DEPARTMENT OF THE AIR FORCE

10TH MISSION SUPPORT GROUP

USAF ACADEMY, COLORADO

NOTICE: Failure to acknowledge all Amendments may cause rejection of the offer.

1 Amendment 001

AMENDMENT 001

Date of Issue: 12 January 2010

Project Number: XQPZ 10-0105C

SUBJECT: Amendment No. 001 to Drawings and Specifications for Construction of

CADET GYM PHASE 3, XQPZ 10-0105C, USAFA, CO.

TO: Prospective Offerors and Others Concerned –

The Drawings and Specifications for subject project are hereby modified as follows (revise all Drawing indices and lists, Specifications indices, table of contents, sections, and Attachment lists accordingly).

DRAWINGS:

1) Architectural Sheet A604, Room Finish Schedule Added – ATTACHMENT A: Insert new

Sheet A604 after Architectural Sheet A603.

2) Interior Signage Schedule for Door Schedule Added – ATTACHMENT B: Insert new Interior Signage Schedule, Sign Type B, Interior Signage Schedule coordinates with Door Schedule on Architectural Sheet A601.

3) Interior Signage Panel Text Schedule for Directional Signage Added – ATTACHMENT C:

Insert new Interior Signage Schedule, Directional Signage, supplement to Architectural Sheet A201.

4) Interior Signage Revised Graphics Added – ATTACHMENT D: Insert new Interior Signage Revised Graphics, to replace Details 4, 5, 6, and 8, on Architectural Sheet A201.

5) Door Hardware – Lock Functions Added – ATTACHMENT E: Insert new Door Hardware Lock Functions, as an attachment to the Door and Frame Schedule on Architectural Sheet A601.

6) Architectural Sheets A409, A410, and A411, Enlarged Plans-Natatorium – Clarification;

Sheet A409 shows two corners of the pool, both are referenced to Detail 1/A513. Sheet A410 shows the layout for the “AF” logo in the pool floor, and has been included twice in the hard copy drawings. Sheet A411 is a duplicate of Sheet A410, delete Sheet A411 from the hard copy drawings.

7) Architectural Sheets A132, A135, A136, Swim Suit Dryers – At all swim suit dryer locations provide ceramic tile finish at walls behind the dryers, and at floors below the dryers. Provide floor drain below the dryers.

2 Amendment 001

8) Architectural Sheet A201, Detail 9 Typical Accessories Mounting Heights – Delete Items 9 and 10, Toilet Seat Cover Dispensers. Delete Toilet Seat Cover Dispensers from Contract Documents.

9) Architectural Sheet A201, Detail 9 Typical Accessories Mounting Heights – For items 16, 17, 18, 19 Robe Hooks, change mounting height to 5’ – 6” above finish floor.

10) Architectural Sheet A201, Detail 9 Typical Accessories Mounting Heights – For items SH-1 and SH-2, shower heads, change mounting height to 7’ – 8” above finish floor at all Men’s showers, mounting height at all Women’s showers to remain at 6’ – 6” above finish floor as indicated.

11) Architectural Sheets A132, A135, A136, and A201, Detail 10 Typical Shower Partitions – At all Showers for Men and Women, delete all soap dishes, whether wall-mounted or shower post-mounted.

12) Architectural Sheet A202, Detail 6, Dance B213 – Elevation drawing indicates 20 cubbies at 12” x 12”, but not indicates 12 cubbies at 24” x 24”. Change note to provide 20 cubbies at 12” x 12”.

13) Architectural Sheet A120, Cheer Room B212 and Dance Room B213 – Audio visual storage to be located in cabinets at south wall of each room. Reference interior elevations 1 and 6 on Sheet A202. Coordinate with User for final locations of audio visual storage in both rooms. Provide empty conduit for wiring from each audio visual storage location to speakers located in finished ceiling of both rooms.

14) Architectural Sheet A131 Natatorium Floor Plan, and Sheet A410 Enlarged Plan – Also reference Aquatics Sheets AQ4.1 and AQ5.0. For the two deck-mounted AF logos, turn both 180-degrees to orient toward the pool, not the seating area. For the AF logo located in the pool dive well, AF logo to be enlarged to match the size of the existing AF logo (to be demolished). New AF logo to be oriented toward the pool shallow end, not the seating area.

All AF logos to be provided in trademarked block lettering text style used by the Athletic Department. Contractor shall provide AF logo shop drawings for approval prior to start of ceramic tile work.

15) Architectural Sheet A131 Natatorium Floor Plan and Sheet A404 Enlarged Floor Plan – For the whirlpool located adjacent the diving tower, delete the whirlpool ladder. Provide whirlpool bench at fourth side of whirlpool to match bench indicated on the drawings.

16) Architectural Sheet A131 Natatorium Floor Plan, and Aquatics Sheet AQ2.1 Water Polo Pool Plan – Recessed Wall Mounted Backstroke Flag Hooks. Provide all hooks with high tension strength and solid wall anchoring, such that the suspended flag lines are taut with minimum sag during use. Provide pairs of backstroke flag hooks to be located in 6 line locations at the Natatorium Pool, and provide one additional pair of backstroke flag hooks to be located at the Water Polo Pool. At the Natatorium Pool, locate one pair of backstroke hooks at Column Grid Line 15 for Water Polo netting. Coordinate all hook locations with User.

