- ii -
TABLE OF CONTENTS
1. DESCRIPTION OF WORK
1.1 Background
1.2 Program Description
1.3 Classifications of Work
1.3.1 Design-Build
1.3.2 Construction w/Limited Design
1.3.3 Construction Only
2. DEFINITIONS
2.1 Contracting Officer (CO)
2.2 Contracting Officer’s Representative (COR)
2.3 Credentialed Professional
3. PERFORMANCE CAPABILITIES
3.1 Contractor Personnel
3.1.1 General Requirements
3.1.2 Key Personnel
3.1.3 Additional Positions
3.1.4 Exceptions/Variances from Experience Requirements
3.1.5 Organizational Chart
3.2 Design/Drafting
3.3 Subcontractors
4. QUALITY CONTROL
4.1 Inspection System
4.2 Deficiency Prevention
4.3 Inspection Files
5. LOCAL OFFICE AND STAGING AREAS
5.1 Local Office
5.2 Storage/Staging Areas
6. START-UP PERIOD
7. DOCUMENT REQUIREMENTS
7.1 DOCUMENT FORMAT
7.1.1 Specifications/Reports/Material Submittals
7.1.2 Drawings
7.2 FILE NAMING CONVENTIONS
8. CORRESPONDENCE
9. COMMUNICATION
10. ORDERING PROCEDURES
10.1 Fair Opportunity Proposal Request (FOPR)
10.2 Project Documents
10.3 Site Visit
10.4 Contractor’s Proposal
10.4.1 Proposal Package .................................................... Error! Bookmark not defined.
10.4.2 Cover Sheet ............................................................. Error! Bookmark not defined.
10.4.3 Project Narrative ..................................................... Error! Bookmark not defined.
10.4.4 Cost Proposal .......................................................... Error! Bookmark not defined.
10.4.5 Proposal Supporting Documentation...................... Error! Bookmark not defined.
- iii -
10.4.6 Proposed Schedule .................................................. Error! Bookmark not defined.
10.4.7 Supporting Personnel .............................................. Error! Bookmark not defined.
10.5 Interchanges ......................................................................... Error! Bookmark not defined.
10.6 Proposal Evaluation .............................................................. Error! Bookmark not defined.
10.6.1 Low Price Evaluation ............................................... Error! Bookmark not defined.
10.6.2 Technical Acceptability ........................................... Error! Bookmark not defined.
10.7 Proposals for Projects in Advance of Funding...................... Error! Bookmark not defined.
10.8 Task Order Award
11. COMMENCEMENT, PROSECUTION, COMPLETION AND PAYMENT FOR WORK
11.1 Order of Precedence
11.2 Notice to Proceed (NTP)
11.3 Task Order Schedule
11.3.1 Schedule Format
11.3.2 Schedule Updates
11.3.3 Coordinating With Government Activities
11.4 Task Order Progress Reporting
11.5 DESIGN REQUIREMENTS
11.5.1 General
11.5.2 Civil
11.5.3 Architectural
11.5.4 Structural
11.5.5 Mechanical
11.5.6 Electrical
11.5.7 Fire Protection
11.6 Design Submittals
11.6.1 Preliminary Design (35% Design)
11.6.2 Intermediate Design (65% Design)
11.6.3 Pre-Final Design (95% Design)
11.6.4 Final Design (100% Design)
11.7 Jobsite Verification / Government-Furnished Record Drawings
11.8 Submittals
11.8.1 Submittal Register
11.8.2 Master Submittal List
11.8.3 Material Samples
11.9 Inspection by the Government
11.10 Field Changes
11.11 Meetings
11.11.1 Post-Award Conference
11.11.2 Quality Control Coordination Meeting
11.11.3 Initial Design Conference
11.11.4 Architectural/Engineering Review Panel
11.11.5 Design Review Conference(s)
11.11.6 Pre-Construction Meeting
11.11.7 Progress Meetings
11.12 Completion Inspections
11.13 Task Order Completion
- iv -
11.14 Record Drawings
11.14.1 Working As-Built Drawings ('Redline' Set)
11.14.2 Record Drawings
11.15 Operations & Maintenance (O&M) Manuals
11.16 Operations & Maintenance (O&M) Training
11.17 Transfer and Acceptance of Military Real Property, DD Form 1354
11.18 Equipment Inventory List
11.19 Warranty
12. GOVERNMENT FURNISHED EQUIPMENT / MATERIALS (GFE/GFM)
13. WORK HOURS
13.1 Normal Duty Hours
13.2 Notes Regarding Working Hours
14. BADGES
15. CONTROLLED/RESTRICTED AREA(S)
16. WORK IN OCCUPIED AREAS
17. PROTECTION OF EXISTING UTILITIES DURING EXCAVATION
18. PROTECTION OF GOVERNMENT PROPERTY
19. OUTAGES AND CLOSURES
20. CONTRACTOR VEHICLES
20.1 Identification
20.2 Parking
20.3 Airfield
21. CONSTRUCTION SITE
21.1 Construction Fencing
21.2 Construction Signs
21.3 Barricades
22. TRANSPORTATION OF CONSTRUCTION EQUIPMENT
23. BASE FIRE REGULATIONS
24. HEALTH AND SAFETY
24.1 Commander’s Statement of Safety Intent
24.2 General Requirements
24.3 OSHA Voluntary Protection Program (VPP)
24.4 Emergency Evacuation Procedures
24.5 Mishap Reporting
25. NOISE CONTROL
26. FOREIGN OBJECT DEBRIS (FOD) AWARENESS AND PREVENTION
27. AIRFIELD SAFETY
Appendix A - Abbreviations Appendix B - Contract Specifications Table of Contents Appendix C - TAFB Facility Standards and Reference Documents Appendix D – Contract Data Requirements List (CDRLs)
- 1 -
1. DESCRIPTION OF WORK
1.1 Background
Tinker Air Force Base (TAFB) is centrally located in Oklahoma, approximately five (5) miles east of Oklahoma City, in southeast Oklahoma County. TAFB occupies about 5,500 acres of land, to include 458 buildings encompassing 18.7M square feet.
