Attach 5 Schedule of Materials REV.xlsx
XLSX spreadsheet 45 KB Posted
- Solicitation number
- FA557526B0003
About this file
This is a Schedule of Materials attachment for a solicitation to add non-potable water distribution lines to irrigation areas at a military installation in Spain. The document provides a detailed inventory of materials required for the project, organized by category and specification. Materials include various types and sizes of pipes, fittings, valves, pumps, and associated hardware necessary for constructing the water distribution system. Each line item specifies the material type, dimensions, quantity required, and unit of measure to enable contractors to accurately price and procure the necessary components.
The schedule supports the overall project QUUG 19-1000, which carries a contract value between $500,000 and $1,000,000 with a 570-day period of performance. Contractors must be authorized to perform government works in Spain under Spanish law per the Defense and Cooperation Agreement between Spain and the United States. The bid deadline is 0930 hours local time on 13 July 2026, with all bids remaining valid through 31 December 2026. Questions must be submitted by 19 June 2026 at 1200 hours, and a pre-proposal conference and site visit are scheduled for 12 June 2026 at 1300 hours at Moron Air Base.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedul
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | ||
| QUUG 19-1000 | PROJECT TITLE |
ADD NON-POTABLE WATER
DIST LINES TO IRRIGATION AREAS, MULTI SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NUMBER OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |||||||||||
| CERTIFICATE OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | |||||||||||
| APPROVED |
None: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
DISAPPROVED
None: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
SECTION 01 11 01
GENERAL CONDITIONS
| 01 | Warranty letter | 1 | Acceptance+15 |
| 02 | Construction Schedule | 1 | Contract Award+7 |
| 03 | Progress Schedule | 1 | Contract Award+10 |
| 04 | Work Plan | 1 | Contract Award+7 |
| 05 | DD Form 1354 | 1 | Final Inspection-10 |
| 06 | As-Built drawings | 1 | Final Inspection-5 |
| 07 | Mobility Plan | 1 | Contract Award+15 |
| 08 | Project Sign | 1 | Contract Award+15 |
| 09 | Quality Control Plan | 1 | Final Inspection-15 |
| 10 | Waste & construction debris management | 1 | Final Inspection |
| 11 | Key Staff | 1 | Final Inspection-15 |
| 12 | Environmental Protection Plan | 1 | As-Built Drawings+10 |
| 13 | Spatial Data | 1 | Final Inspection-5 |
| 14 | Health and safety Plan | 1 | Contract Award+15 |
| SECTION 01 11 02 |
SPECIAL CONDITIONS
| 15 | GPR report | 1 | CWC + 15 |
| 16 | Existing conditions | 1 | CWC + 16 |
| SECTION 02 41 00 |
DEMOLITION
| 17 | Demolition Plan | 1 | CWC + 15 | |
| 18 | Authorized dump or treatment and recovery plant | 1 | ||
| 19 | Delivery and disposal certificate | 1 | ||
| SECTION 03 30 00 |
CAST IN PLACE CONCRETE
| 20 | Polyethylene sheet catalog data | 1 | |||
| 21 | Precast concrete cabinet | 1 | |||
| 22 | Quality Control Program | 1 | |||
| 23 | Concrete Mix design | 1 | |||
| 24 | Slump Tests | 1 | |||
| 25 | Compressive Strength Tests | 1 | |||
| 26 | Inspection certificate of the concrete batch plant | 1 | |||
| 27 | Reinforcing Bars | 1 | |||
| SECTION 07 92 00 |
JOINT SEALANTS
| 28 | Sealants, Primers and Bond Brakers | 1 |
| SECTION 09 90 00 |
PAINTING AND COATING
| 29 | Coatings | 1 | 1 | 1 |
| 30 | Deliverty Tickets | 1 | ||
| SECTION 31 00 00 |
EARTHWORK
| 31 | Geotechnical investigation report | 1 | |
| 32 | Shoring design report | 1 | |
| 33 | Topographical study of the trenches | 1 | |
| 34 | Utility Crossings Plan and Report | 1 | |
| 35 | Compaction Plan | 1 | |
| 36 | Dewatering Method Statement and Drawings | 1 | |
| 37 | As-built Records of Encountered Utilities | 1 | |
| 38 | Nuclear gauge calibration report | 1 | |
| 39 | Proposed materials test reports for Backfill | 1 | |
| 40 | Proposed materials for reused topsoil and soil | 1 | |
| 41 | Field Density and Moisture | 1 | |
| 42 | Plate Load Test and Footprint | 1 | |
| 43 | Saturation Lines / Isosaturation Curves Laboratory Report | 1 | |
| SECTION 31 05 19 |
GEOTEXTILE
| 44 | Geotextile | 1 |
| SECTION 32 92 19 |
SEEDING
| 45 | Seed | 1 | 1 |
| 46 | Fertilizer | 1 | |
| 47 | Topsoil | 1 | |
| SECTION 33 11 00 |
WATER UTILITY DISTRIBUTION PIPING
| 48 | Pipe, Fittings, Joints, Couplings and electrowelded joining for HDPE | 1 | |||
| 49 | Valves and valve box | 1 | |||
| 50 | Hose bibb and Hose connection vacuum breaker. | 1 | |||
| 51 | Water meter | 1 | |||
| 52 | Irrigation Timer (Programer) | 1 | |||
| 53 | Handhole and covers | 1 | |||
| 54 | Combined Hydrostatic Pressure and Leakage Test | 1 | |||
| 55 | SCADA system | 1 | 1 | ||
| 56 | Stainless steel pipe, fittings, flanges and fabricated assemblies | 1 | |||
| 57 | Welding consumables | 1 | |||
| 58 | Passivation products and procedures | 1 | |||
| 59 | Irrigation Timer (Programmer): Solar Power Supply System (Photovoltaic Panels, MPPT Solar Charge Controller, Battery Storage System, exterior IP66 cabinet) | 1 | 1 | ||
| 60 | Hydrostatic test reports for fabricated stainless steel assemblies | 1 | |||
| 61 | Liquid Penetrant Examination (PT) reports | 1 | |||
| 62 | Fabricated stainless steel assemblies - shop drawings | 1 | |||
| 63 | Welding Procedure Specifications (WPS) | 1 | |||
| 64 | Procedure Qualification Records (PQR) | 1 | |||
| 65 | Welder Qualification Records | 1 |
&8 Schedule of Material Submittals, Feb 05 (SAF/AQCP) Page &P of &N
File details come from the government source that posted it. Updated .