Attach 4 Cost Estimate Blank.xlsx
XLSX spreadsheet 97 KB Posted
- Solicitation number
- FA557526B0003
About this file
This is a blank cost estimate template for a federal construction project at Morón Air Base, Spain. The template is designed for contractors to submit pricing for Project QUUG 19-1000, which involves adding non-potable water distribution lines to irrigation areas at the facility. The cost estimate form accommodates a base bid (CLIN #1) plus six optional line items (CLINs #2-7), allowing contractors to propose costs for different project phases or areas.
The template requires contractors to break down costs across multiple categories including materials, labor (measured in man-hours/man-days with average rates), and other direct costs, with provision for overhead and profit calculations. The work items span several functional areas: modification of non-potable water systems at the potable water treatment facility, installation of programmers in existing sprinkler irrigation systems, and distribution line installation across five designated areas (Areas #1-5) plus obstruction-related work and geophysical survey work. Specific line items include polyethylene pipe (HDPE) in various diameters (DN40-DN200), solenoid valves, water meters, concrete cabinets, gate valves, road crossings, ground penetrating radar surveys, GPS surveys, and site restoration work such as topsoil and seeding. All cost totals on this blank template currently show 0.00, as it is an unfilled template awaiting contractor pricing input. The form includes signature blocks for firm name, preparer title, and preparer identification.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | SUMMARY | |||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| 1 | CLIN #1 BASE BID |
| CLIN #1 BASE BID | |
| 2 | CLIN #2 OPTION #1 |
| CLIN #2 OPCIÓN #1 | |
| 3 | CLIN #3 OPTION #2 |
| CLIN #3 OPCIÓN #2 | |
| 4 | CLIN #4 OPTION #3 |
| CLIN #4 OPCIÓN #3 | |
| 5 | CLIN #5 OPTION #4 |
| CLIN #5 OPCIÓN #4 | |
| 6 | CLIN #6 OPTION #5 |
| CLIN #6 OPCIÓN #5 | |
| 6 | CLIN #7 OPTION #6 |
| CLIN #7 OPCIÓN #6 |
| TOTAL |
| TOTAL |
DATE: FIRM NAME:
TITLE:
These costs and overhead and profit will be applied in any possible future modifications
Page &P
CLIN #1-BASE BID
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #1 BASE BID | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| CLIN #1 BASE BID | ||||||||||
| CLIN #1 BASE BID | ||||||||||
| WORKS RELATED TO MODIFICATION OF NON-POTABLE WATER SYSTEM AT POTABLE WATER TREATMENT FACILITY | ||||||||||
| TRABAJOS RELACIONADOS CON LA MODIFICACIÓN DEL SISTEMA DE AGUA NO POTABLE EN LA INSTALACIÓN DE TRATAMIENTO DE AGUA POTABLE | ||||||||||
| 1 | Polyethylene pipe HDPE PN16 DN200, connection fittings and excavation and filling of trench | |||||||||
| Tubo de polietileno HDPE PN16 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |||||||||
| 2 | Solenoid Valve Ø200mm and accessories | |||||||||
| Válvulas solenoide Ø200mm y accesorios | Ea | |||||||||
| 3 | Solenoid valves and accessories (on the water inlet line for the water treatment plant) | |||||||||
| Válvulas solenoide y accesorios (en la línea de entrada de agua para la planta potabilizadora) | Ea | |||||||||
| 4 | Install water meter BMETERS. WDE-K50 Ø200mm compatible with existing SCADA system | |||||||||
| Instalar contador de agua BMETERS. WDE-K50 Ø200mm compatible con el sistema SCADA existente | Ea | |||||||||
| TOTAL WORKS | ||||||||||
| TOTAL TRABAJO |
| WORKS RELATED TO INSTALLATION OF PROGRAMMERS IN EXISTING SPRINKLER IRRIGATION SYSTEM | ||
| TRABAJOS RELACIONADOS CON INTALACIÓN DE PROGRAMADORES EN SISTEMAS DE RIEGO POR ASPERSIÓN EXISTENTE | ||
| 5 | Cabinet type C2:precast concrete cabinet with reinforce concrete slab(15cm/Ø6mm) including hose bibb, hose connection vacuum breaker 3/4" water meter Ø110mm, pressure gauge solenoid valve Ø110mm, programmer with solar panel and accesories | |