TAFB is home to the Air Force Sustainment Center (AFSC) Headquarters and includes a large industrial complex that performs overhaul functions on numerous airframes, engines, and accessories, as well as software support. TAFB is also home to three major flying wings: Air Force Air Combat Command's (ACC) 552d Air Control Wing; Navy’s Strategic Communications Wing ONE; and the Air Force Reserve Command’s (AFRC) 507th Air Refueling Wing. Other major associate Units on TAFB include the 38th Cyberspace Engineering Installation Group (CEIG) located just east of Douglas Boulevard and the Defense Logistics Agency's (DLA) Defense Distribution Center Oklahoma City.
The facilities on base range from large industrial buildings which support overhaul and testing of aircraft, aircraft parts, engines and airframes to office space, warehouses, computer facilities, dining facilities, dormitories, medical facilities, and other community support facilities such as the base exchange and commissary.
The utilities on base include but are not limited to water supply, storage, and distribution (owned and operated by the Oklahoma City Water Utilities Trust (OCWUT)); electrical distribution (owned and operated by Oklahoma Gas & Electric (OG&E)) and backup generators;
natural gas distribution; sanitary sewage (OCWUT); industrial waste sewage collection and treatment; storm sewers; facilities for the generation and distribution of steam, chilled water, and compressed air; and petroleum, oil, and lubricants (POL) storage and hydrant fueling.
1.2 Program Description
The Multiple Award Construction Contract for General Construction Services (MACC) will accomplish a broad range of sustainment, maintenance, repair, alteration/renovation, and minor construction projects affecting real property facilities at Tinker Air Force Base, Oklahoma.
Work performed will be complex in nature, require multiple construction trades, and may require engineering design performed by credentialed professionals (reference section DEFINITIONS elsewhere in this document).
1.3 Classifications of Work
Project execution methods will fall within one of the following classifications. The execution method will be defined in the project documents for each Task Order (TO) under this contract.
1.3.1 Design-Build
Under this method, the Contractor provides both the design and construction services for a project; in the Design-Build process, final design solutions are provided by the Contractor, not the Government.
The Government will provide a Statement of Work (SOW), drawings, and other preliminary documents as necessary to establish requirements for the work to be accomplished; these documents will be equivalent to a schematic (15% or greater) design. When awarded the TO for the project, the Contractor will complete the design to the 100% level, to include drawings,
- 2 -specifications, design analysis/narrative, and other documentation as required by the Government.
Design-Build projects may be further classified as follows:
• Conventional Design-Build: Contractor provides a complete design before construction activity begins.
• Fast-Track Design-Build: Contractor provides a complete design; however, construction may begin at a mutually agreed point prior to completion of the design.
In general, the Contractor will provide design development (i.e. 35-65%), pre-final (i.e. 95%), and final (Issued for Construction (IFC)) design submissions for Government review and comment.
The number of design submittals may vary for any individual TO (i.e. well-defined requirements may require fewer submissions, fast-track projects may require additional submissions to allow construction to begin before completion of the entire design). The number of design submissions will be defined in the project documents for each TO.
Issued for Construction (IFC) design submissions will be signed/sealed by credentialed professionals authorized to provide services in the State of Oklahoma.
Upon completion of the IFC design submission(s), and acceptance by the Government, the Contractor shall commence with construction in accordance with approved design and the contract requirements.
1.3.2 Progressive Design-Build
Progressive Design-Build is a phased, qualifications-based delivery method. Work may be highly complex, poorly defined, or volatile. The primary focus is collaboration, risk mitigation and price transparency. The Government values qualifications-based selection under this method.
Phase 1 (Pre-construction & Design): The Government and the design-builder work together to define the project scope, conduct site investigations, and progress the design (typically to 60% to 80% completion). Risks are collaboratively identified, priced and shared between the Contractor and the Government during Phase 1.
Phase 2 (Final Design & Construction): Once the design is sufficiently mature, the builder proposes a Guaranteed Maximum Price (GMP) or lump sum contract. Open-book pricing will be utilized.
If the Government and the Contractor cannot agree on a final price or scope at the end of Phase 1, the Government can elect not to move onto Phase 2. The Government may terminate the remainder of the contract, take ownership of the design developed to date, and solicit for the remainder of the work by other methods.
1.3.3 Accelerated Design-Build
This method focuses on shrinking procurement timelines and compressing the schedule through aggressive overlap between the design and construction phases. The Government may consolidate the acquisition schedule by issuing a single step solicitation to award a single task order as quickly as possible. The Government values best value selection under this method.
