Industry Feedback QA AMEND 4.docx
DOCX document 37 KB Posted
- Attached to
- Global Prepositioned Materiel Services (GPMS) Federal contract opportunity
- Solicitation number
- FA4890-19-R-A004
About this file
This document contains industry questions and responses regarding Solicitation Number FA4890-19-R-A004 for the Global Prepositioned Materiel Services requirement. The solicitation requests proposals for providing Global Prepositioned Materiel Services for the United States Air Force Air Combat Command. Key details include a pre-proposal conference tentatively scheduled for 3 November 2020, questions regarding the formal solicitation to be submitted by an unspecified deadline, and proposals due by 3 December 2020 at 1400 Eastern Standard Time. The questions and responses clarify that the base year period of performance is nine months, from 1 February 2022 to 31 October 2022, rather than the twelve months indicated in the pricing templates, and contractors may make corrections to the templates.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GPMS RFP Industry Questions / Comments
| RFP Reference |
| Industry Questions/Comment |
| Government Response |
| 1 |
| Section L - Attachment 3 - GPMS USAFE Pricing Template FINAL (Section B) AMD 2 and Section L - Attachment 3 - GPMS PACAF Pricing Template FINAL (Section B) AMD 2 |
| On the referenced Attachment 3s in the Base Year Units and Units of issue for the operational CLINs (other than Transition) it states 12 months, however in the Base PoP column indicates 1 Feb 2022 – 31 Oct 2022, which is 9 months which coincides with the section L instructions. |
Question 1: Could the government please confirm that the Base Year Units should be 9?
Question 2: If yes, should the contractor make the correction to the referenced Attachment 3s or will the Government provide corrected ones?
Yes, the base year units should be 9.
Yes, the contractor may make the correction to the referenced attachments.