48 - Example SABER Design Intent Drawing Sets_28 Nov.pdf

PDF 8 MB Posted

Attached to
SABER IDIQ
Solicitation number
FA486125R0003
Issued by

About this file

The SABER Design Intent Drawing Set is a comprehensive architectural and engineering document that provides detailed design drawing requirements for projects at Nellis Air Force Base. The document outlines two levels of design submission (Level 1 and Level 2) with specific drawing requirements across multiple disciplines, including civil, architectural, structural, mechanical, electrical, plumbing, fire protection, and telecommunications systems.

For each discipline, the document specifies the required drawing components, such as cover sheets, floor plans, notes, symbols, abbreviations, schedules, equipment details, and system layouts. The drawings must progressively increase in detail from Level 1 to Level 2, with Level 2 requiring more comprehensive documentation including single-line diagrams, equipment schedules, utility metering, grounding plans, and detailed route specifications for underground cables and communication infrastructure. The document is specifically for the SABER Contract and focuses on standardizing design intent drawings for construction projects at Nellis Air Force Base in Nevada.

View the file

Other files

File Type Posted
51_RFI Log_ SABER Seed RKMF 2400010 Reno Honor Guard 99 FSS B10250.xlsx XLSX spreadsheet
45 - Attachment Contract Information Sheet.pdf PDF
44 - SABER SOO RKMF240010 Renovate Honor Guard 99 FSS B10250_14Feb2025.pdf PDF
36 - AF 3000 Material Approval Submittal - 01 Sep 2003.pdf PDF
33 - AF Form 3065 Progress Report Template - 01 Apr 1996.pdf PDF
30 - AF Form 103 Base Civil Engineering Work Clearance Request - 01 Aug 1994.pdf PDF
28 - Nuclear Gauge Form 1.xlsx XLSX spreadsheet
22_RUS Bulletin 1728F-806 UG Main VEA Standard - 18 October 2018.pdf PDF
20_UT1-UT5 Modified Trenching Drawing - Aug 2016.pdf PDF
15 - Hazardous Material Management Guidance Document 2023-06-03.pdf PDF
14_ACC Sole Source EMCS Letter.pdf PDF
10_Nellis-Creech Utility Meter Req 2019-09-13.pdf PDF
2 - Price Schedule 23 September 25.pdf PDF
52 - 99 SFS - Mass Pass Request Template.xlsx XLSX spreadsheet
Atch 50_RFI Log_General Solicitation and Non-SABER Seed Related Questions.xlsx XLSX spreadsheet
42 - General Decision Number NV20240001 Bldg NTTR.pdf PDF
40 - General Decision Number NV20240058 Highway Clark County.pdf PDF
31 - AF Form 3052 Cost Estimate Template.xlsx XLSX spreadsheet
24_UG3.3 Three Phase Six Bushing Pad-mounted Transformer - Aug 2016.pdf PDF
18 - Nellis Supplement to DAFI 31-218 Motor Vehicle Traffic Supervision - 23 Mar 2023.pdf PDF
17 - Installation Plan 12 - Hazardous Waste Management Plan 27 Sep 23.pdf PDF
16_USAF Integrated Cultural Resources Mgmt Plan 32-7065 ICRMP - 06 Nov 2019.pdf PDF
9_Nellis-Creech Mech-Plumb Req 2020-07-07.pdf PDF
8_Nellis-Creech Lighting Req 2019-01-22.pdf PDF
49 - As-Builts.pdf PDF
47 - Example SABER Design Intent Drawing Set Level 2_20 Nov.pdf PDF
41 - General Decision Number_NV20240038 Building Clark County.pdf PDF
39 - Form SS-PER-007-003 Internal Combustion Engine Worksheet.pdf PDF
37 - BUILDER Inventory Sheet.xlsx XLSX spreadsheet
35 - AF 66 Schedule of Material Submittals.xlsx XLSX spreadsheet
32 - AF 3064 Progress Schedule Template - 01 Apr 1996.xlsx XLSX spreadsheet
27 - NTTR Visit Request - 27 Jan 2023.pdf PDF
25 - UH1.2 - Grounding Assembly for Pad-mounted Transformers and Enclosures 2 Rods - Aug 2016.pdf PDF
19_UF3.PC Concrete Pad for Three Phase Requirement - Aug 2016.pdf PDF
13 - Work Clearance Triggers.pdf PDF
6 - Nellis-Creech Comm Req NC 2710 - Jun 2023.pdf PDF
3 - Self Score Worksheet SABER_23 Sept 2025.xlsx XLSX spreadsheet
34 - Schedule of Values Template.xlsx XLSX spreadsheet
1 - SABER SOW 25 Sep 25.pdf PDF
23_Power Trench Sand and Backfill Requirements - Apr 2013.pdf PDF
Solicitation - FA486125R0003.pdf PDF
46 - Example SABER Design Intent Drawing Set Level 1_20 Nov.pdf PDF
43 - General Decision Number_NV20250024 Heavy Clark County.pdf PDF
38_NTTR Automated Information System _AIS_ Equipment Form.pdf PDF
29 - Nuclear Gauge Form 2.docx DOCX document
26 - Connection Charge Agreement - 22 Feb 23.pdf PDF
21_US3.PJ Single and Three Phase Primary Junctions - Aug 2016.pdf PDF
12 - Env Permit-ATP Guidance 2023.pdf PDF
11_Nellis-Creech Plant List.pdf PDF
7 - Nellis-Creech Electrical Req 2023-10-17.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SABER Design Intent Drawing Set

