BUILDING
| PROJECT NUMBER: | XQPZ 10-0105C | REAL PROPERTY | ||||
| PROJECT TITLE: | Cadet Gym Modernization - PH 3 | |||||
| BUILDING NO.: | 2170 | APPROVED: | ||||
| BUILDING NAME: | Cadet Gym | |||||
| DESIGN MANAGER: | Bryan L. Suhler | Real Estate Manager | ||||
| CONSTR. MANAGER: | 10CES/CECR | |||||
| DATE COMPLETED: | (Construction Completion Date) | |||||
| This form should be filled out completely for every contract project including replacement or repair. Both the QUANTITY and TOTAL COST for each line needs be annotated whether it is a Unit of Measure change (TN, SF, EA, etc.) or if no change, insert N/A. This checklist consists of 6 pages. Please do not separate pages or remove from project folder. | ||||||
| GENERAL DATA | ||||||
| ESTIMATED PROJECT COST | $ | N/A | ||||
| ACTUAL CONSTRUCTION COST | $ | N/A | ||||
| TOTAL FLOOR SPACE new building | N/A | SF | ||||
| TOTAL FLOOR SPACE addition | N/A | SF | ||||
| TOTAL FLOOR SPACE rehab existing | N/A | SF | ||||
| NUMBER OF FLOORS | N/A | NO | ||||
| O&M Manuals - Delivered to Maintenance Engineering | N/A | YES or NO | ||||
| Material Types (list predominant type) | ||||||
| foundation | N/A | |||||
| wall | N/A | |||||
| roof | N/A | |||||
| flooring | N/A | |||||
| Utilities Entering Building | SIZE | |||||
| water | N/A | |||||
| sewer | N/A | |||||
| gas | N/A | |||||
| electricity | N/A | |||||
| telephone | N/A | |||||
| fiber | N/A | |||||
| BUILDING SYSTEMS | TOTAL | |||||
| QUAN | UNIT | COST | ||||
| Fire Protection | ||||||
| 880-211 | closed head auto sprinklers | / | SF/HD | N/A | ||
| 880-212 | open head Delug system | / | SF/HD | N/A | ||
| 880-216 | preaction sprinkler system | / | SF/HD | N/A | ||
| 880-217 | aff preaction sprinkler system | / | SF/HD | N/A | ||
| 880-218 | high expansion foam system | EA | N/A | |||
| 880-221 | auto fire detection system | / | SF/EA | N/A | ||
| 880-222 | manual fire alarm system, interior | EA | N/A | |||
| 880-231 | carbon dioxide fire system | EA | N/A | |||
| 880-232 | foam fire systems | EA | N/A | |||
| 880-233 | other fire system | EA | N/A | |||
| 880-234 | halon fire system | EA | N/A | |||
| 880-235 | dry chemical system | EA | N/A | |||
| Security | ||||||
| 872-841 | security alarm system | EA | N/A | |||
| Mechanical/Electrical | ||||||
| 890-126 | a/c units window units | / | SF/TN | N/A | ||
| 890-125 | a/c units <5TN | / | SF/TN | N/A | ||
| 890-121 | a/c unit 5-25TN | TN | N/A | |||
| Air Handling Unit | N/A | |||||
| Evap Cooling | N/A | |||||
| 823-111 | Heat Gas Source | / | SF/MB | N/A | ||
| 821-115 | Heating Plant | MB | N/A | |||
| 821-155 | Steam plant industrial | MB | N/A | |||
| Transformer | KVA | N/A | ||||
| 890-134 | air compressor | HP | N/A | |||
| 890-144 | compressed air dist system | LF | N/A | |||
| 811-147 | emer electric power generator plt | kW | N/A | |||
| emer lighting | EA | N/A | ||||
| Misc | ||||||
| Elevators | EA | N/A | ||||
| Hoist | EA | N/A | ||||
| 890-158 | Loading/Unloading Platform | SF | N/A | |||
| Appliances | EA | N/A | ||||
| Rear Projection Screens | EA | N/A | ||||
| Postal Lock Boxes | EA | N/A | ||||
| Attached Seating | EA | N/A | ||||
| Satellite Antennas | EA | N/A | ||||
| Lockers(permanent) | EA | N/A | ||||
| 890-161 | Misc Support Structure | EA | N/A | |||
| . |
&C&"Times New Roman,Bold"&16REAL PROPERTY 1354 CHECKLIST &"Times New Roman,Regular"&12Section 1 Building &L&"Times New Roman,Regular"&8&F&C&"Times New Roman,Regular"&7PAGE&P&R&"Times New Roman,Regular"&7Current as of Sep 04
