Attachment 12 Site Visit Q A 12 Feb 2013 The purpose of this attachment is to amend question 2 to state that the video footage could not be uploaded to www.fbo.gov therefore CD are available upon request

View the file

Other files

File Type Posted
Atch_3_Specifications_20130325.pdf PDF
Atch_28 _Drainage_Questions_12_March_2013.pdf PDF
Atch_29_UFC_3-260-01-Tie_Down.pdf PDF
Atch_20 _Drainage_Q A _20130325.pdf PDF
Amendment__5 _FA6703-13-R-0004-0005.pdf PDF
Atch_11 _Proposal_Information_Amend_2.pdf PDF
Amendment__4 _FA6703-13-R-0004-0004.pdf PDF
Atch_25 _Site_Visit_II_Instruction_Amend_1.pdf PDF
atch_27 _SiteVisit _Map_Locations_20130312.pdf PDF
Atch_26 _Site_Visit_II_Roster.pdf PDF
Atch_22 _ASTM_C478_manholes.pdf PDF
Atch_25 _Site_Visit_II.pdf PDF
Atch_23 _ASTM_C924.pdf PDF
Atch_20 _Drainage_Q A.pdf PDF
Atch_21 _ASTM_C443.pdf PDF
Amendment_3 _FA6703-13-R-0004-0003.pdf PDF
Atch_24 _Dobbins_APE.pdf PDF
Amendment__2 _FA6703-13-R-0004-0002.pdf PDF
Atch_14 _Airfield_Drainage_Study_Video_Amend__1.pdf PDF
Atch_10 _Site_Visit_Instruction_Amend_2.pdf PDF
Atch_13 _Archived_Instructions_to_Drainage_Solicitation_2012.pdf PDF
Atch_15 _Airfield_Drainage_Study_Drawings.pdf PDF
Atch_11 _Proposal_Information_Amend__1.pdf PDF
Atch_18 _Site_Visit_Attendee_Listing.pdf PDF
Amendment__1 _FA6703-13-R-0004-0001.pdf PDF
Atch_16 _Site_Visit_Location_Map.pdf PDF
Atch_14 _Airfield_Drainage_Study_Video.pdf PDF
Atch_12 _Site_Visit_Q A _12_Feb_2013.pdf PDF
Atch_17 _Site_10A_Photos.pdf PDF
Atch_19 _ETL_04-4 _Trenchless_Technology.pdf PDF
Atch_10 _Airfield_Site_Visit_Instructions_Amend__1_Q A.pdf PDF
Submittal_Register.pdf PDF
Specifications_20121210.pdf PDF
Solicitation _FA6703-13-R-0004.pdf PDF
Past_and_Present_Performance_Questionnaire.pdf PDF
02935TurfEstablishment.pdf PDF
FGWB_04-0014_Option_Bid_Plan_Setv2.pdf PDF
FGWB_04-0014_Base_Plan_Setv2.pdf PDF
Proposal_Submission_Information.pdf PDF
Drainage_Project_Displaced_Threshold.pdf PDF
WD79.pdf PDF
Site_Visit_Instructions.pdf PDF
Geotechnical_Report.PDF PDF
Draft_TurfEstablishment.pdf PDF
Draft_Submittal_Register.pdf PDF
Draft_FA6703-13-R-0004.pdf PDF
Draft_Drainage_Project_Displaced_Threshold.pdf PDF
Draft_Specifications.pdf PDF
Draft_Past_and_Present_Performance_Questionnaire.pdf PDF
Draft_FGWB_04-0014_Option_Bid_Plan_Set.pdf PDF
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

14 Feb 2013

AIRFIELD STORM DRAINAGE SYSTEM

FA6703-13-R-0004

SITE VISIT 12 FEB 2013

QUESTIONS & ANSWERS, Amendment #1

1. Would previous Questions and answers be uploaded as well from the first solicitation?

No, you may review the Questions & Answers in the archive portion of www.fbo.gov. To locate the previous Questions and Answers, pls see attachment 13, Archived Instructions to Drainage Project 2012

2. Video mentioned during 12 Feb 2013 Site Visit. Can video be obtained & uploaded before Questions are due?

No, due to size limitations attachment 14, Airfield Drainage Study Video, cannot be uploaded on www.fbo.gov. Individuals may request a CD by sending an email to both Patrina Sheffield and Thomas Milloy. Attachment 15, Airfield Drainage Study Drawings, was uploaded and viewable on www.fbo.gov. Additionally, Question submission has been extended to Thursday 21 Feb 2013 NLT 2:00 pm EST.

3. What small Business criteria must be met?

Certified with Small Business Administration (SBA) as Small business and/or any of its socioeconomical criteria (e.g. veteran owned, woman owned, etc.), meet financial & bonding criteria and meet NAICS 237990 “prior” to contract award

4. Please upload a large format scan of the aerial view of the site provided at the pre-bid meeting (the sheet with the bust stops noted in red).

See attachment 16, Site Visit Locations Map (all locations seen on the site visit will be identified by with a number either within the shape or outside.

5. Could we see Site 10A?

Not available at this time. Pls reference attachment 17, Site 10A photos

6. Pls advise of access into this area (Site 10A)?

C-510 shows a construction entrance/exit – the area of disturbance is identified for maintenance and repair

7. Is it true that funding is not available?

Funding is not available at this time and all proposals should be good until 30 Sep 2013

8. Will as-builts, utility locations and etc. be available.

Yes, Reference note 4 on C-003

9. Will this be considered an unforeseen circumstance (differing site condition(s)) then? Additionally, will we be able to come back out to survey? Will this be a change order to deal with unforeseen conditions? We are not aware of what each area is like therefore cannot provide a proper bid for this item.

No, Reference note 4 on C-003

10. Is sod a requirement?

See attachment 5, Turf Establishment

14 Feb 2013

11. Will a list of the attendees be available?

Yes, see attachment 18, Site Visit Attendee List

12. Radio signals to landing?

When working in these areas the KTR will plan ahead to notify contracting of dates so that airfield ops can publish a NOTAM

13. Micro tunneling available for use?

Yes, See attachment 17, ETL 04-4