| Armario tipo C2: armario prefabricado de hormigón con losa de hormigón armado (15 cm/Ø6 mm) que incluye grifo para manguera, conexión para manguera, válvula de vacío de 3/4", contador de agua de Ø110 mm, manómetro, válvula solenoide de Ø110 mm, programador con panel solar y accesorios. | Ea | |
| 6 | Cabinet type C3:precast concrete cabinet with reinforce concrete slab(15cm/Ø6mm) including hose bibb, hose connection vacuum breaker 3/4" water meter Ø63mm, pressure gauge solenoid valve Ø63mm, programmer with solar panel and accesories | |
| Armario tipo C3: armario prefabricado de hormigón con losa de hormigón armado (15 cm/Ø6 mm) que incluye grifo para manguera, conexión para manguera, válvula de vacío de 3/4", contador de agua de Ø63 mm, manómetro, válvula solenoide de Ø63 mm, programador con panel solar y accesorios. | Ea | |
| 7 | Cabinet type C4:precast concrete cabinet with reinforce concrete slab(15cm/Ø6mm) including hose bibb, hose connection vacuum breaker 3/4" water meter Ø40mm, pressure gauge solenoid valve Ø40mm, programmer with solar panel and accesories | |
| Armario tipo C4: armario prefabricado de hormigón con losa de hormigón armado (15 cm/Ø6 mm) que incluye grifo para manguera, conexión para manguera, válvula de vacío de 3/4", contador de agua de Ø40 mm, manómetro, válvula solenoide de Ø40 mm, programador con panel solar y accesorios. | Ea |
| TOTAL WORKS |
| TOTAL TRABAJO |
| AREA #1 | ||
| ZONA #1 | ||
| 8 | Ground Penetrating Radar GPR survey | |
| Estudio Geo-Radar (GPR) | m2 | |
| 9 | GPS Survey | |
| Estudio GPS | m2 | |
| 10 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 11 | Polyethylene pipe HDPE PN10 DN160, connection fittings, excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN160, accesorios de conexión, excavación y relleno de zanja | Lm | |
| 12 | Polyethylene pipe HDPE PN10 DN110, connection fittings, excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión, excavación y relleno de zanja | Lm | |
| 13 | Polyethylene pipe HDPE PN10 DN63, connection fittings, excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN63, accesorios de conexión, excavación y relleno de zanja | Lm | |
| 14 | Cabinet type C1:Precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4" water meter Ø63mm, pressure gauge and accesories | |
| Armario tipo C1:Armario prefabricado de hormigón con grifo de manguera, conexión de manguera, disyuntor de vacío de 3/4", contador de agua Ø63mm , manómetro y accesorios | Ea | |
| 15 | Gate Valve Ø160mm and accessories (valve box) | |
| Válvulas de compuerta Ø160mm y accesorios (caja de válvulas) | Ea | |
| 16 | Gate Valve Ø110mm and accessories (valve box) | |
| Válvulas de compuerta Ø110mm y accesorios (caja de válvulas) | Ea | |
| 17 | Road crossing (drilled) RC-01 for pipe Ø160mm | |
| Cruce carretera (con topo) RC-01 para tubería Ø160mm | Lm | |
| 18 | Road crossing (drilled) RC-02 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-02 para tubería Ø110mm | Lm | |
| 19 | Road crossing (drilled) RC-03 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-03 para tubería Ø110mm | Lm | |
| 20 | Road crossing (drilled) RC-04 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-04 para tubería Ø110mm | Lm | |
| 21 | Road crossing (drilled) RC-05 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-05 para tubería Ø110mm | Lm | |
| 22 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 23 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #1 | ||
| Total Zona #1 |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
SUBTOTAL 0.00
PROFIT % 0.00
TOTAL PROJECT EUROS 0.00
DATE: FIRM NAME:
TITLE: PREPARED BY:
These costs and overhead and profit will be applied in any possible future modifications
CLIN #2-OPTION 1
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #2-OPTION 1 | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| CLIN #2 OPTION #1 |
| CLIN #2 OPCIÓN #1 |
| AREA #2 | ||
| ZONA #2 | ||
| 1 | Ground Penetrating Radar GPR survey | |
| Estudio Geo-Radar (GPR) | m2 | |
| 2 | GPS Survey | |
| Estudio GPS | m2 | |