Under Accelerated Design-Build a target price, incentive, or fixed-price structure will be established by the Government as required to bypass prolonged negotiations and keep the project moving at a high rate of speed. Cost estimates are updated transparently via “open-book” pricing as the design matures. More risk is transferred to the Contractor to avoid
- 3 -construction delays. This method is utilized when uninterrupted execution is required.
Requirements for this method should be highly standardized or critical schedule-driven projects.
Construction packages (e.g., site preparation, foundation, utility rough-ins) are finalized, permitted, and built while the design team is still finalizing the structural, mechanical, and architectural blueprints.
1.3.4 Construction w/Limited Design
Under this method, the Government provides the design; the Contractor further develops portions of the design as required and provides construction services for the project. This method will generally be utilized for non-complex or repetitive work types of projects where full design cost and effort is not warranted.
The Government will provide a SOW, drawings, and other documents as necessary to establish requirements for the work to be accomplished; these documents will be equivalent to a design development submittal (35% to 65%). When awarded the TO for the project, the Contractor will complete any additional design efforts required by the project documents to produce a set of working documents (i.e. shop drawings) for use during construction.
The extent of Contractor's design effort will depend upon the complexity of each project;
generally, the design effort will not require the services of a credentialed professional. In those instances when the Government determines professional certification of the design is necessary, the requirement will be indicated in the project documents. Examples of work requiring professional certifications include but are not limited to life safety plans; fire suppression and alarm plans; cathodic protection systems; and pre-engineered structures.
Upon completion of the required working documents/submittals, and acceptance by the Government, the Contractor shall commence with construction in accordance with the approved documents and the contract requirements.
1.3.5 Construction Only
The Government will provide a 100% design package, including SOW, drawings, specifications, and other documents as necessary to establish requirements for the work to be accomplished.
When awarded the TO for the project, the Contractor shall commence with construction in accordance with the design and the contract requirements.
Note, some ‘Construction Only’ TOs will include ‘deferred design’, i.e. working documents/shop drawings produced by the Contractor, their sub-contractors, and/or equipment manufacturers;
in some instances, certification by a credentialed professional will be required. The requirement for deferred design/professional certification will be indicated in the project specifications and drawings. Examples of deferred design include but are not limited to equipment support/working platforms; fire suppression and alarm plans; pre-engineered structures; and hangar door assemblies.
2. DEFINITIONS
2.1 Contracting Officer (CO)
An individual with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.
The CO is the ONLY person authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.
- 4 -
It shall be the Contractor’s responsibility to contact the CO concerning any matters where the Contractor believes that the direction received from the COR may affect price, quality, quantity, delivery, or any other term or condition of an awarded TO prior to performing work or purchase of material. Proceeding without direction/approval from the CO could result in financial impacts (i.e. non-payment for work performed outside the original contract); delays which affect the Contractor's schedule; or termination of a TO at the Contractor's cost.
2.2 Contracting Officer’s Representative (COR)
An individual designated by the Contracting Officer to perform specific technical or administrative functions (e.g. approval of design submissions, approval of submittals, initial badging of personnel).
2.3 Credentialed Professional
An individual who (a) is licensed (i.e., professional engineer or registered architect) to practice, and (b) commands the necessary expertise, in terms of knowledge and experience, to undertake the required task. Oklahoma State Statutes, Rules and Regulations will apply to licensure, stamp and seal requirements.
2.4 Project Manager
An individual designated by the Government for the purposes of (but not limited to): primary point of contact for individual Task Orders awarded under this contract; review of Contractor’s proposals for technical acceptability; coordinating the review of contractor submittals for adherence to the contract drawings and specifications; coordination of Government responses to Contractor submitted Requests for Information (RFIs); monitoring Contractor’s progress for adherence to the approved schedule; and, as required, generating packages for supplemental agreements/change orders for individual Task Orders.
2.5 Quality Assurance Construction Inspector (QACI)
An individual designated by the Contracting Officer for the purpose of (but not limited to):
monitoring Contractor’s adherence to the submitted/approved Quality Control and Safety plans;
surveillance of materials and workmanship for adherence to the contract drawings and specifications; review of contractor submitted progress reports against observed work performed; and coordination of Contractor’s activities with the Government (e.g.
communication with building occupants, outages, utility marking, etc.).
3. PERFORMANCE CAPABILITIES
The Contractor is required to furnish all materials, labor, plant, tools, transportation, equipment, testing services, quality control, and incidentals necessary to provide a complete usable end product as specified in the TO/project documents. The final product provided by the Contractor shall conform to Government-accepted commercial/industrial quality standards with regards to fit, finish, form, and function as detailed in the TO/project documents; the Basic Contract Technical Specifications; and industry standards as typically referenced to and utilized by the trades industries.
The Contractor shall provide sufficient technical support and project management to process submittals in a timely manner; accommodate a number of concurrent 'active' projects; assure quality and safety for construction projects in progress; and perform according to schedule.
At a minimum, the Contractor shall maintain the following management and technical support capabilities at all times the Contractor has active TOs awarded under this contract.
- 5 -
3.1 Contractor Personnel
3.1.1 General Requirements
The Contractor shall ensure that employees and subcontractor employees working an awarded TO have current, valid licenses and certifications necessary to perform their functions. Any cost or time associated with obtaining licenses or certifications shall be at the Contractor’s expense.