EXTERIOR UTILIES
| PROJECT NUMBER: | XQPZ 10-0105C | RP INITAIL | |||
| PROJECT TITLE: | Cadet Gym Modernization - PH 3 | ||||
| This form should be filled out completely for every contract project including replacement or repair. Both the QUANTITY and TOTAL COST for each line needs be annotated whether it is a Unit of Measure change (TN, SF, EA, etc.) or if no change, insert N/A. This checklist consists of 6 pages. Please do not seperate pages or remove from project folder. | |||||
| UTILITIES | TOTAL | ||||
| QUAN | UNIT | COST | |||
| ELECTRIC | |||||
| Electric Distribution System | |||||
| 812-223 | Primary Distro Line Overhead | LF | N/A | ||
| 812-224 | Secondary Distro Line Ovhd | LF | N/A | ||
| 812-225 | Underground Prim Distr Line | LF | N/A | ||
| 812-226 | UG Secondary Prim Dist Line | LF | N/A | ||
| Substations and Switching Stations | |||||
| 813-228 | Elect Switching Station | / | SF/EA | N/A | |
| 813-231 | Elect Substation | kW | N/A | ||
| Elec Use Facilities | |||||
| 812-926 | Exterior Area Lighted | EA | N/A | ||
| 812-928 | Traffic Lights | EA | N/A | ||
| HEAT | |||||
| Heat, Gas - Transmission | |||||
| 821-115 | Heat plant | MB | N/A | ||
| 823-244 | Gas Storage | CF | N/A | ||
| 824-464 | Gas Mains (list sizes) | LF | N/A | ||
| 824-468 | Gas Valve Facility | SF | N/A | ||
| AIR CONDITIONING | |||||
| 826-122 | Air Conditioning 25-100 tons | TN | N/A | ||
| 826-123 | Air Conditioning >100 tons | TN | N/A | ||
| CHILLED WATER (Air Conditioning) EXTERIOR | |||||
| 827-111 | Chilled Water Exterior Distriburtion Lines | LF | N/A | ||
| SEWAGE WASTE, TREATMENT, AND DISPOSAL | |||||
| Wastewater | |||||
| 831-165 | Sewage Treatment & Disposal Sys | KG | N/A | ||
| 831-168 | Waste Treatment Facility Bldg | SF | N/A | ||
| 831-169 | Sewage Septic Tank | KG | N/A | ||
| 832-266 | Sanitary Sewer Main (list sizes) | LF | N/A | ||
| 832-267 | Sanitary Sewage Pump Station | SF | N/A | ||
| WATER | |||||
| Water Supply and Storage | |||||
| 841-161 | Water Supply Main | LF | N/A | ||
| 841-165 | Water Supply Treatment | KG | N/A | ||
| 841-166 | Water Well | KG | N/A | ||
| 841-169 | Water Supply Building | SF | N/A | ||
| 841-425 | Water Storage Reservoir | KG | N/A | ||
| 841-427 | Water Tank Storage | KG | N/A | ||
| Water Distribution System | |||||
| 842-245 | Water Distro Mains (list all sizes) | LF | N/A | ||
| 842-246 | Water Hydrants | EA | N/A | ||
| 842-249 | Water Pumping Stations | SF | N/A | ||
| Fire Protection | |||||
| 843-314 | FP Water Mains | LF | N/A | ||
| 843-315 | Fire Hydrants | EA | N/A | ||
| 843-319 | FP Water Storage | KG | N/A | ||
| Non-Pot Water Storage | |||||
| 844-367 | Non-Pot Water Storage | KG | N/A | ||
| 844-368 | Non-Pot Water Supply System | KG | N/A | ||
| 845-362 | Non-Pot Water Supply Bldg | SF | N/A | ||
| 845-363 | Non-Pot Water Supply Mains | LF | N/A | ||
| PAVEMENTS | |||||
| Roads | |||||
| 851-142 | Roadway Bridges | LF | N/A | ||
| 851-143 | Curb and Gutter | LF | N/A | ||
| 851-145 | Driveways | SY | N/A | ||
| 851-147 | Roads | / | SY/LF | N/A | |
| 852-261 | Vehicle Parking, operations | SY | N/A | ||
| 852-262 | Vehile Parking, non-organization | SY | N/A | ||
| 852-289 | Sidewalk | SY | N/A | ||
| 852-287 | Covered Walkway | SY | N/A | ||
| AIRFIELD | |||||
| 113-321 | Aprons | SY | N/A | ||
| 111-111 | Runway | SY | N/A | ||
| 112-211 | Taxiways | SY | N/A | ||
| DRAINAGE | |||||