| 3 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN6200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 4 | Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 5 | Polyethylene pipe HDPE PN10 DN63, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN63, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 6 | Cabinet type C5:precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4" water meter Ø63mm and pressure gauge. | |
| Armario tipo C5: armario prefabricado de hormigón que incluye grifo para manguera, conexión para manguera, válvula de vacío de 3/4" ,contador de agua de Ø63 mm y manómetro | Ea | |
| 7 | Cabinet type C1: Precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4" water meter Ø63mm , pressure gauge and accesories | |
| Armario tipo C1:Armario prefabricado de hormigón con grifo de manguera, conexión de manguera, disyuntor de vacío de 3/4", contador de agua Ø63mm , manómetro y accesorios | Ea | |
| 8 | Handhole with blind flange | |
| Arqueta con brida ciega | Ea | |
| 9 | Gate Valve Ø110mm" and accessories (valve box) | |
| Válvulas de compuerta Ø110mm y accesorios (caja de válvula) | Ea | |
| 10 | Gate Valve Ø63mm and accessories | |
| Válvulas de compuerta Ø63mm y accesorios | Ea | |
| 11 | Road crossing (drilled) RC-06 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-06 para tubería Ø63mm | Lm | |
| 12 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 13 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #2 | ||
| Total Zona #2 |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
| SUBTOTAL | 0.00 | |||
| DATE: | FIRM NAME: | |||
| PROFIT | % | 0.00 |
TITLE: PREPARED BY: TOTAL PROJECT EUROS 0.00
These costs and overhead and profit will be applied in any possible future modifications
CLIN #3-OPTION 2
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #3-OPTION 2 | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| CLIN #3 OPTION #2 |
| CLIN #3 OPCIÓN #2 |
| AREA #3 | ||
| ZONA #3 | ||
| 1 | Ground Penetrating Radar GPR survey | |
| Estudio Geo-Radar (GPR) | m2 | |
| 2 | GPS Survey | |
| Estudio GPS | m2 | |
| 3 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 4 | Polyethylene pipe HDPE PN10 DN63, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN63, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 5 | Cabinet tipe C1: Precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4" water meter Ø63mm , pressure gauge and accesories | |
| Armario tipo C1: Armario prefabricado de hormigón (tipo 1) con grifo de manguera, conexión de manguera Ø63mm , disyuntor de vacío de 3/4", contador de agua, manómetro y accesorios | Ea | |
| 6 | Gate Valve Ø63mm and accessories | |
| Válvulas de compuerta Ø63mm y accesorios | Ea | |
| 7 | Road crossing (drilled) RC-07 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-07 para tubería Ø63mm | Ea | |
| 8 | Road crossing (drilled) RC-08 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-08 para tubería Ø63mm | Ea | |
| 9 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 10 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #3 | ||
| Total Zona #3 |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
SUBTOTAL 0.00
PROFIT % 0.00
TOTAL PROJECT EUROS 0.00
DATE: FIRM NAME:
TITLE: PREPARED BY:
These costs and overhead and profit will be applied in any possible future modifications
CLIN #4-OPTION 3
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #4-OPTION 3 | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| CLIN #4 OPTION #3 |
| CLIN #4 OPCIÓN #3 |
| AREA #4 | ||
| ZONA #4 | ||
| 1 | Ground Penetrating Radar GPR survey | |
| Estudio Geo-Radar (GPR) | m2 | |
| 2 | GPS Survey | |
| Estudio GPS | m2 | |
| 3 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 4 | Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 5 | Polyethylene pipe HDPE PN10 DN63, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN63, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 6 | Cabinet typo C1: Precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4", water meter Ø63mm ,pressure gauge and accesories | |
