Consolidated Q-A3.pdf

PDF 132 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER) Federal contract opportunity
Solicitation number
FA4830-23-R-0001
Issued by
Department of the Air Force Air Combat Command

About this file

This document contains consolidated questions and answers regarding Solicitation Number FA4830-23-R-0001 for the Simplified Acquisition of Base Engineering Requirements (SABER) contract from the Department of the Air Force Air Combat Command. The questions and answers clarify that no design work is required for the seed project referenced in the solicitation. An amendment will be issued to remove references to mechanical, electrical, structural, fire protection, life safety, and energy drawings and design from the solicitation language. Additionally, the amendment will specify that offerors should not include the 1.95% eGordian fee in their proposed coefficients, as the fee will be added separately to task orders awarded under the SABER contract.

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition of Base Engineering Requirements (SABER), newest first.
File Type Posted
2. Summary of Changes_Atch 1_Amend02.pdf PDF
1. SF30_Amend02_FA483023R0001.pdf PDF
Atch 3_SABER Pre-Prop Conf Slides.pdf PDF
SABER Pre-Proposal Conference Minutes.pdf PDF
RFP Atch 3a - B326 Floor Plan 1.pdf PDF
RFP Atch 4 - Wage Determination.pdf PDF
Atch 2_Consolidated Q-A1 (Site Visit).pdf PDF
RFP Atch 3 - Seed Project SOW QSEU 20-0171.pdf PDF
RFP Atch 5 - Base Pass Template.pdf PDF
RFP Atch 6 - AF Form 66.xlsx XLSX spreadsheet
RFP Atch 11 - Subcontractor Consent Ltr.docx DOCX document
RFP Atch 12 - SABER Ordering Guide.pdf PDF
RFP FA483023R0001.doc.pdf PDF
RFP Atch 1 - SABER Specifications.pdf PDF
RFP Atch 2 - MAFB A-E Design Guide.pdf PDF
RFP Atch 3b - B326 Floor Plan 2.pdf PDF
RFP Atch 8 - PPPI.docx DOCX document
Atch 1_Pre-Prop_Site Visit Attend Sheet.pdf PDF
RFP Atch 7 - PPQ.docx DOCX document
RFP Atch 9 - Q - A Form.docx DOCX document
RFP Atch 10 - Client Authorization Ltr.docx DOCX document
Amendment Atch 2_Consolidated Q-A2.pdf PDF
RFP Atch 1_(Rev1) SABER Specifications.pdf PDF
SF30_FA483023R00010001.pdf PDF
Amendment Atch 1_Summary of Changes.pdf PDF
RFP Atch 3_(Rev1) Seed Project SOW QSEU 20-0171.pdf PDF
RFP Atch 3c_Bldg 326 Furniture Inventory.pdf PDF
RFP Atch 12_(Rev1) SABER Ordering Guide.pdf PDF
Site Visit Pre-Registration Form.docx DOCX document
RFP Atch 1 - SABER Specifications.pdf PDF
RFP Atch 3 - Seed Project SOW QSEU 20-0171.pdf PDF
RFP Atch 4 - Wage Determination.pdf PDF
RFP Atch 6 - AF Form 66.xlsx XLSX spreadsheet
RFP Atch 8 - PPPI.docx DOCX document
RFP Atch 12 - SABER Ordering Guide.pdf PDF
RFP Atch 2 - MAFB A-E Design Guide.pdf PDF
RFP Atch 3a - B326 Floor Plan 1.pdf PDF
RFP Atch 7 - PPQ.docx DOCX document
RFP Atch 10 - Client Authorization Ltr.docx DOCX document
RFP Atch 3b - B326 Floor Plan 2.pdf PDF
Pre-Proposal_Site Visit Invite.pdf PDF
RFP FA483023R0001.doc.pdf PDF
RFP Atch 5 - Base Pass Template.pdf PDF
RFP Atch 9 - Q - A Form.docx DOCX document
RFP Atch 11 - Subcontractor Consent Ltr.docx DOCX document
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4830-23-R-0001

Consolidated Q&A 3

K – Contracting C – Cost/Pricing T- Technical P – Past Perf.

Solicitation Reference

Question/Comment

Government Response (Govt Use Only)

Resulted in change in

RFP? (Y/N)

(Govt Use

Only)

Change Reference

(Govt Use Only)

T-001

RFP FA483023R0001 –

L-4.3.1.1(a) Scope of Work (pg. xx)

In Q&A #2, the answer provided for T-008 states, “The government confirms that there is no design scope for mechanical, electrical, structural, fire protection, life safety, or energy as part of this project.” However, in Amendment 0001, Section L-4.3.1.1(a) Scope of Work, the following is mentioned:

“ii. Provide the drawings describing a preliminary design, including basic layout and planning of work, and at a minimum, the following components: mechanical, electrical, structural, fire protection, life safety, and energy.

iii. Provide design calculations to substantiate appropriate equipment or material selection/sizing, component assembly, and proposed labor and sizing of utilities and structural elements (e.g. mechanical, electrical, structural, fire protection, life safety, and energy) in compliance with the Seed Project SOW (Attachment 3).”

What drawing/design information is needed for the proposal?

The government re-confirm that there are no design requirements for the seed project. To correct the discrepancies, Section L- 4.3.1.1(a), Scope and Section M-3.1.1, Subfactor 1: Execution of Moody AFB Seed Project, Table, will be revised, via Amendment 0002, as follows:

L-4.3.1.1 Provide a preliminary work plan to demonstrate coordination efforts among the different trades/subcontractors, the sequencing of construction, and the implementation of roles and responsibilities of the key personnel.

(a) Scope of Work – Provide a written narrative summarizing, explaining, and documenting the processes anticipated to successfully fulfil the requirements of the seed project from task order award to final acceptance. Identify the different trades and subcontractors and demonstrate how each will coordinate work to show a fluid sequence and minimize down-time or delay. The narrative should clearly define the roles and responsibilities of all key personnel and show how each will implement their responsibilities.

M-3.1.1 The standard is met when the proposed work plan demonstrates the offeror’s technical understanding and capability for successfully executing and completing the seed project IAW the Seed Project SOW and the proposal provides:

(a) Efficiently, logically, and sufficiently detailed narrative summarizing, explaining, and documenting the preliminary work plan processes to address offeror’s technical approach.

Y

Amendment 0002:

L-4.3.1.1(a), Scope of Work & M-3.1.1, Subfactor 1:

Execution of

Moody AFB Seed Project, Table

K-001

RFP FA483023R0001 –

Section L-6.3.2(a) Coefficient Rates (pg. xx)

In Section L-6.3.2(a), you do not call out the Gordian Fee of 1.95% that you have in response to question 3 that is mentioned in “Consolidated Q&A 1 (Site Visit).”

My question is, do you mean for all contractors to carry the 1.95% in their coefficient?

Please refer to the answer provided in Consolidated Q&A1, Question #3. The eGordian fee will be added to each task order as a separate line item. In other words, the SABER contractor does not absorb the fee cost. Rather, the contractor is simply passing the cost to the government on each task order they receive after the contract award. Therefore, the eGordian fee is applicable to the SABER awardee only. For the purpose of developing coefficient at the source selection level, the offeror should not be concerned with the fee and should not include the eGordian fee in the proposed coefficient.

To ensure clarity, the following will be added, via Amendment 0002, to Section L-6.3.2, Coefficient Rates:

The offerors shall not include the eGordian fee into the proposed coefficient. Only the selected SABER awardee will include the eGordian fee as a separate line-item in each task order cost proposal.

Y Amendment 0002:

L-6.3.2, Coefficient

Rates