32 01 22.pdf

PDF 17 KB Posted

Attached to
TINKER AFB MAC BOA WWYK190023 Renovate Restrooms B117
Solicitation number
FA813726R0030
Issued by

About this file

This is a technical specification document for bituminous rejuvenation work at Tinker Air Force Base, Oklahoma, dated April 2019. The specification covers the rejuvenation of existing bituminous airfield pavements, roads, streets, parking areas, and other general applications using chemical rejuvenators.

The rejuvenator product must be composed of a petroleum resin-oil base uniformly emulsified with water and must meet specific physical and chemical requirements, including viscosity of 15-40 Saybolt Furol seconds at 77°F, residue content of 0-65 percent minimum, sieve test maximum of 0.10 percent, viscosity at 140°F of 80-500 centistokes, and a flash point minimum of 350°F (Cleveland Open Cup). The mineral aggregate used must meet defined gradation requirements, passing 100 percent through No. 16 sieve, 40-75 percent through No. 30, 4-12 percent through No. 50, and 0-5 percent through No. 100. Government approval of all materials is required prior to use, with submittals including product data, samples, certificates, and manufacturer's instructions. The rejuvenator shall be applied uniformly at a rate of 0.06 gallons per square yard with an allowable variation of plus or minus 20 percent at the temperature recommended by the manufacturer. Surface preparation must remove all loose material, dirt, clay, and other objectionable materials immediately before application. The contractor must provide approved mineral aggregate to blot up any excess rejuvenator material remaining on the treated surface after 24 hours, and if the actual application rate falls more than 20 percent below the approved rate, subsequent applications must be made within 24 hours to ensure adequate penetration.

View the file

Other files

File Type Posted
03 39 00.00 10.pdf PDF
03 62 16.pdf PDF
04 20 00.pdf PDF
05 21 00.pdf PDF
06 20 00.pdf PDF
06 61 16.pdf PDF
07 60 00.pdf PDF
07 61 14.00 20.pdf PDF
07 84 00.pdf PDF
07 92 00.pdf PDF
08 11 16.pdf PDF
08 36 13.pdf PDF
08 71 00.pdf PDF
09 68 00.pdf PDF
10 28 13.pdf PDF
13 48 00.pdf PDF
21 13 17.pdf PDF
22 00 00.pdf PDF
23 00 00.pdf PDF
23 08 00.pdf PDF
23 11 25.pdf PDF
23 35 00.pdf PDF
23 64 26.pdf PDF
23 82 16.00 40.pdf PDF
23 82 43.00 40.pdf PDF
26 56 00.pdf PDF
31 23 06.pdf PDF
32 01 14.pdf PDF
32 13 74.pdf PDF
02 41 00.pdf PDF
06 10 00.pdf PDF
07 12 00.pdf PDF
07 42 13.pdf PDF
07 42 63.pdf PDF
07 53 23.pdf PDF
07 54 19.pdf PDF
07 62 13.pdf PDF
08 41 13.pdf PDF
08 51 13.pdf PDF
08 51 23.pdf PDF
09 51 00.pdf PDF
00 71 00.pdf PDF
01 78 23.pdf PDF
00 72 00.pdf PDF
00 80 00.pdf PDF
Solicitation - FA813726R0030.pdf PDF
Att10_190023_SOW.pdf PDF
EAL List - BLANK to Contractors WWYK190023.xlsx XLSX spreadsheet
Att11_190023_Submittal Register_Final.pdf PDF
Wage Determination.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Section 32 01 22 Page 1

SECTION 32 01 22

BITIMINOUS REJUVENATION

PART 1 GENERAL

1.1 Scope

This specification covers the rejuvenation of existing bituminous airfield pavements, roads, streets, parking areas, and other general applications by the use of a chemical rejuvenator.

1.2 Submittals

Government approval of all materials is required prior to use. The following is to be submitted in accordance with Section 01 33 00;

SUBMITTAL PROCEDURES: SD-03 Product Data SD-04 Samples SD-07 Certificates SD-08 Manufacturer’s Instructions

PART 2 PRODUCTS

2.1 Rejuvenator

The asphalt rejuvenating agent shall be composed of a petroleum resin-oil base uniformly emulsified with water and shall conform to the following physical and chemical requirements:

Property Test Method Requirement

Viscosity, S.F at 77 oF, sec. ASTM D 244 15 - 40

Residue, % 1 ASTM D 244(mod.) 0 – 65 (min)

Sieve Test, % ASTM D 244 (Mod.) 0.10 (max.)

Viscosity @ 140 oF, ASTM D 2170 80 - 500 Centistokes 2

Flash Point, Cleveland Open ASTM D 92 350 (min.)

Cup (COC), oF 3

1 ASTM D 244 Modified Evaporation Test for percent residue is made by heating 50 gm samples to 300 F until foaming ceases; then cool immediately and calculate results.

2 Viscosity on residue obtained from evaporation test.

3 Flash point on residue from evaporation test.

April 2019 Section 32 01 22 Page 2

2.2 Aggregate

Gradation of mineral aggregate shall meet the following requirements:

Sieve Percent by Designation Weight Passing No. 16 100 No. 30 40-75 No. 50 4-12 No. 100 0-5

PART 3 EXECUTION

3.1 Bituminous Storage Tanks

Bituminous Storage Tanks shall be capable of heating the bituminous material under effective and positive control at all times to the required temperature.

3.2 Bituminous Distributor

Bituminous Distributor shall be designed and equipped to spray the bituminous material in a uniform double to triple lap at the temperature recommended by the manufacturer, at variable widths, and at readily determined and controlled rates from 0.04 to 0.2 gallons per square yard, plus or minus 5 percent.

3.3 Brooms and Blowers

Brooms and Blowers shall be of the power type.

3.4 Preparation of Surface

Immediately before applying the rejuvenator, all loose material, dirt, clay, or other objectionable material shall be removed from the surface to be treated.

3.5 Application of Rejuvenator

The rejuvenator shall be uniformly applied over the surface at a rate of 0.06 gallons per square yard, with an allowable variation of plus or minus 20 percent. Materials shall be applied at the temperature recommended by the manufacturer.

3.6 Excess Rejuvenator Material

Approved mineral aggregate shall be provided by the Contractor and shall be spread in sufficient quantity to effectively blot up any excess rejuvenator material remaining on the treated pavement surface after 24 hours.

April 2019 Section 32 01 22 Page 3

3.7 Insufficient Rejuvenator Material

When it is determined by the Contracting Officer that the actual application rate of the rejuvenator is more than 20 percent below the approved application rate, subsequent application(s) shall be made within 24 hours to ensure adequate penetration into the pavement surface.

- End of Section -

Part 1 General
part 2 PRODUCTS
2.1 Rejuvenator
2.2 Aggregate
part 3 EXECUTION
3.1 Bituminous Storage Tanks
3.2 Bituminous Distributor
3.3 Brooms and Blowers
3.4 Preparation of Surface
3.5 Application of Rejuvenator
3.6 Excess Rejuvenator Material
3.7 Insufficient Rejuvenator Material