| Armario tipo C1: Armario prefabricado de hormigón (tipo 1) con grifo de manguera, conexión de manguera, disyuntor de vacío de 3/4", contador de agua Ø63mm, manómetro y accesorios | Ea | |
| 7 | Handhole with blind flange | |
| Arqueta con brida ciega | Ea | |
| 8 | Gate Valve Ø110mm and accessories (valve box) | |
| Válvulas de compuerta Ø110mm y accesorios (caja de válvulas) | Ea | |
| 9 | Road crossing (drilled) RC-19 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-19 para tubería Ø110mm | Ea | |
| 10 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 11 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #4 | ||
| Total Zona #4 |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
| SUBTOTAL | 0.00 | |||
| DATE: | FIRM NAME: | |||
| PROFIT | % | 0.00 |
TITLE: PREPARED BY: TOTAL PROJECT EUROS 0.00
These costs and overhead and profit will be applied in any possible future modifications
CLIN #5-OPTION 4
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #5-OPTION 4 | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| CLIN #5 OPTION #4 |
| CLIN #5 OPCIÓN #4 |
| AREA #5 | ||
| ZONA #5 | ||
| 1 | Ground Penetrating Radar GPR survey | |
| Estudio Geo-Radar (GPR) | m2 | |
| 2 | GPS Survey | |
| Estudio GPS | m2 | |
| 3 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 4 | Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 5 | Polyethylene pipe HDPE PN10 DN63, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN63, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 6 | Cabinet type C1: Precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4",water meter Ø63mm and accesories | |
| Armario tipo C1: Armario prefabricado de hormigón con grifo de manguera, conexión de manguera, disyuntor de vacío de 3/4", contador de agua Ø63mm y accesorios | Ea | |
| 7 | Gate Valve Ø110mm and accessories | |
| Válvulas de compuerta Ø110mm y accesorios | Ea | |
| 8 | Gate Valve Ø63mm and accessories | |
| Válvulas de compuerta Ø63mm y accesorios | Ea | |
| 7 | Road crossing (drilled) RC-09 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-09 para tubería Ø63mm | Ea | |
| 8 | Road crossing (drilled) RC-10 pipe Ø63mm | |
| Cruce carretera (con topo) RC-10 para tubería Ø63mm | Ea | |
| 9 | Road crossing (drilled) RC-11for pipe Ø110mm | |
| Cruce carretera (con topo) RC-11para tubería Ø110mm | Ea | |
| 10 | Road crossing (drilled) RC-12 pipe Ø110mm | |
| Cruce carretera (con topo) RC-12 para tubería Ø110mm | Ea | |
| 11 | Road crossing (drilled) RC-13 para tubería Ø63mm | |
| Cruce carretera (con topo) RC-13 para tubería Ø63mm | Ea | |
| 12 | Road crossing (drilled) RC-14 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-14 para tubería Ø63mm | Ea | |
| 13 | Road crossing (drilled) RC-15 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-15 para tubería Ø63mm | Ea | |
| 14 | Road crossing (drilled) RC-16 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-16 para tubería Ø63mm | Ea | |
| 15 | Road crossing (drilled) RC-17 for pipe Ø63mm | |
| Cruce carretera (con topo) RC-17 para tubería Ø63mm | Ea | |
| 16 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 17 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #5 | ||
| Total Zona #5 |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
SUBTOTAL 0.00
PROFIT % 0.00
TOTAL PROJECT EUROS 0.00
DATE: FIRM NAME:
TITLE: PREPARED BY:
These costs and overhead and profit will be applied in any possible future modifications
CLIN#6-OPTION 5
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #6-OPTION 5 | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| CLIN #6 OPTION #5 | ||
| CLIN #6 OPCIÓN #5 | ||
| WORKS RELATED TO OBSTRUCTIONS | ||
| TRABAJOS RELACIONADOS CON OBSTRUCCIONES | ||
| 1 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 2 | Polyethylene pipe HDPE PN10 DN160, connection fittings, excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN160, accesorios de conexión, excavación y relleno de zanja | Lm | |
| 3 | Polyethylene pipe HDPE PN10 DN63, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN63, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 4 | Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 3 | Gate Valve Ø160mm and accessories (valve box) | |
