CROSS REFERENCE MATRIX FA488721R0003 SABER IDIQ
For Prospective Offerors: See Section L, L.2.1.4. regarding instructions for completion of the solicitation Cross Reference Matrix. If this matrix conflicts with any other requirement, direction, or provision of this solicitation, the other reference shall take precedence over this matrix. Sections L and M references in the matrix are for information purposes only, and the Government shall be obligated to evaluate proposals solely in conformance with the provisions of the Section L and M of the solicitation.
SOLICITATION CROSS REFERENCE MATRIX
| REQ. |
| Requirement Description |
| CLIN |
| Section |
L Section M Proposal Page
Factor 3: Price
| 1 |
| Coefficient, Base Ordering Period Luke AFB & 161st ANG – |
Standard Hours Work
| 2 |
| Coefficient, Base Ordering Period Luke AFB & 161st ANG – |
Non-Standard Hours Work
| 3 |
| Coefficient, Base Ordering Period Gila Bend AF Auxiliary Field |
– Standard Hours Work
| 4 |
| Coefficient, Base Ordering Period Gila Bend AF Auxiliary Field |
– Non-Standard Hours Work
| 5 |
| Coefficient, Base Ordering Period Ft. Tuthill Recreation Center |
– Standard Hours Work
| 6 |
| Coefficient, Base Ordering Period Ft. Tuthill Recreation Center |
– Non-Standard Hours Work
| 7 |
| Coefficient, Option Year 1 Luke AFB & 161st ANG |
– Standard Hours Work
| 8 |
| Coefficient, Option Year 1 Luke AFB & 161st ANG |
– Non-Standard Hours Work
| 9 |
| Coefficient, Option Year 1 Gila Bend AF Auxiliary Field |
– Standard Hours Work
| 10 |
| Coefficient, Option Year 1 Gila Bend AF Auxiliary Field |
– Non-Standard Hours Work
Attachment 8- FA488721R0003 Solicitation Cross Reference Matrix 28 October 202011 January 2021
| 11 |
| Coefficient, Option Year 1 Ft. Tuthill Recreation Center |
– Standard Hours Work
| 12 |
| Coefficient, Option Year 1 Ft. Tuthill Recreation Center |
– Non-Standard Hours Work
| 13 |
| Coefficient, Option Year 2 Luke AFB & 161st ANG |
– Standard Hours Work
| 14 |
| Coefficient, Option Year 2 Luke AFB & 161st ANG |
– Non-Standard Hours Work
| 15 |
| Coefficient, Option Year 2 Gila Bend AF Auxiliary Field |
– Standard Hours Work
| 16 |
| Coefficient, Option Year 2 Gila Bend AF Auxiliary Field |
– Non-Standard Hours Work
| 17 |
| Coefficient, Option Year 2 Ft. Tuthill Recreation Center |
– Standard Hours Work
| 18 |
| Coefficient, Option Year 2 Ft. Tuthill Recreation Center |
– Non-Standard Hours Work
Subfactor 1: Bonding Capacity
Subfactor 2: Luke Seed Project
Subfactor 3: Management Approach
| 22 |
| Factor 2: Past Performance |
Luke AFB SABER Seed Project Price Proposal
| 234 |
| Complete SF1442, Blocks 14, 15, 17, 19, 20A, 20B, 20C, 30A, 30B, |
30C, all fill-ins and Reps and Certs
| 254 |
| Attachment 8 – Solicitation Cross Reference Matrix |
L.2.1.4.