The Contractor shall not employ any person who is or was an employee of the US Government, if the employment of that person would create a conflict of interest.
Personnel shall be easily recognized as a Contractor employee or subcontractor. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name. The badge shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times. The badge shall clearly identify the individual as a contract employee.
3.1.2 Key Personnel
The Contractor shall have the following key personnel in place when working TOs awarded under this contract.
• Key personnel may be assigned to more than one active TO, except as noted in the paragraphs below.
• One Contractor employee may hold up to two (2) key positions as noted in the table below. Contractor employees holding more than one key position must meet the minimum requirements for both positions.
Contract Prog Mgr. QCM SSHO
Design Prog. Mgr. Super
Design Proj. Mgr.
Const. Proj.
Mgr.
Contract Prog Mgr. X
QCM X
SSHO X
Design Prog. Mgr. X
Super
Design Proj. Mgr. X X
Const Proj.
Mgr. X
These restrictions are intended to apply across all work performed under the Basic Contract, not on a per TO basis, e.g. the Superintendent for one TO cannot serve as the Quality Control Manager for another TO awarded under this contract.
- 6 -
The names of the key personnel shall be designated in writing to the CO and COR upon award of the initial TO, and for each subsequent TO against this contract (reference section ORGANIZATIONAL CHART elsewhere in this document).
3.1.2.1 Contract Program Manager
The Contract Program Manager is an employee of the Prime Contractor who is responsible for the overall performance of this contract. The Contract Program Manager shall have a minimum of ten (10) years combined experience in the following positions: Project Superintendent, Quality Control Manager, Project Manager, Project Engineer, or Construction Manager with general contracting firm(s) engaged in multi-trade commercial/industrial construction. The individual must have at least two (2) years' experience as a Project/Program Manager.
If the Contract Program Manager is absent for a period longer than 24 hours, an equally-qualified alternate must be provided and must fulfill the same roles and responsibilities as the primary Contract Program Manager.
The Contract Program Manager (or Alternate) shall have direct oversight of all project planning, design, and construction activities. The Contract Program Manager shall provide overall contract management, including full authority to develop TO proposals; negotiate and sign TOs; negotiate and sign contract modifications; purchase/administer subcontracts; and shall attend all status meetings, site visits and pre-final/final acceptance inspections.
The CO must be able to contact the Contract Program Manager (or Alternate) by phone to always discuss awarded/active TOS during normal duty hours (reference section WORK HOURS elsewhere in this document).
Throughout the life of this contract, the Contract Program Manager (or Alternate) shall be available to meet with the CO at Tinker Air Force Base or online via online collaboration/ teleconference software (e.g. Microsoft Teams) during normal duty hours.
• Discussions regarding awarded/active TOs: within one (1) hour after notification by telephone.
• Discussions regarding matters outside of active TOs: within 24 hours after notification by telephone or e-mail.
3.1.2.2 Quality Control Manager (QCM)
The QCM is an employee of the Prime Contractor who is responsible for management of the Contractor Quality Control Program. The QCM shall have the minimum qualifications set forth in specification section 01 45 00, Quality Control. For the purposes of this SOW, QCM is equivalent to QC Manager in specification section 01 45 00.
The QCM must always be at the work site (i.e. Tinker AFB) while TOs are in progress, to implement and administer the Contractor's quality control program and the Government-accepted Quality Control Plan. If the QCM is off-site for a period longer than 24 hours, an equally qualified alternate QCM must be provided and must fulfill the same roles and responsibilities as the primary QCM. Alternate(s) shall be designated in writing to the CO.
The QCM, as a minimum, shall visit each active project site daily to ensure full compliance with the Contractor's quality control program. The QCM must arrive at any particular TO/project site within one (1) hour of telephone direction from the CO, COR, Contract Specialist, or QACI.
- 7 -
When the Contractor has multiple TO/projects sites, provide a separate full-time assistant QCM or QC Specialist (reference specification section 01 45 00) for each project site; the assistant/specialist may not serve as the Superintendent. A designated member of the QC organization shall be at each TO/project site at all times when work is being performed.
For additional information regarding the requirements for Contractor’s Quality Control Program, refer to specification section 01 45 00.
3.1.2.3 Site Safety and Health Officer (SSHO)
The SSHO is an employee of the Prime Contractor who is responsible for management of the Contractor Health and Safety Program. The SSHO shall meet the qualification requirements of a Level One or Two SSHO as set forth in specification section 01 35 26, Governmental Safety Requirements and U.S. Army Corps of Engineers (USACE) publication EM 385-1-1, Safety -- Safety and Occupational Health (SOH) Requirements.
The SSHO must be at the work site (i.e. Tinker AFB) at all times, while TOs are in progress, to implement and administer the Contractor's safety program and the Government-accepted Accident Prevention Plan. If the SSHO is off-site for a period longer than 24 hours, an equally qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. Alternate(s) shall be designated in writing to the CO.
The SSHO, as a minimum, shall visit each active project site daily to ensure full compliance with the Contractor's health and safety requirements. The SSHO must arrive at any particular TO/project site within one (1) hour of telephone direction from the CO, COR, Contract Specialist, or QACI.