| Válvulas de compuerta Ø160mm y accesorios (caja de válvulas) | Ea | |
| 4 | Gate Valve Ø110mm and accessories (valve box) | |
| Válvulas de compuerta Ø110mm y accesorios (caja de válvulas) | Ea | |
| 5 | Road crossing (drilled) RC-01 for pipe Ø160mm | |
| Cruce carretera (con topo) RC-01 para tubería Ø160mm | Lm | |
| 6 | Road crossing (drilled) RC-02 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-02 para tubería Ø110mm | Lm | |
| 7 | Cabinet type 1: Precast concrete cabinet including hose bibb, hose connection vacuum breaker 3/4",water meter Ø63mm and accesories | |
| Armario tipo 1:Armario prefabricado de hormigón con grifo de manguera, conexión de manguera, disyuntor de vacío de 3/4", contador de agua Ø63mm y accesorios | Ea |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
SUBTOTAL 0.00
PROFIT % 0.00
TOTAL PROJECT EUROS 0.00
DATE: FIRM NAME:
TITLE: PREPARED BY:
These costs and overhead and profit will be applied in any possible future modifications
CLIN#7-OPTION 6
| COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| MORÓN AIR BASE, SPAIN | ||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| ADD NON-POTABLE WATER DIST LINES TO IRRIGATION AREAS, MULTI | CLIN #7-OPTION 6 | 0.00 | ||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 19-1000 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| CLIN #7 OPTION #6 | ||
| CLIN #7 OPCIÓN #6 | ||
| GROUND PENETRATING RADAR (GPR) Y GPS | ||
| GEO-RADAR Y GPS | ||
| 1 | Ground Penetrating Radar GPR survey | |
| Estudio Geo-Radar (GPR) | Lm | |
| 2 | GPS Survey | |
| Estudio GPS | Lm | |
| TOTAL GPR AND GPS WORKS | ||
| TOTAL TRABAJO DE GPR Y GPS |
| AREA #3 (Blg. #106, #110, #119) | ||
| ZONA #3 (Blg. #106, #110, #119) | ||
| 3 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 4 | Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 5 | Handhole with blind flange | |
| Arqueta con brida ciega | Ea | |
| 6 | Gate Valve Ø110mm and accessories (valve box) | |
| Válvulas de compuerta Ø110mm y accesorios (caja de válvulas) | Ea | |
| 7 | Road crossing (drilled) RC-20 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-20 para tubería Ø110mm | Ea | |
| 8 | Road crossing (drilled) RC-18 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-18 para tubería Ø110mm | Ea | |
| 9 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 10 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #3 | ||
| Total Zona #3 | ||
| AREA #4 (Blg #192, #203) | ||
| ZONA #4 (Edif. #192, #203) | ||
| 11 | Polyethylene pipe HDPE PN10 DN200, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN200, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 12 | Polyethylene pipe HDPE PN10 DN110, connection fittings and excavation and filling of trench | |
| Tubo de polietileno HDPE PN10 DN110, accesorios de conexión y excavación y relleno de zanja | Lm | |
| 13 | Handhole with blind flange | |
| Arqueta con brida ciega | Ea | |
| 14 | Gate Valve Ø200mm and accessories (valve box) | |
| Válvulas de compuerta Ø200mm y accesorios (caja de válvulas) | Ea | |
| 15 | Gate Valve Ø110mm and accessories (valve box) | |
| Válvulas de compuerta Ø110mm y accesorios (caja de válvulas) | Ea | |
| 16 | Road crossing (drilled) RC-20 for pipe Ø110mm | |
| Cruce carretera (con topo) RC-20 para tubería Ø110mm | Ea | |
| 17 | Top soil and seeding | |
| Tierra vegetal y sembrado | m2 | |
| 18 | Repair elements affected by the execution of the project | |
| Reparar elementos afectados por la ejecución del proyecto | Job | |
| Total, Area #4 | ||
| Total Zona #4 | ||
| TOTAL WORKS | ||
| TOTAL TRABAJO CONSTRUCCIÓN |
| TOTAL |
| TOTAL |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD % 0.00
SUBTOTAL 0.00
PROFIT % 0.00
TOTAL PROJECT EUROS 0.00
DATE: FIRM NAME:
TITLE: PREPARED BY:
These costs and overhead and profit will be applied in any possible future modifications image1.png
File details come from the government source that posted it. Updated .