CAF_ADAIR_Risk_Assessment_17_May_17.pdf

PDF 231 KB Posted

Attached to
CAF Contracted Air Support (CAS) Federal contract opportunity
Solicitation number
FA4890-17-R-0007
Issued by
Department of the Air Force Air Combat Command

About this file

CAF ADAIR Risk Assessment

View the file

Other files for this federal contract opportunity

Other files attached to CAF Contracted Air Support (CAS), newest first.
File Type Posted
WD2015-5253_Rev_6.pdf PDF
FA4890-17-R-0007-0001_Amendment.pdf PDF
CDRL_1_-_Organizational_Structure_and_Personnel_Listing.pdf PDF
Section_B,_Attachment_1_-_IDIQ_Pricing_Worksheet.xlsx XLSX spreadsheet
Appendix_N_-_CAF_CAS_Blue_1_and_Mission_Lead_Evaluation.pdf PDF
Appendix_M_-_Definitions,_Abbreviations,_and_Acronyms.pdf PDF
Appendix_D_-_Government_Furnished_Equipment.pdf PDF
Appendix_G_-_Quality_Management_System.pdf PDF
Appendix_C_-_Publications_and_Forms.pdf PDF
FA4890-17-R-0007_SF33.pdf PDF
Pre-RFP_Conference_Attendees_(7_June_2018).pdf PDF
Pre-RFP_Conference_-_CAF_CAS__slides.pdf PDF
Pre-RFP_Conference__Agenda_-_5_Jun_18.pdf PDF
DRAFT_CAF_CAS_Appendix_I_-_Aircraft_Attributes_4_Jun_2018.pdf PDF
DRAFT_CAF_CAS_Sections_L_M_5_Jun_2018.pdf PDF
Consolidated_Q&As_CAF_Contracted_Air_Support_11_May_2018.pdf PDF
CAF_CAS_Proposal_Writing_Conf_-_24_May_18.pdf PDF
Attachment_X_CAF_CAS_Engineering_Feasibility_Assessment.docx DOCX document
DRAFT_CAF_CAS_Appendix_C_-_Publications_and_Forms_2_Apr_2018.pdf PDF
DRAFT_CAF_CAS_Appendix_G_-_Quality_Management_System_-_2_Apr_2018.pdf PDF
DRAFT_FA4890-17-R-0007_2_Apr_2018.pdf PDF
DRAFT_CAF_CAS_Appendix_I_-_Aircraft_Attributes_2_Apr_2018.pdf PDF
DRAFT_IDIQ_Pricing_Table_Section_J_Attachment_2_-2_Apr_18_-_Protected.xlsx XLSX spreadsheet
Q&A_Format.docx DOCX document
DRAFT_CAF_CAS_Appendix_M_-_Definitions,_Abbreviations,_and_Acronyms.pdf PDF
DRAFT_CAF_CAS_Appendix_N_-_CAF_ADAIR_Blue_1_Evaluation_2_Apr_2018.pdf PDF
DRAFT_TO_Ordering_Guide_2_Apr_2018.pdf PDF
Attachment_2-AFSOC_CCAS_PWS_(similar_past_effort).PDF PDF
CCAS_Notice_to_Industry_2_Feb_2018.pdf PDF
Attachment_1-Market_Research_Questionnaire.pdf PDF
Notice_to_Industry_17_Jan_18.pdf PDF
CAF_ADAIR_Sections_L&M_17_Jan_18.pdf PDF
DRAFT_CAF_ADAIR_Appendix_I_-_Aircraft_Attributes_17_Jan_18_-_Abbreviated.pdf PDF
Airworthiness_Assessment_Technical_Evaluation_Training.pdf PDF
Notice_to_Industry_19Oct17.pdf PDF
DRAFT_CAF_ADAIR_Appendix_I_-_Aircraft_Attributes_19Oct17.pdf PDF
Follow-up_Questions_for_Industry_19_Sep17.pdf PDF
Additional_Questions_for_Industry.pdf PDF
JBLE_Base_Map_with_71_FTS.pdf PDF
CAF_ADAIR_Memo_-_Industry_Site_Visit_and_One-on-One_Meetings.pdf PDF
DRAFT_CAF_ADAIR_Kingsley_PWS_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Hickam_PWS_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Kelly_PWS_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Appendix_G_-_Quality_Management_System_25_Jul_17.pdf PDF
CAF_ADAIR_Questions_for_Industry_-_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Tyndall_PWS_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Master_PWS_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Langley_PWS_25_Jul_17.pdf PDF
DRAFT_CAF_ADAIR_Eglin_PWS_25_Jul_17.pdf PDF
DRAFT_Pricing_Table_Section_J_Attachment_2_-_25_Jul_17.xlsx XLSX spreadsheet
Show all 50

CAF Contracted Air Support (CAS) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Risk

Ranking

POC

RISK

TYPE

RISK DESCRIPTION RISK FACTOR

PROBABILITY

(LIKELIHOOD)

IMPACT

(CONSEQUENCE)

RISK

FACTOR

RATING

OVERALL

RISK RATING

RISK

MITIGATION

STRATEGY

MANAGEMENT ACTIONS /

RESPONSE CONTROL

SERVICE

SUMMARY

ITEM NO.