When the Contractor has multiple TO/projects sites, provide a separate full-time Level Three SSHO for each project site; the Level Three SSHO may also serve as the Superintendent. A designated SSHO shall be at each project site at all times when work is being performed.
For purposes of this contract, a Level Three SSHO (i.e. Superintendent) is not considered to be a member of the QC organization.
3.1.2.4 Design Program Manager
The Design Program Manager will be responsible for the overall performance of the design portions of this contract; this individual may be an employee of the Prime Contractor or a subcontractor. The Design Program Manager shall be a credentialed professional; the Design Program Manager shall have a minimum of ten (10) years’ previous experience in project management, with at least five (5) of those years managing design-build programs similar to the requirements of this contract.
The Design Program Manager shall provide direct oversite and overall management of the design process, including coordinating day to day production; schedule adherence; quality control of all design submittals; verification that designs meet applicable codes and standards (including Air Force/DoW standards); review of material submittals and shop drawings; and answering construction RFIs related to the design. The Design Program Manager shall attend all design status meetings, initial pre-design meetings and site visits, and design review conferences.
- 8 -
3.1.2.5 Project Superintendent(s)
The Superintendent is an employee of the Prime Contractor who is responsible for managing and coordinating day-to-day production for each TO issued under this contract.
Qualifications for Superintendents are as follows:
1. Minimum of five (5) years’ experience in construction.
2. Minimum of two (2) years as a superintendent with general contracting firm engaged in multi-trade commercial/industrial construction.
3.Qualified as a Level Three SSHO (competent person) per specification section 01 35 26 and EM 385-1-1.
4. Experience in the areas of hazard identification and safety compliance.
The Superintendent shall be at the TO/project site at all times when work is being performed.
If the Superintendent must leave a TO/project site for any length of time, an alternate Superintendent must be provided and must fulfill the same roles and responsibilities as the primary Superintendent; subcontractors will not be used as alternates. Qualifications for alternates are the same as for the Superintendent, except:
1. Previous experience as a superintendent is not required.
2. Qualified as a Level Three SSHO (qualified person) as set forth in specification section 01 35 26 and EM 385-1-1.
3. Alternate(s) shall be designated in writing to the CO.
An individual Superintendent may be assigned to more than one TO; however, the Superintendent shall not be assigned to more than 5 active TOs unless approved by the CO.
The Superintendent shall visit each respective TO/project site daily. Alternates may only be assigned to a single TO/project site.
Superintendents shall provide on-site supervision, submit weekly progress reports for each TO; schedule and coordinate subcontractors and material suppliers; and attend all status meetings, site visits and pre-final/final inspections.
The Superintendent must arrive at any particular TO/project site within one (1) hour of telephone direction from the CO, COR, Contract Specialist, or QACI.
When the Contractor has multiple TO/projects sites, the Superintendent (or alternate) may serve as the Level Three SSHO for their respective TO/project sites (reference paragraph SITE
SAFETY AND HEALTH OFFICER).
3.1.3 Additional Positions
At the Contractor's discretion, or as directed by the CO, the following positions may be added based on the quantity and/or complexity of awarded TOs.
3.1.3.1 Design Project Manager(s) (Design PM)
Design PM will be responsible for the overall performance of the design portions of TOs issued under this contract. The Design PM shall be a credentialed professional with a minimum of five (5) years’ design experience on projects similar in size and complexity.
The Design PM shall provide direct oversite and overall management of the design process for TOs, including coordinating day to day production; schedule adherence; quality control of all design submittals; verification that designs meet applicable codes and standards (including Air
- 9 -
Force/DoW standards); review of material submittals and shop drawings; and answering construction RFIs related the design. The Design PM shall attend all TO related design status meetings, initial pre-design meetings and site visits, and design review conferences.
3.1.3.2 Construction Project Manager (Construction PM)
The Construction PM will be responsible for the overall performance of TOs issued under this contract. The Construction PM shall have a minimum of ten (10) years’ experience in construction with at least five (5) of those years as a superintendent on commercial construction projects similar in size and complexity.
The Construction PM shall have direct oversight of project planning, design, and construction activities for awarded TOs. The Construction PM shall provide overall project/TO management, including full authority to develop proposals, provide subcontract administration, review material submittals and shop drawings, and shall attend all status meetings, site visits and pre-final/final inspections.
An individual Construction PM may be assigned to more than one TO; however, the Construction PM shall not be assigned to more than 10 active TOs unless approved by the contracting officer.
The CO must be able to contact the Construction PM by phone at all times if the Contractor has active task orders under this contract. Throughout the life of an each TO, the Construction PM shall be available to meet with the CO, at Tinker Air Force Base or online via collaboration/ teleconference software (e.g. Microsoft Teams), within one (1) hour of telephone notification during normal duty hours.
3.1.4 Exceptions/Variances from Experience Requirements
Exceptions or variances to experience requirements above require prior approval from the CO or the COR. Exceptions/variances will be considered where the Contractor can demonstrate comparable experience and/or competency.
Contractor shall forward any requests for exception/variance to the CO and the COR; include resumes for each individual for whom a variance is requested, listing the qualifications to be considered (e.g., education, experience, professional certifications, etc.).