3 Amendment 001

17) Architectural Sheet A132 Partial Plan Level A, and Sheet A601 Door Schedule – Reference Swim Team Room A176, door A176B. In the Door Schedule, change door A176B from “Door Type A” to “Door Type F”, and change material type from “HM” to “HM/GL”.

18) Architectural Sheet A135 Partial Plan Level A – Reference Doors A162C and A202 located along Column Line 7. For both doors and door frames, change door swings, such that they swing into the Locker Rooms, rather than swinging into the Natatorium.

19) Architectural Sheet A135 Partial Plan Level A – Reference Men’s Instructor Locker Room A202. At the southwest corner of this locker room, at the intersection of Column Lines 5 and E, there is a door indicated as a part of this project, but does not have a door number. Add a new door and frame as Door number A202A. Provide door size 3’ – 0” x 7’ – 0” x 1 ¾”, Door Type A, hollow metal, paint finish. Provide door frame Type 1, hollow metal, paint finish. Provide hardware Set 09.

20) Architectural Sheets A144 and A145, and Sheet A601 Door Schedule – Reference Doors 1201F and 1201G that exit from the Boxing Gym into the Center Gym. Provide both locations as alarmed fire exits only, not for regular use. Also reference Specification Section 08 71 00 Door Hardware, hardware Set 02, add alarmed fire exit requirements to door hardware at both locations.

21) Architectural Sheet A401 – At BDU Storage Rooms A174 and A178, add BDU Storage Hooks for a total of 30 hooks at each room. Coordinate final locations and height above finish floor with User.

22) Architectural Sheet A406 Plan Detail 1 – In Women’s Swim Locker Room A179, rotate the AF logo in the carpet flooring 180 degrees.

23) Architectural Sheet A406 Plan Detail 2 – In Men’s Swim Locker Room A171, increase size of AF logo from 2 carpet tiles to 3 carpet tiles.

24) Architectural Sheet A136 Partial Plan Level A – For Directional Sign C1 indicated to be located west of Janitor A161, relocate this sign further north and west, to the east end of the Hallway that overlooks the Climbing Wall. See Attachment for signage text.

25) Architectural Sheet A132 Partial Plan Level A – Add a Directional Sign C1, to be located at the north side of the corridor intersections where Column Lines A and 16 intersect, generally located northeast of the Natatorium. See Attachment for signage text.

26) Architectural Sheet A140 Partial Plan Level 1 – Add a Directional Sign C1, to be located on the wall that straddles Column Line J, and between Column Lines 16 and 17, generally located east of the South-Central Vestibule and west of the ramp. See Attachment for signage text.

27) Architectural Sheet A136 Partial Plan Level A – Reference Storage Room A153, located between Column Lines 1 and 4, and just north of Column Line A. Demolish the temporary wall and door located near the middle of this space. Provide new interior finishes throughout this corridor. Ceiling to be 2’x2’ suspended tegular acoustical grid with 2’x2’ lay-in lighting fixtures at 10-feet on center. Floor to be polished concrete. At walls provide

4 Amendment 001 metal stud furring at 16-inches on center full height, with 5/8-inch gypsum wallboard typical at walls. Provide paint finish at all wall surfaces. Provide rubber wall base at all wall surfaces. Interior finish materials and colors shall match finishes used elsewhere in the project.

28) Architectural Site Plan Sheet AS100, and Electrical Site Power Plan E-100 – Delete Temporary Fabric Structure indicated to be located southwest of the Cadet Gym, and delete all requirements for power and communications utilities to service the temporary structure.

In the Specifications, delete Section 13 31 33 Framed Fabric Structures in its entirety (6 pages). By association, also delete any related items such as site work, demolition, and new work that was to have been a part of the temporary structure.

29) Electrical Drawing Sheets, Steam Rooms and Sauna Rooms – At all Steam Rooms and Sauna Rooms, provide a wall-mounted panic button inside the room, mounted at 30-inches above finish floor, and adjacent the exit door. Also, adjacent each door location on the outside wall of each Steam Room and Sauna Room, provide wall-mounted audible alarm and visual alarm, wired to the panic button each location. Audible and visual alarms to be mounted 7’ – 0” above finish floor.

30) Electrical Sheet E131 Natatorium Floor Plan, and Architectural Sheet A301 Natatorium Building Section – At seating entrance between Column Lines 12 and 13 (north wall), add two camera outlets in the wall, coordinate final locations and height above finish floor with User.

31) Electrical Sheet E131 Natatorium Floor Plan, and Architectural Sheet A301 Natatorium Building Section – At wall north of the pool, between Column Lines 8 and 9, add scoreboard outlet at 18-inches above finish floor. At wall north of the pool, between Column Lines 12 and 13, add scoreboard outlet at 18-inches above finish floor. At wall north of the pool, near Column Line 15, add camera outlet at 18-inches above finish floor. Coordinate final locations and heights above finish floor with User.