INDIVIDUAL

RISK

FACTOR

SCORE

OVERALL

RISK SCORE

Performance 4 H 3.00

Cost 4 H 3.00

Schedule 4 H 3.00

Performance 4 H 3.00

Cost 5 H 3.00

Schedule 5 H 3.00

Performance 4 H 3.00

Cost 4 H 3.00

Schedule 4 H 3.00

Performance 4 H 3.00

Cost 3 M 2.00

Schedule 4 H 3.00

Performance 4 H 3.00

Cost 4 H 3.00

Schedule 3 M 2.00

5 PM/CO Business

If the Government fails to properly coordinate and execute the required National Environmental Protection Act (NEPA) actions, then the contract award and performance could be significantly delayed or halted.

4 H Control

Transfer

The Government will develop and utilize source selection criteria to evaluate offeror's Logistics Sustainment Plan. This plan should clearly outline the offeror's source of supply, the vendor's availability of parts and supplies and the supply-transportation methodology to ensure adequate logistics support.

AMIC has formed an EIAP team consisting of representatives from ACC

A3T (the requirement owner), ACC A8BA (Basing) AFIMSC Det 8 and the

AFMC NEPA Division (AFCEC/CZN). This team conducts weekly planning meetings and conducted a NEPA Scoping meeting 9-11 May 17. This team will continue to meet weekly throughout the EAIP planning and execution process. AMIC CO/PM will ensure the contract task orders are not awarded until the EA/EIS actions are complete.

2.67

4 H

AMIC

PM/CO/DRQA

Programmatic &

Technical

If the contractor's aircraft modification execution doesn't meet the PWS desired timelines, or fails, ADAIR support will be deficient, and vital pilot training opportunities delayed or missed.

4 H

Transfer and

Control

The Government will identify the threshold and objective aircraft attribute requirements across the enterprise and specify required capabilities by option years. Source selection criteria will evaluate an offeror's aircraft attribute modernization plan. This plan should clearly outline the offeror's capability to acquire suitable aircraft, in sufficient quantities, modify as required with respect to required threshold/objective aircraft performance attributes. AMIC has identified the State Department/ATF and USAF Airworthiness office as advisors to assist in evaluating the contractors mobilization plan. At a minimum offerors must have an interim Third Party Transfer and a purchase approval letter, indicating a valid aircraft purchase. Post-award the government will closely monitor the contractors execution of their mobilization and modification plan.

3.00

3.00

2.67

1 PM/CO Programmatic

If the contractor fails to execute an effective mobilization plan

(provide/modify aircraft) to meet Government requirements, then ADAIR support will be deficient and scheduled training will not occur.

4 H

Transfer and

Control

AMIC PM and CO must engage closely with the USAF Airworthiness

Technical Airworthiness Authority to ensure airworthiness criteria is clearly outlined and communicated to prospective offerors. The CO must compile an Aircraft Airworthiness Data Package (AADP) with each contractor to present to the TAA for approval. Any aircraft later requiring modification must also process through the AW TAA for approval. This effort must be accomplished efficiently, or delays to mission execution, or insufficient aircraft will negatively impact the

ADAIR mission. The AW office will provide training to the CO, PM, and

DRQ to ensure the key government personnel fully understand the AW process. Additionally, the USAF AW Office offers AW training to interested Contractors to enhance their understanding of the AW process.

Transfer and

Control

The Government will clearly identify required aircraft systems performance attributes within the PWS and communicate these to

Industry throughout the acquisition process. The threshold and objective aircraft attribute requirements will be specified by option years. Source selection criteria will evaluate an offeror's Aircraft

Modification Plans. AMIC will utilize a variety of SME sources (OEM, ALC

SPOs, MAJCOM staff and USAF AW office) to evaluate the feasibility of modification plans.

AMIC

PM/CO/DRQA

Programmatic &

Technical

If the contractor's logistics sustainment plan isn't robust with credible vendors and an effective supply-transportation chain, then aircraft availability will be degraded with significant impact to the ADAIR support mission.