SABER DESIGN INTENT DRAWING SET – LEVEL 1

The following serves as a supplement to the Statement of Work (SOW) to outline the Nellis AFB requirements for design drawings required under the SABER Contract. An acceptable level 1 design submission shall reflect the final basic plan with sufficient detail to illustrate (as applicable) the structural, architectural, mechanical, electrical, fire and communications systems as well as the paving/grading/drainage plan, haul route and proposed storage site, designed to level 1 definition. Drawings shall include detailed schedules and legends appropriate to describe the design, as well as be of sufficient detail to fully communicate the design concept. Drawings for level 1 shall include all applicable drawings from the following list and any additional required to fully illustrate the work.

Cover Sheet and Drawing Index

• Project number and full project name

• Contract and task order number

• Date drawings were issued

• Name of the Contractor, DOR, and other agencies involved

• Drawing index outlining all sheets in the drawing set

Level 1 Cover Sheet Example

Haul Route and Contractor’s Storage Site

• Haul route from entrance onto base to location of project

• Project site location with laydown yard for equipment storage

Level 1 Haul Route Example

Civil Drawings

• General notes

• Existing conditions, elements, and areas to be demolished; all applicable exterior and interior features

• New construction and exterior work

• Building location and orientation

• Airfield runways, taxiways, ramps, streets, roads, walks, and parking

• Exterior utilities beyond five feet (5’) building line

• Landscape plan and plant schedule

Level 1 General Civil Notes Example

Level 1 Demolition Plan Example

Level 1 Civil Plan Example

Level 1 Utility Plan Example

Architectural Drawings

• General notes, symbol list, and abbreviations

• Overall key floor plan with room legend

• Interior finish schedules

• Architectural features

Level 1 Architectural Symbols, Abbreviations, and Notes Example

Level 1 Floor Plan Example

Level 1 Interior Finish Schedules Example

Plumbing Drawings

• Symbol list and abbreviations

• Floor plan – system layout, tie-in to supporting utilities

Level 1 Plumbing Symbol List and Abbreviations Example

Level 1 Plumbing Floor Plan Example

Mechanical (Heating, Ventilation, Air Conditioning, Refrigeration) Drawings

• General notes and symbol list

• Floor plan – system layout, tie-in to supporting utilities

Level 1 Mechanical Legend and Abbreviations Example

Level 1 Mechanical Notes Example

Level 1 Mechanical Floor Plan Example

Electrical Drawings

• General notes and symbols

• Floor plan with fixture location, circuiting, switching, convenience outlets-electrical service to equipment, and existing power panels

Level 1 Electrical Notes and Symbols Example

Level 1 Electrical (Lighting) Floor Plan Example

Level 1 Electrical (Power) Floor Plan Example

Telecommunication Drawings

• Symbol list and abbreviations

• Overall floor plan

• Details of OSP routes

• Location of all cable terminations

• Notes shall include all equipment being provided by the Contractor

Level 1 Telecommunication Symbols and Abbreviations Example

Level 1 Telecommunication Floor Plan Example

Level 1 OSP Route/Riser Diagram Example

SABER DESIGN INTENT DRAWING SET – LEVEL 2

The following serves as a supplement to the Statement of Work (SOW) to outline the Nellis AFB requirements for design drawings required under the SABER Contract. An acceptable level 2 design submission shall automatically incorporate all requirements/levels/aspects of the level 1 design requirements and reflect the final basic plan with sufficient detail to illustrate (as applicable) the structural, architectural, mechanical, electrical, fire and communications systems as well as the paving/grading/drainage plan, haul route and proposed storage site, designed to a level 2 definition. Major mechanical and electrical equipment items shall be shown on the drawings with single line diagrams, and all utilities and structures shall be shown.

Drawings shall include detailed schedules and legends appropriate to describe the design, as well as be of sufficient detail to fully communicate the design concept. Drawings for a level 2

Design shall include all applicable drawings from the following list and any additional required to fully illustrate the work.