32) Electrical Sheet E131 Natatorium Floor Plan, and Architectural Sheet A302 Natatorium Building Section – Shot/game clock outlets indicated between Column Lines 11 and 12 (south wall), delete from this location; relocate shot/game clock outlets to the end of the concrete curb at Column Line 12. Coordinate final locations and height above finish floor with User.

5 Amendment 001

SPECIFICATIONS:

33) Instructions to the Contractor, for Construction – ATTACHMENT F: Insert the Instructions to the Contractor, for Construction, into the Contract Documents as a supplement to the Specifications.

34) Specification Section 01 35 18, Field Testing Requirements for Abatement Work – Construction Contractor shall provide all monitoring and testing as required, delete all references to monitoring and testing by the Government.

35) Specification Section 01 40 00, Quality Control – Paragraph 1.04D Government Responsibilities. All testing and related services and costs will be provided and paid for by the Construction Contractor as a part of the project. Delete all services and costs provided by the Government – the Government does not provide these services or costs. All quality control shall be the responsibility of the Construction Contractor.

36) Specification Section 01 64 06, Schedule of Government Furnished Products – Delete all telephones from schedule that shows telephones as Contractor Installed.

37) Specification Section 01 73 29, Cutting and Patching – Add Paragraph 1.02 E, Provide patching of all holes in structural glazed finish tile (SGFT), and concrete masonry units (CMU) and all disturbed wall finishes within the construction project area. During demolition work, remove all unused electrical conduits and wiring, and unused wall-mounted items.

38) Specification Section 03 30 00, Cast-in-Place Concrete – Construction Contractor shall provide all concrete testing, delete all references to testing by the Government.

39) Specification Section 03 45 00, Plant Precast Architectural Concrete – Construction Contractor shall provide all materials testing; delete all references to testing by the Government. Paragraph 3.05, Add Contractor shall provide concrete sealant at all top and side surfaces of precast concrete.

40) Specification Section 06 40 23, Interior Architectural Woodwork – Paragraph 2.03 Cabinet Hardware and Accessories, Para C Wire Pulls, add words “and maximum depth of 1 ½-inches”.

41) Specification Section 08 71 00, Door Hardware – Paragraph 2.06, Locksets and Latchsets.

All locks are to be 6-pin locks per USAFA Standards.

42) Specification Section 13 11 00, Swimming Pools – Paragraph 1.02 Summary, add Paragraph A.3.c, to read: “Provide swimming pool mechanical piping and equipment to replace the existing filtration system at the Polo Pool with a completely new filtration system, system to be complete and usable, sizes and capacities calculated specifically for the Polo Pool requirements. Filtration System to be Defender system as manufactured by Neptune- Benson, Inc., West Warwick, RI, similar to filtration system for Natatorium Pool. It is the intent to provide a filter system complete with all accessory items supplied and warranted by one manufacturer.”

6 Amendment 001

43) Specification Section 13 11 00, Swimming Pools – Paragraph 1.04 Submittals, add Paragraph A.1.d, to read: “Provide detailed computations and shop drawings for new Filter System at Polo Pool.”

44) Specification Section 21 10 00, Automatic Fire Sprinkler System - Paragraph 2.01B, Contractor shall use steel pipe specified in Paragraph 1 only. Delete all requirements in Paragraphs 2, 3, and 4.

45) Specification Section 23 05 00, Common Work Results for HVAC – Paragraph 1.8 Coordination, Add “Paragraph E, Ceiling Heights. Contractor shall maintain ceiling clearance as high as possible in all spaces in the project. Contractor shall coordinate locations of HVAC ducting and related items to accommodate required ceilings heights.”

MISCELLANEOUS REQUIREMENTS:

46) Double Entry Doors, Northwest Upper Entrance Ramp – Contractor shall repair damaged door and frame. Include all labor, materials, and equipment required for repairs.

47) Double Stainless Steel Doors, East Ramp to the Polo Pool - Two doors 3-feet in 6-feet wide opening, replace doors and vision panels and door frame. Include all labor, materials, and equipment required for replacement.

48) Temporary Electrical Panel TM-1 - Relocate existing electrical panel TM-1 from Room B-212 to the Old Human Performance Lab located one level down. Contractor shall install conduit wire from the electrical closet adjoining Room B-183 to the Old Human Performance Lab.

Provide 36 circuits, one to serve each tread mill, will require 120V duplex outlets wall mounted. Contractor shall provide manpower to relocate approximately 50 pieces of personal fitness machines, including stairmasters, treadmills, and elliptical equipment.

Provide conduit for 5 television outlets, evenly spaced approximately 25-feet apart, coordinate with 10 Communications Squadron as required. Contractor shall size conduit for 36 circuits from electrical closet to the Old Human Performance Lab, approximately 300-feet distance, and will require at least one concrete core 12-inches thick. All circuits shall be 120V.