3.1.5 Organizational Chart
Within 10 days of initial TO award against contract, the Contractor shall provide an organizational chart to the CO and COR, reference attached Contract Data Requirements List (CDRL) A001 for additional information. Include names and contact information of personnel assigned to the key positions and their areas of responsibility. Provide a list of assigned TOs for each Project Superintendent/ Alternate shown on the organization chart. Clearly delineate on-site from off-site personnel.
Provide an updated organizational chart within 10 days of each subsequent TO award.
When personnel changes are required (position vacated or filled), submit resumes and a revised organization chart to the CO and the COR within five (5) business days.
3.2 Design/Drafting
The Contractor’s design staff or design subcontractor shall have multidiscipline design experience to execute a full range of design in accordance with specification section 01 33 16.00 10, Design Data (Design After Award). The Contractor’s design team shall include
- 10 -architectural and engineering personnel with experience in the following disciplines: Civil, Land Surveying, Geotechnical (Soils Engineer), Architectural, Interior Design, Landscape Architecture, Structural, Mechanical, Electrical, Fire Protection, and Environmental.
Contractor will be required to provide as-built (record) drawings in accordance with the requirements of specification section 01 78 00, Closeout Submittals.
All construction drawings, specifications, and design analysis/calculations produced by the Contractor's design consultants shall be developed under the direction of credentialed professionals currently licensed in accordance with RFO 52.236-25, Requirements for Registration for Designers. Contractor shall utilize individuals and firms that are licensed/ authorized to offer engineering or architectural services in the State of Oklahoma.
3.3 Subcontractors
All subcontractor firms shall be licensed in the State of Oklahoma for their specialty where required; Contractor shall provide a copy of these licenses as part of the QC Plan for each awarded Task Order.
4. QUALITY CONTROL
Quality control (QC) shall be executed in accordance with specification section 01 45 00. The QC program shall include, but is not limited to the following:
4.1 Inspection System
The Contractor shall establish and maintain a three-phase inspection system which monitors the execution of each task completed under this contract. The Contractor must specify the areas to be inspected on a scheduled or unscheduled basis, how often inspections will be accomplished, and titles of the individuals who will perform the inspections.
4.2 Deficiency Prevention
The Contractor shall establish a method for identifying, correcting, and preventing future recurrence of quality deficiencies; this includes deficiencies within the same TO (i.e. a deficiency addressed in an initial phase of a TO shall not recur in follow-on phases) and in future TOs awarded to the Contractor.
4.3 Inspection Files
In accordance with specification section 01 45 00, the Contractor shall maintain records for each TO of all required inspections conducted by the QCM and the necessary corrective actions taken. This documentation shall be submitted to the Government with the progress reports (reference section TASK ORDER PROGESS REPORTING) throughout the life of each TO.
5. LOCAL OFFICE AND STAGING AREAS
5.1 Local Office
A permanent on-base office space will not be provided for the Contractor’s administrative/ management personnel. Contractor owned 'job trailers' will be allowed but are subject to the requirements of the section STORAGE/STAGING AREAS below.
- 11 -
5.2 Storage/Staging Areas
A permanent on-base storage area will not be made available for Contractor owned material/equipment.
As required for each TO, the Contractor shall request an area located on or near each construction site to stage materials, store equipment and tools, and maintain miscellaneous items. Storage/staging areas are not guaranteed and are subject to availability. If approved, the Contractor’s storage area shall conform to specification section 01 50 00, Contractor Facilities, and shall be utilized for the purposes of that TO only, or as authorized by the COR.
All equipment, materials, supplies, etc. required to establish and maintain the staging area shall be at the Contractor’s expense. Portable buildings and structures may be used in these staging areas; however, the space shall not be used for occupancy. The assigned area must be fenced in accordance with specification Section 01 50 00.
All Contractor supplied materials and equipment are the sole responsibility of the Contractor.
The Government is not liable for the theft, vandalism, or damage (to include acts of God) of any Contractor supplies, equipment, or property. The Contractor shall take necessary steps to secure their materials and protect all equipment from damage.
6. START-UP PERIOD
The first thirty (30) calendar days following award of the basic contract shall be designated as a start-up period, after which the Contractor shall be prepared to perform activities associated with solicitation/award of a TO (reference section ORDERING PROCEDURES elsewhere in this document).
7. DOCUMENT REQUIREMENTS
All documents shall be submitted in accordance with specification section 01 33 00, Submittal Requirements.
The Contractor shall submit all documents electronically via optical disk, e-mail, or a file transfer service, unless noted otherwise in the TO or as directed by the CO or the COR.
All documents submitted by the Contractor requiring a signature shall be submitted to the CO and the COR with an electronic digital signature. All documents submitted by the Contractor requiring further action and signature by the Government shall be capable of being digitally signed and saved by the Government representative(s) as required.
7.1 DOCUMENT FORMAT
7.1.1 Specifications/Reports/Material Submittals
Specifications, design narratives/analyses, calculations, material submittals, reports/test results, warranty information, and similar documents shall be letter sized (8½" x 11"), submitted in Adobe Acrobat (.pdf) format.
7.1.2 Drawings
All drawings produced by the Contractor shall be created utilizing Computer-Aided Design and Drafting (CADD) software. The drawing files shall be in AutoCAD (.dwg) format and adhere to the drawing standards contained in Tri-Services A/E/C CADD Standard Release 6.0.
