Summary of Changes Memorandum.pdf

PDF 258 KB Posted

Attached to
Modernize Electrical and HVAC Redundancy
Solicitation number
FA4855-20-R-0012
Issued by

About this file

This document provides details for a firm-fixed-price solicitation from the Department of the Air Force Special Operations Command seeking offers for a project to modernize electrical and HVAC redundancy at Cannon Air Force Base. The project calls for establishing a redundant electrical power system, replacing two 200-ton primary chillers with air-cooled units, and installing dedicated HVAC for ground control station bays. The electrical work includes upgrading power to the facility via the transformer and setting up dual systems to permit independent operations on either side of the bays. The HVAC work creates a fully redundant system for the bays. The period of performance is 570 calendar days for a project valued between $5-10 million. The solicitation utilizes Lowest Price Technically Acceptable procedures and has a total small business set-aside in accordance with FAR 19.502-2. Offers are due by the date specified in the attached solicitation.

View the file

Other files

File Type Posted
(Updated) Questions and Answers 24 August 2020.pdf PDF
Final Questions and Answers 18 August 2020.pdf PDF
Site Visit Photo 009.JPG JPG image
Site Visit Photo 007.JPG JPG image
Site Visit Photo 003.JPG JPG image
Site Visit Photo 008.JPG JPG image
Site Visit Photo 006.JPG JPG image
Site Visit Photo 004.JPG JPG image
Site Visit Photo 002.JPG JPG image
List of Site Visit Attendees.pdf PDF
Site Visit Photo 0010.JPG JPG image
Site Visit Photo 001.JPG JPG image
Site Visit Photo 0011.JPG JPG image
Site Visit Photo 005.JPG JPG image
Attachment 12- 100 percent Drawings 31 July 2020.pdf PDF
Solicitation Amendment 0001 (FA4855-20-R-0012-0001).pdf PDF
Attachment 11- 100 percent Specifications 31 July 2020.pdf PDF
Questions and Answers 7 August 2020.pdf PDF
Questions and Answers 4 August 2020.pdf PDF
Questions and Answers 30 July 2020.pdf PDF
Appendix C2. AF Form 3064 Progress Schedule (SOW Appendix).xlsx XLSX spreadsheet
Attachment 4-Wage Determination 24 January 2020.pdf PDF
Appendix D5. AEC CAD Standards (SOW Appendix).pdf PDF
Appendix C1. DD Form 1354 (SOW Appendix).pdf PDF
Attachment 1- Statement of Work 17 July 20.pdf PDF
Appendix D6. As-built Submittal Guidelines (SOW Appendix).pdf PDF
Solicitation FA4855-20-R-0012.pdf PDF
Attachment 2- 95 percent Specifications 17 June 2020.pdf PDF
Attachment 5 - Past Performance Information Sheet 17 July 2020.docx DOCX document
Appendix C3. AF Form 3065 Progress Reports (SOW Appendix).xlsx XLSX spreadsheet
Appendix D1. Contractor Base Briefing Pamphlet (SOW Appendix).pdf PDF
Attachment 3- 95 percent Drawings 17 June 2020.pdf PDF
Attachment 7- WBS 8 July 2020.xlsx XLSX spreadsheet
Attachment 9 - Past Performance Cover Letter 08 July 2020.pdf PDF
Attachment 10 - Consent Form 17 July 2020.pdf PDF
Appendix D3. Fire Protection Fire Prevention (SOW Appendix).pdf PDF
Appendix D2. Architectural Compatibility Guide (SOW Appendix).pdf PDF
Attachment 8- RESERVED 17 July 2020.pdf PDF
Attachment 6 - Past Performance Questionnaire 17 July 2020.docx DOCX document
Appendix D4. COMM Labeling Standards (SOW Appendix).pptx PPTX presentation
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

27TH SPECIAL OPERATIONS CIVIL ENGINEER SQUADRON (AFSOC)

CANNON AIR FORCE BASE NEW MEXICO

AIR COMMANDOS

MEMORANDUM FOR 27 SOCONS/PKB

FROM: Ms. Sherrie Nymeyer, 27 SOCES/CENM

SUBJECT: Summary of Changes from 95% to 100% Drawings on Modernize HVAC and Electrical Redundancy, B848

1. The purpose of this memorandum is to summarize updates from the 95% product which was released during solicitation (dated 17 June 2020), and the 100% Issued For Construction (IFC) set (dated and stamped on 31 July 2020). This memo is intended only as a summary and does not detail each addition, deletion, or modification to the drawings. The offerer shall review the respective drawing sheets to see the full extent of changes.

2. Summarized changes are as follows:

G005 – Phasing Notes have been updated/added. KeyNotes have been updated/added.

A101 – KeyNotes have been updated. For Electrical Room 132: the door between Room 132 and the corridor has been removed; the door between UPS Room 127 and 132 has been removed;

construction standards for wall between Room 132 and corridor as well as wall between Room 132 and Room 133 has changed. See KeyNotes for specifics.

A501 – Door Schedule and Materials Finish Legend has been updated. Details 3, 4 and 5 have been updated.

A502 – All Wall Types have been updated.

XM101 – General Notes have been updated/added. KeyNotes have been updated/added.

XM102 – General Notes have been added.

M101 – General Notes have been added. KeyNotes have been updated/added.

M102 – General Notes have been added.

M103 – General Notes have been added. KeyNotes have been updated/added.

M104 – General Notes have been added. KeyNotes have been updated/added.

M401 – General Notes have been added. KeyNotes have been updated/added. Added Typical GCS Room Section.

M501 – Detail 2 has been updated. Detail 5 for Glycol Makeup Unit has been added.

M601 – Computer Room Air Handling Unit Schedule has been updated. Added: Air Separator Schedule; Glycol Makeup Schedule; Diffuser, Register and Grille Schedule.

M602 – Split System Control-SS-A has been updated.

E101 – General Notes have been added.

E102 – General Notes have been updated/added.

E103 – General Notes have been updated/added. Key Notes have been updated/added.

E104 – General Notes have been updated/added. Key Notes have been updated. Electrical Plan 1st Floor Area “D” has been updated.

E105 – General Notes have been updated/added.

E401 – Enlarged Plan detail 1 has been updated. General Notes have been updated/added. Key Notes have been updated/added.

E501 – Grounding Diagram detail 4 has been updated.

AIR COMMANDOS

E601 – Existing One Line Diagram has been updated.

E611 – Proposed One Line Diagram has been updated.

E612 – KeyNotes have been updated/added. Proposed One Line Diagram has been updated.

E613 – KeyNotes have been updated/added. Proposed One Line Diagram has been updated.

E614 – Proposed One Line Diagram has been updated.

E615 – KeyNotes have been updated. Proposed One Line Diagram has been updated. Proposed Circuit Breaker Settings has been added along with associated notes.

FA101 – General Note has been added.

FA102 – General Note has been added.

FP101 – General Note has been added.

FP102 – General Note has been added.

2. This summary of changes does not relieve the offeror of any responsibility to review the 100% IFC set in its entirety. In addition, refer to the 100% stamped Specifications for the most up-to-date information associated with the final design product.