Cover Sheet and Drawing Index

• Project number and full project name

• Contract and task order number

• Date drawings were issued

• Name of the Contractor, DOR, and other agencies involved

• Drawing index outlining all sheets in the drawing set

Level 2 Cover Sheet Example

Haul Route and Contractor’s Storage Site

• Haul route from entrance onto base to location of project

• Project site location with laydown yard for equipment storage

Level 2 Haul Route Example

Civil Drawings

• General notes

• Existing conditions, elements, and areas to be demolished; all applicable exterior and interior features

• New construction and exterior work

• Building location and orientation

• Airfield runways, taxiways, ramps, streets, roads, walks, and parking, including subsurface

• Exterior utilities beyond five feet (5’) building line. Details of connection into existing utilities

• Landscape plan and plant schedule

Level 2 General Civil Notes Example

Level 2 Demolition Plan Example

Level 2 Civil Plan Example

Level 2 Utility Plan Example

Structural Drawings

• General notes, symbols, and abbreviations

• Foundation plan with column locations

Level 2 Structural Abbreviations Example

Level 2 Structural Notes Example

Level 2 Foundation Plan Example

Architectural Drawings

• General notes, symbol list, and abbreviations

• Overall key floor plan with room legend

• Roof plan with slopes

• Reflected ceiling plan

• Interior and exterior elevations

• Interior finish schedules

• Door and window schedules

• Hardware schedule

• Exterior building elevations

• Architectural features

Level 2 Architectural Notes, Symbol List, Abbreviations Example

Level 2 Floor Plan Example

Level 2 Roof Plan Example

Level 2 Reflected Ceiling Plan

Level 2 Exterior Elevations Example

Level 2 Exterior Elevations Example

Level 2 Interior Elevations Example

Level 2 Door, Window, and Hardware Schedules Example

Level 2 Interior Finish Schedules Example

Fire Protection Drawings

• Fire Alarm/Mass Notification System notes, symbol list, and abbreviations

• Floor plan and riser diagram indicating arrangement of automatic sprinkler system, smoke and/or heat detectors, and alarm systems provided by the Contractor in areas applicable to the task order

• Typical device details

• Schedule of fire resistance ratings for fire walls, interior partitions, and fire doors

Level 2 Fire Alarm and Mass Notification System Notes and Symbols Example

Level 2 FA/MNS Floor Plan Example

Level 2 FA/MNS Device Details Example

Level 2 FA/MNS Riser Diagram Example

Level 2 Fire Sprinkler System Layout Example

Plumbing Drawings

• Symbol list and abbreviations

• Floor plan – system layout, tie-in to supporting utilities

• Key details

• Fixture and equipment schedules

Level 2 Plumbing Symbol List and Abbreviations Example

Level 2 Plumbing Floor Plan Example

Level 2 Plumbing Fixtures and Equipment Schedules and Details Example

Mechanical (Heating, Ventilation, Air Conditioning, Refrigeration) Drawings

• General notes and symbol list

• Floor plan – system layout, tie-in to supporting utilities

• Equipment details

• Fixture and equipment schedule

• System controls and utility metering

Level 2 Mechanical Legend and Abbreviations Example

Level 2 Mechanical Notes Example

Level 2 Mechanical Floor Plan Example

Level 2 Mechanical Equipment Details Example

Level 2 Mechanical Fixture and Equipment Schedule Example

Level 2 System Controls and Utility Metering Example

Electrical Drawings

• General notes and symbol list

• Floor plan with fixture location, circuiting, switching, convenience outlets-electrical service to equipment, and existing power panels

• Grounding and lightning protection plan

• Electrical details, mountings, tie-in to existing, and supporting utilities

• Panel board schedules for items being provided by the Contractor

• Single line and electrical riser diagram for areas applicable to the task order

• Fixture and equipment schedules for items being provided by the Contractor

Level 2 Electrical Notes and Symbol List Example

Level 2 Grounding Plan Example

Level 2 Electrical (Lighting) Floor Plan Example

Level 2 Fixture and Equipment (Lighting) Schedule Example

Level 2 Electrical (Power) Floor Plan Example

Level 2 Electrical Riser Diagram and Panel Schedule Example

Level 2 Fixture and Equipment (Feeder) Schedule Example

Level 2 Single Line Diagram Example

Telecommunication Drawings

• Symbol list and abbreviations

• Overall floor plan

• Details of OSP routes. Specify exact route of underground cable

• Location of all cable terminations

• Telecommunications OSP and riser diagrams

• Notes shall include all equipment being provided by the Contractor

• Details of all wire ways and cable tray(s)/support locations

• Details of all grounding systems, points, and connections IAW codes/standards

• Electrical, structural, architectural, mechanical, fire protection, and other systems required to support communications infrastructure, IAW codes shall be included in those respective design sheets

• Identified labels for each termination and cable

• Details of wiring and components showing compliance with TIA/EIA-568 o Equipment support frame o Connector blocks, cable guides, and patch panels o Optical fiber distribution panels o Telecommunications outlet/connector assemblies o Alarm circuits, access controls, & IDS o Critical communication facilities and nodes o Location of equipment cabinets/racks

Level 2 Telecommunication Symbol List and Abbreviations Example

Level 2 Telecommunication Floor Plan and Notes Example

Level 2 OSP Route/Riser Diagram Example

Level 2 OSP Route Underground Cable Example

Level 2 OSP Route Underground Cable Example Continued

Level 2 Telecommunications Riser Diagram Example