Drawing size shall be ANSI D (22" x 34"). Drawing scale shall be at least 1"=30' for civil/site drawings and ⅛"=1' for all other plan drawings; text and other non-scale annotation elements
- 12 -shall be sized to produce clear and legible prints at half-size. Scales and dimensions shall be in U.S. Customary Units.
Drawings submitted by the Contractor shall be .pdf format; in addition, final design drawings and as-builts record drawings shall be submitted in .dwg format.
Reference specification sections 01 33 00, 01 33 16.00 10, and 01 78 00 for additional requirements regarding developing and submitting design, shop, and as-built drawings.
7.2 FILE NAMING CONVENTIONS
All documents submitted by the Contractor shall follow a standardized file naming convention as indicated below. File naming conventions shall be strictly adhered to and may only be modified by the CO and/or the COR. File names shall have no spaces.
The following items in the below naming conventions are defined as followed:
• WWYK###### = Project number as defined by Civil Engineering Example: WWYK201234
• YYYYMMDD = Effective date of document or report
• ZZZ = Contractor’s Company Initials
• 001 = Submittal Number or Serial Report Number
1. Proposals:
WWYK######_Proposal#_ZZZ_Document Description Example: WWYK201234_Proposal1_ACS_Cost Proposal
2. RFIs:
WWYK######_RFI_001
3. Submittals:
WWYK_FORM#_001 (Brief Description of Submittal) Example: WWYK201234_AF3000_004 CeramicTile
4. Daily Reports:
WWYK######_Daily Report_001_YYYYMMDD
5. Progress Reports:
WWYK######_PR_001_YYYYMMDD
6. Other Miscellaneous Documents/Reports:
WWYK######_Form Name, Number, Or Description_YYYYMMDD
8. CORRESPONDENCE
All electronic correspondence related to the awarded contract shall be addressed to the CO, Contract Specialist, Government PM, QACI, the COR, and the respective organizational workflow accounts.
Contact information for the above will be provided at the Post-Award/Pre-Construction meeting for each TO.
All electronic correspondence from the Contractor regarding a specific project shall follow a standardized subject line naming convention. Subject line for all electronic correspondence shall be as follows:
- 13 -
• WWYK###### Project Title: Subject of E-mail
9. COMMUNICATION
The Contractor shall ensure that the Contract Program Manager, QCM, SSHO, Project Superintendents, and any designated alternates can be contacted by telephone at any time the Contractor has active TOs at Tinker AFB.
The Contractor shall ensure the Contract Program Manager can be contacted by telephone or email regarding matters outside of active TOs.
Contractor shall include contact information for all key positions as required in section
ORGANIZATIONAL CHART.
10. ORDERING PROCEDURES
10.1 Fair Opportunity Proposal Request (FOPR)
For each TO awarded under this contract, a FOPR will be issued with required proposal response date; and other documentation as required to communicate the Government's requirements.
Submission of proposals in response to all FOPRs is not required; however, Contractor is required to notify the CO a minimum of two days prior to the required response date if they will not be submitting a proposal.
It shall be the contractor’s responsibility to provide current and accurate contact information for proper receipt of FOPRs.
10.2 Project Documents
For each TO, the Contractor will be furnished with one electronic copy of the contract documents, including a SOW, drawings, specifications (if available), and a submittal register. The Contractor may reproduce the drawings and specifications at the Contractor’s own expense if additional copies are needed. The Contractor shall review the contract documents for discrepancies upon receipt and notify the CO immediately of any/all discrepancies found in the form of a Request for Information (RFI).
10.3 Site Visit
The site visit date will be established by the CO. The Contractor shall attend the site visit and obtain all necessary measurements and information to develop and produce a complete and accurate proposal; subcontractors may attend the site visit at the discretion of the Contractor.
The Contractor shall have one of its company employees present at the site visit to be eligible to submit a proposal. The site visit discussions may include:
• Necessary refinements for Contractor-furnished scope requirements
• Methods and alternatives for accomplishing work
• Access to the facility/project site, work hours, etc.
• User impacts
• Phasing or work sequence
• Security requirements
• Utility outages
• Airfield Waivers, Permits, Excavation
• Temporary protection of Government property
- 14 -
• Debris and trash disposal
• Fire protection and alarm scope
• Noise and dust control
• Environmental Impacts/Asbestos, Lead, PCBs, SWPPP
• Special Requirements specific to project such as applicable codes and regulations
Questions or clarifications concerning information presented during the site visit shall be directed to the Contract Specialist/CO in the form of an RFI. The CO shall determine due dates for contractor submitted RFIs.
Pursuant to the requirements of RFO 52.236-3, Site Investigation and Conditions Affecting the Work.
• Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government.
• Government assumes no responsibility for any understanding reached or representation made by any of its officers or agents before the execution of a TO concerning conditions which can affect the work, unless that understanding or representation is expressly stated in the TO.
Failure of the Contractor to take the actions described and acknowledged in RFO 52.236-3 will not relieve the Contractor from responsibility for properly estimating the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
10.4 Contractor’s Proposal
Contractor's proposal shall be submitted in accordance with the FOPR and the Instructions to Offerors. General expectations for proposal turn around are categorically listed below:
1. Construction w/Limited Design projects:
a. Routine: Proposals shall be submitted within fourteen (14) calendar days after the site visit.
b. Urgent: Proposals shall be submitted within five (5) calendar days after the site visit.
c. Emergency: Proposals shall be submitted within eight (8) hours after the site visit.
