APPENDIX 4.5
OVER AND ABOVE PROJECT DESIGN AND CONSTRUCTION MANAGEMENT
PRICING TABLE
For projects considered over and above the contract threshold during the fiscal year, the following not-to-exceed (NTE) percentages will be used to calculate the fee.
I. Design Only Services:
a. Over the contract threshold:
In-House Design Levels NTE
100% 6% of PA w/ ODC to be negotiated 15-35% 6% of PA w/ ODC to be negotiated
Outside A-E Firm Design Level NTE Up to 100% 6% of PA w/ ODC to be negotiated
b. Over the contract threshold:
COE Managed Project Design Level NTE
Up to 100% .03% of PA
c. Additional design services that will be negotiated on a project by project basis:
Site Inspections Soil Boring Asbestos/LBP testing Soil Environmental Samples Water Sampling Environmental Permits
II. Construction Management:
a. Over the contract threshold:
PROJECT TYPE NTE
O&M 2% of PA to be negotiated MILCON 1% of PA to be negotiated
b. For COE managed projects, the Contractor will be paid five hours per week x # of weeks x $$ per hour for Senior Construction Management Engineer. The five hours per week will be adjusted for problem projects on a negotiated basis. The # of weeks is the number of weeks requiring Contractor surveillance in the FY, based on construction schedule.