3.00CO/PM/AW Office Programmatic &

Technical

If the contractor’s aircraft cannot meet USAF Airworthiness requirements, then sufficient aircraft with desired capabilities will not be available as needed at the earliest projected date to support ADAIR requirements. If this occurs, ADAIR support will be deficient, and vital pilot training opportunities delayed or missed.

4 H

Performance 4 H 3.00

Cost 5 H 3.00

Schedule 3 M 2.00

Performance 4 H 3.00

Cost 5 H 3.00

Schedule 3 M 2.00

7 ACC A3TO/GFRs Technical

If the contractor fails to follow safe ground operating procedures, then there is increased and significant risk to aircraft, equipment, facility, personnel or the local civilian community.

4 H Control

Control

The contractor will be required to provide flight operating procedures for each operating location IAW with AFI 10-220; these procedures will be reviewed and approved by the Government during contract transition. The Government also must ensure the contractor's receive local area orientations, are aware of airfield cpability risks and adhere to the local Flight Crew Information Files (FCIF) and in-flight guides. The

GFR has the responsibility to surveil contractor flight operations and have focused attention on contractor performance to ensure safe operations. Operating location active duty flight leaders must augment the GFRs efforts and be "eyes and ears" of the GFR to solidify the surveillance of flight operations. The Government should include the

Contractor’s Aviation Safety team within the established Wing/Group

Flying Safety process. If the contractor does not follow the Government approved Flight Operations Plan the CO can/will direct the contractor to cease operations.

2.67

The contractor will be required to provide ground operating procedures for each operating location IAW with AFI 10-220; these procedures will be reviewed and approved by the Government during contract transition. The GFR/GGR have the responsibility to surveil contractor ground operations and have focused attention on contractor performance to ensure safe operations. Operating location SMEs must augment the GFR/GGRs efforts and be "eyes and ears" of the GFR/GGR to solidify the surveillance of ground operations. The Government should include the Contractor’s Aviation Safety team within the established Wing/Group Safety program. If the contractor does not follow the Government approved Ground Operations Plan the CO can/will direct the contractor to cease operations.

6 ACC A3TO/GFRs Technical

If the contractor fails to follow safe flight operating procedures, then there is increased and significant risk to aircraft, equipment, facility, personnel or the local civilian community.

4 H 2.67

Performance 4 M 2.00

Cost 5 H 3.00

Schedule 3 M 2.00

Performance 4 H 3.00

Cost 3 M 2.00

Schedule 3 M 2.00

Performance 3 M 2.00

Cost 5 H 3.00

Schedule 3 M 2.00

Performance 4 M 2.00

Cost 4 M 2.00

Schedule 3 M 2.00

Performance 4 M 2.00

Cost 4 M 2.00

Schedule 4 M 2.00

Performance 4 M 2.00

Cost 4 M 2.00

Schedule 4 M 2.00

Performance 5 M 2.00

Cost 2 L 1.00

Schedule 5 M 2.00

4 H

2.33

The contractor will be required to be compliant with all applicable FAA requirements, ISO 9001; 2015 and AFI 10-220 ground operating procedures. The submitted contractor procedures will be reviewed by the Govt during contract transition. Final approval will be executed by the GFR.

Transfer and

Control

AMIC

PM/CO/DRQA

Technical

If the contractor Quality Management System does not adequately assess the quality and safety of services then the

Government will require additional oversight to ensure

Government quality standards are met.

2 M

AMIC

PM/CO/DRQA/GG

Rs

Technical

If the contractor fails to follow established quality standards and provide safe and reliable aircraft then the Government will be exposed to significant operational risk.

3 H

11 CO/PM Programmatic

If the Government fails to establish viable pools of contractors that can perform the requirements, then there may be limited competition at the Task Order level resulting in higher costs and a higher potential for sub-standard performance.

3 M

AMIC

PM/CO/DRQA

Business

If Govt does not have authorizations for dedicated, assigned and adequately trained personnel (GFR/GGR positions) appropriately focused to execute contractor oversight, then

Govt surveillance of contractor flight and ground operations will be ineffective, increasing the likelihood of safety incidents.

1.67Control

The PWS will outline required pilot qualifications and experience levels.

Contractor will be required to provide pilots with qualifications and experience that meet/exceed AFI 10-220. ACC A3T will prescribe the qualification criteria for a contractor ADAIR pilot for inclusion into the

PWS. The GFR has an ongoing responsibility to ensure contractor pilots are qualified. The Government will ensure pilots are operationally ready to conduct flights in their assigned location. The pilots must be knowledgeable and current in local flight operating procedures, be fully briefed on area nuances and ready to safely integrate their flights into the operating location's environment.