2. Design-Build and Construction Only projects:
a. Routine: Proposals shall be submitted within thirty (30) calendar days.
b. Urgent: Proposals shall be submitted within fourteen (14) calendar days.
c. Emergency: Proposals shall be submitted to the CO within two (2) calendar days.
10.5 Task Order Award
Upon award of the TO, the CO will schedule a post-award conference; Contractor shall submit performance bonds and certificates of insurance prior to the post award conference. Reference section MEETINGS/POST-AWARD CONFERENCE for additional information.
- 15 -
11. COMMENCEMENT, PROSECUTION, COMPLETION AND PAYMENT FOR WORK
11.1 Order of Precedence
For each TO issued, in the event of a conflict or inconsistency between any of the provisions of this contract, precedence shall be applied in the following order:
• Any portions of the accepted TO proposal which both conform to and exceed the requirements of the solicitation. The government intends to incorporate the technical proposal as an attachment to the TO.
• The provisions of the FOPR, including:
- The TO Solicitation, Offer and Award
- TO Specifications
- TO Drawings
- TO Statement of Work
- All other provisions of the accepted TO proposal
• MACC Statement of Work for General Construction Services (this document)
• Any Contractor generated design products including, but not limited to, plans, specifications, engineering studies and analyses, shop drawings, and equipment installation drawings.
11.2 Notice to Proceed (NTP)
Upon approval of the Contractor’s performance bonds and insurance, and completion of the post-award conference, the CO will issue the NTP. The period of performance for each TO begins with issuance of the NTP and ends with acceptance/approval of the final progress report.
11.3 Task Order Schedule
In accordance with RFO 52.236-15, Schedules for Construction Contracts, for each awarded TO, the Contractor shall submit a baseline schedule to the COR for approval within ten (10) calendar days after the NTP is issued. An approved schedule will be required prior to commencement of work.
EXCEPTION: for TOs with a performance period less than sixty (60) calendar days, this requirement may be waived by the CO.
11.3.1 Schedule Format
Schedules shall be developed in accordance with specification section 01 32 16.00 20; schedules will be developed utilizing the ‘Network Analysis/Critical Path’ method and presented in the Gantt Chart format.
The schedule shall generally match the schedule submitted with the Contractor's accepted proposal, with the following additional information included:
• TO start (NTP) and end dates
• Additional detail/breakdown of major work elements, as necessary
• Cost Loading data entered for all work items. Cost loading must total to 100 percent of the value of the contract.
Any partial progress payments for materials, as approved by the CO, shall be entered separately on the schedule.
- 16 -
All schedules will reserve, as a minimum, the final 10% of the TO cost for final acceptance. No progress payments will be made against this final 10% of the TO until all closeout items have been submitted, all punch list items have been resolved, and final inspection/acceptance has been completed.
11.3.2 Schedule Updates
Contractor shall keep the schedule current, reflecting actual start and end dates for work elements, activity progress, and plan for completing the remaining work. The Contractor shall submit the updated schedule at monthly intervals, with the first progress report of the month.
Reference specification section 01 32 16.00 20 for additional information.
In addition, the Contractor shall submit updated baseline schedules when directed by the CO.
Examples of when a new baseline schedule may be required include instances where the period of performance has been revised through modification to the awarded TO; or as part of a 'get well plan' for construction that is significantly behind schedule.
Note: Changes to the baseline schedule which extend the completion date of the TO will not be accepted unless specifically requested by the CO or the COR (e.g. to show the effects of a Government delay or a proposed change to the contract by the Government).
Requested changes to the schedule pursuant to RFO 52.249-14, Excusable Delays, must be accompanied by documentation and presented to the CO for consideration.
11.3.3 Coordinating With Government Activities
In developing the schedule, the Contractor shall account for the following Government review times in addition to design/construction activities:
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time (calendar days) Remarks
Baseline Construction Schedule and Schedule of Values/Progress Report 14 days Provide within
10 days of NTP
Design Submittals (each) 14 days
Review conferences and approval of Contractor responses (each) 7 days
SD-01 Preconstruction Submittals (except as noted below) 14 days
Provide all preconstruction submittals per section
SUBMITTALS
Health and Safety Plan 21 days
Internal Combustion Engines Plan 21 days
Entry Access List / Vehicle Entry Access List 14 days
Must be approved prior to obtaining access to controlled/secure areas
Airfield Construction Waiver 60 days Must be provided by 1st business day
- 17 -
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time (calendar days) Remarks of month
Notice of Proposed Construction (FAA Form 7460-1) 60 days
Must be provided by 1st business day of month
Request for Contractor Staging Area 30 days Must be approved prior to mobilization
Storm Water Pollution Prevention Plan (SWPPP) 21 days
Must be approved prior to submitting Tinker Excavation Permit Request
Water System Construction Permits 30 days
Chemical/Hazardous Material Request/Authorization 21 days
Spray Painting Plan 21 days
Abatement Submittals (asbestos, lead based paint) 21 days
Material Submittals
(SD-03, SD-04, SD-07, SD-08)
14 days Provide within 30 days of NTP
Out…