About this file

Offeror's questions and the Government responses dated 18 Jul 11

View the file

Other files

Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5209-11-R-0004 Amendment 0005 Attachment 1

18 Jul 11 Question

No.

Reference

(Sect/Para/Page)

QUESTION GOVERNMENT RESPONSE

Section J, Attachment 5

Permitted duration for outage (2 days for the 1st floor, 1 day for the 3rd floor) does not secure enough leadtime for the Contractor to remove necessary items and to install temporary ducts.

Replacing AHU units requires at least 3 days of outage for both floors regardless of the option chosen by the government. Is it possible to extend the duration for outage?

No.

Section J, Attachment 5

Replacing AHU unit takes a hole for temporary ducts; in other words, small part of exterior wall need to be removed (current opening for ducts cannot be used since the opening is intended for the new AHU unit).

Kindly specify the permissible largest size of the opening for the temporary duct (please note that size of the wall to be removed has yet to be determined).

Not permitted to make new opening for exterior wall.

Existing louver may be used for temporary system. However, the louver has security bar, and shall not be removed. Existing system is not connected to the louver. (1st floor and 3rd floor)

Section L, YCL004, Para. I.1

(v) Phasing schedule execution plan;

The limit of 50 pages for technical proposal applies to the execution plan?

Yes. The page limit applies to the plan since it is one of the sabfactors of Technical Proposal.

Question Sheet

File details come from the government source that posted it. Updated .