Attachment 4 - Price Evaluation Worksheet - 23Oct20.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- SABER Construction Services IDIQ
- Solicitation number
- FA488721R0003
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TAB 1 - Weighted Coefficients
| FA488721R0003 Attachment 4 | ||||
| PRICE EVALUATION WORKSHEET | ||||
| Simplified Acquisition of Base Engineer Requirements (SABER) Contract | ||||
| Luke AFB and 161st ANG | ||||
| CLIN | Item Description | Weight Based on Historical Data | Proposed Coefficient | Weighted Value Result |
| 0001AA- Base Ordering Period 1001AA- Option Year 1 2001AA- Option Year 2 | Luke/161st ANG - Standard Hours | 79% | 0.000 | |
| 0001AB- Base Ordering Period 1001AB- Option Year 1 2001AB- Option Year 2 | Luke/161st ANG - Non-Standard Hours | 8% | 0.000 | |
| SUBTOTAL WEIGHTED COEFFICIENT RATE | 87% | 0.000 |
| Gila Bend Auxiliary Field | ||||
| CLIN | Item Description | Weight Based on Historical Data | Proposed Coefficient | Weighted Value Result |
| 0002AA- Base Ordering Period 1002AA- Option Year 1 2002AA- Option Year 2 | Gila Bend Auxiliary Field - Standard Hours | 6% | 0.000 | |
| 0002AB- Base Ordering Period 1002AB- Option Year 1 2002AB- Option Year 2 | Gila Bend Auxiliary Field - Non-Standard Hours | 1% | 0.000 | |
| SUBTOTAL WEIGHTED COEFFICIENT RATE | 7% | 0.000 |
| Ft Tuthill Receration Center, Flagstaff AZ | ||||
| CLIN | Item Description | Weight Based on Historical Data | Proposed Coefficient | Weighted Value Result |
| 0003AA- Base Ordering Period 1003AA- Option Year 1 2003AA- Option Year 2 | Ft Tuthill - Standard Hours | 5% | 0.000 | |
| 0003AB- Base Ordering Period 1003AB- Option Year 1 2003AB- Option Year 2 | Ft Tuthill - Non-Standard Hours | 1% | 0.000 | |
| SUBTOTAL WEIGHTED COEFFICIENT RATE | 6% | 0.000 | ||
| 100% | ||||
| NOTE: Fill-in highlighted boxes only; data to correspond with offerors proposed prices as inserted within the bid schedule. The coefficient shall be no further out than to the thousandths (0.000). Transfer subtotal weighted coefficient rate to the Total Evaluated Price Tab. |
Tab 2 - Total Evaluated Price
| FA488721R0003 Attachment 4 | |||||
| PRICE EVALUATION WORKSHEET | |||||
| Simplified Acquisition of Base Engineer Requirements (SABER) Contract | |||||
| Equation: (For Evaluation Purposes Only!) | |||||
| Luke AFB Price = $37,000,000 x Luke AFB Weighted Coefficient | |||||
| Gila Bend & Goldwater Range Price = $37,000,000 x Gila Bend & Goldwater Range Weighted Coefficient | |||||
| JBAB Price = $37,000,000 x JBAB Weighted Coefficient | |||||
| Luke & 161st ANG + Gila Bend & Goldwater Range + Ft Tuthill Price = Total Evaluated Price | |||||
| Instructions to Offerors: The weighted coefficient rates will be evaluated. Fill-in highlighted boxes only; data to correspond with offerors proposed prices as inserted within the bid schedule. The coefficient shall be no further out than to the thousandths (0.000). | |||||
| Estimate Aggregate Total Over All Periods and Options | Subtotal Weighted Coefficient Rates | Evaluated Total(s) | |||
| Luke + 161st ANG | $37,000,000.00 | X | 0.000 | = | $0.00 |
| Gila Bend + Goldwater Range | $37,000,000.00 | X | 0.000 | = | $0.00 |
| Ft Tuthill - Flagstaff AZ | $37,000,000.00 | X | 0.000 | = | $0.00 |
| Total Evaluated Price: | $0.00 | ||||
| *Estimate Aggregate per location is for evaluation purposes only & is non-binding. |
Tab 3 - Coefficient Development
| FA488721R0003 Attachment 4 | |||
| PRICE EVALUATION WORKSHEET | |||
| Simplified Acquisition of Base Engineer Requirements (SABER) Contract | |||
| Basis for Development of the Coefficient | Percentage of Coefficient for Luke AFB & 161st ANG | Percentage of Coefficient for Gila Bend | Percentage of Coefficient for Ft. Tuthill |
The coefficient shall cover all items including all general conditions, profit, overhead, bonds, taxes, insurance, administrative/technical support and labor burden for the prime Contractor’s office staff and workforce. Bond costs shall be included in the coefficient and bonds will be required for each Task Order IAW FAR 28.
| General Conditions |
| Profit |
| Overhead |
| Bonds |
| Taxes |
| Insurance |
| Administrative/Technical Support |
| Labor Burden - Prime Contractor |
| Total Coefficient |
NOTE: Offerors shall identify cost elements that compose the total coefficient for each area of work. The above elements are included as a reference, but can be edited as necessary based on each offeror's coefficient pricing.