| 871-183 | Storm Drainage (list sizes,feature) | LF | N/A | ||
| pipe | N/A | ||||
| channel | N/A | ||||
| catch basin | N/A | ||||
| culvert | N/A | ||||
| manhole | N/A | ||||
| inlet | N/A | ||||
| 871-185 | Storm Drainage Pump Station | SF | N/A | ||
| MISC UTILITIES | |||||
| 871-187 | Retaining Wall | SY/LF | N/A | ||
| 872-245 | Fence, Boundary | LF | N/A | ||
| 872-247 | Fence, Security | LF | N/A | ||
| 872-248 | Fence, Interior | LF | N/A | ||
| 890-181 | Utility Line Conduit/Duct | LF | N/A | ||
| 890-185 | Utility Door | LF | N/A | ||
| 890-187 | Ultility Vault | SF | N/A | ||
| Utility Manhole | LF | N/A | |||
| Comm Manhole | EA | N/A | |||
| 135-583 | Duct Facility | LF | N/A | ||
| 135-586 | Pole Facility (Telephone Poles) | LF | N/A | ||
| 890-171 | Tank, Miscellaneous Storage | BL | N/A | ||
| 890-269 | Cathodic Protection Systems | EA | N/A | ||
| Oil Water Separater | EA | N/A | |||
| HTHW Lines (list sizes) | LF | N/A | |||
| MTHW Lines | LF | N/A | |||
| 841-161 | Water Supply Main | LF | N/A | ||
| EMCS | |||||
| 890-271 | EMCS Central Station | EA | N/A | ||
| 890-272 | EMCS Field Equipment | EA | N/A | ||
| 890-273 | EMCS Data Links | LF | N/A |
&C&"Times New Roman,Bold"&16REAL PROPERTY 1354 CHECKLIST &"Times New Roman,Regular"&12Section 2 Utilities &L&"Times New Roman,Regular"&7&F&R&"Times New Roman,Regular"&7PAGE &P Current as of Sep 04
RPIE
| PROJECT NUMBER: | XQPZ 10-0105C | RP INITAIL | |||
| PROJECT TITLE: | Cadet Gym Modernization - PH 3 | ||||
| This form should be filled out completely for every contract project including replacement or repair. Both the QUANTITY and TOTAL COST for each line needs be annotated whether it is a Unit of Measure change (TN, SF, EA, etc.) or if no change, insert N/A. This checklist consists of 6 pages. Please do not seperate pages or remove from project folder. | |||||
| MISC RPIE | |||||
| RPIE DEFINITION: Those items of government owned or leased accessary equipment apparatus and fixtures that are essential to the function of the real property and are permanently attached to, integral into, or on government-owned or leased property. POC is Ms Karen Leikam building 8120, ex 3-8407. | |||||
| TOTAL | |||||
| DESCRIPTION | QUAN | UNIT | COST | ||
| Appliances (list each MFH Only) | EA | N/A | |||
| Air Dryers/Compressors | EA | N/A | |||
| Auditorium Curtains | EA | N/A | |||
| Central Vac Sys | EA | N/A | |||
| Chalkboards | EA | N/A | |||
| Chapel Equip | |||||
| pews | LF | N/A | |||
| altars | EA | N/A | |||
| pulpits | EA | N/A | |||
| baptistry | EA | N/A | |||
| Chlorinators | EA | N/A | |||
| Dehumidifiers | EA | N/A | |||
| Electronic Air Cleaner | EA | N/A | |||
| Elevators | EA | N/A | |||
| Fire Shutters | EA | N/A | |||
| Room divider curtain | EA | N/A | |||
| Latrine Equipment | |||||
| lavatories | EA | N/A | |||
| commodes | EA | N/A | |||
| urinals | EA | N/A | |||
| Playground Equip (list) | EA | N/A | |||
| Projection screens | EA | N/A | |||
| Saunas | EA | N/A | |||
| Scoreboards | EA | N/A | |||
| Spray Paint Booth | EA | N/A | |||
| Stadium Seats | EA | N/A | |||
| Theater Chairs | EA | N/A | |||
| Wardrobes/Lockers | EA | N/A | |||
| Window A/C unit | EA | N/A | |||
| ADDITIONAL PROJECT INFORMATION |
&C&"Times New Roman,Bold"&16REAL PROPERTY 1354 CHECKLIST &"Times New Roman,Regular"&12Section 3 Misc. RPIE &L&"Times New Roman,Regular"&7&F&R&"Times New Roman,Regular"&7PAGE &P Current as of Sep 04
File details come from the government source that posted it. Updated .