14 ACC A3TO/ GFRs Technical

If the contractor fails to provide qualified, experienced pilots, then the Government will be exposed to significant degradation of operational capabilities and delays in mission execution.

2 M

The contractor shall have a Quality Management System compliant with

AS9110 and AFI 10-220 that identifies risk mitigation, safety adherence, PWS/SDS compliance, key personnel compliance with PWS and QMS audit schedule. The Quality Management System will be evaluated in practice as part of the initial contract performance review IAW AFI 63-

138.

2.00

Control

The Government will award task orders with required flight hours and aircraft performance attributes. GFRs, GGRs, the ADAIR PM and CO must monitor sortie/flight mission effectiveness for each task order utilizing assigned Service Summary metrics. The GFR/GGR must initiate

Corrective Action Requests (CAR)s to contractors for any non-conformance.

2.00

Control

Permanently assigned GFR and GGRs is the most effective solution. If feasible, identify and POM for manning authorizations required to perform oversight duties. In the short term identify and acquire appropriate training for Govt pilots and maintenance personnel to perform these duties. This approach can also be the long-term solution but will require leadership focus to ensure oversight duties are effectively executed. AMIC/DRQ, ACC/A3T and ACC/A4 will perform semi-annual surveys of execution of duties.

2.33

Conducted extensive Market Research to include Sources Soughts/RFI, Industry Days, and one-on-one sessions; based on information gained, determined "viable pool" of contractors, which should enable adequate competition for subsequent Task Orders.

2.00Control

Control

10 CO/PM Programmatic

If the Government doesn't ensure adequate liability insurance for the risk of damage or loss to public/Government personnel, facilities, and equipment. Then the Government/contractor may be subject to catastrophic financial loss.

3 H Assume

Contract PWS will be written for contractor to be liable for any and all damages to contractor owned equipment/personnel by securing an insurance policy with coverage limits identified by the Contracting

Officer. The coverage limits will meet all limits in Table 2 of AFI 10-1001, Civil Aircraft Landing Permits. In order to mitigate the risk to

Government/public assets, AFI 10-220 will be utilized as a mandatory compliance document; the Contractor's Flight and Ground Risk clause will not be incorporated into the contract. It is critical that the Govt ensure the GFR, GGR and Aviation Safety Team remain focused in the execution of their duties as outlined in AFI 10-220.

2.33

12 PM/CO/GFR/GGR

Technical

If the contractor fails to sustain mission effectiveness of ADAIR aircraft, then the government training requirements will be negatively impacted.

3 M

Performance 5 M 2.00

Cost 2 L 1.00

Schedule 5 M 2.00

Performance 2 L 1.00

Cost 2 L 1.00

Schedule 2 L 1.00

Performance 2 L 1.00

Cost 2 L 1.00

Schedule 2 L 1.00

1.6715

AMIC

PM/CO/DRQA/GG

Rs

Technical

If the contractor fails to provide trained and qualified ground operations personnel to ensure safe, reliable aircraft, then the

Government will be exposed to significant degradation of ground operational capabilities and delays in mission execution.

2 M Control

Within the PWS, contractors will be required to comply with the requirements of AFI 10-220, the CFR Part 135 and all airworthiness bulletins. All of these documents require the contractor to provide and ensure ongoing training/qualification currency of ground operations personnel. AFI 10-220 requires submission of a Ground Operations Plan

(GOP). The GOP requires contractors to develop/continually utilize a master training plan for personnel to ensure required qualifications/certifications are met. The GGRs will surveil contractor ground operations to verify personnel training and safety of ground operations. The Govt will review submitted contractor GOPs to ensure a thorough approach to ground operations. GGRs will audit contractor procedures during the initial contractor performance review and periodically audit throughout contract execution.

1.00

17 CO/PM Programmatic

If the Government fails to award to companies that understand the complexities involved with the required capabilities, then performance and delivery schedule may be severely impacted.

2 L Control

The Government hosted both an ADAIR Forum and an Industry Day to communicate the requirement and seek Industry input. The

Government also compiled market research data and determine those companies with legitimacy as potential adversay air providers. The

Government will also clearly identify the requirements with the PWS, Appendices and RFP sections L & M and post on FBO. Finally, the

Government will conduct a pre-proposal conference to enhance performance and delivery understanding.

1.00

16 A3TO / AMIC PM Business

If mission requirements result in multiple contractors operating simultaneously at a particular location on-base, then this could significantly stress base infrastructure/support capacity requiring more government effort to ensure effective integration and safety.

3 L Control

The Government must identify clear operating procedures at locations where multiple contractors are likely to perform services simultaneously. The Government's intent is to not utilize multiple contractors at a given location.